Power Control and Automation

How power systems are controlled: PLC and PMS, generator synchronising and load sharing, transfer logic, load shedding, black start and SCADA.

In short. Automation decides how a power system behaves when nobody is watching. It decides which generators start, how they synchronise and share load, when load is shed and restored, how transfers happen, and what operators see. Good control design is layered: protection acts first and independently, automatic control follows, and supervision sits on top. Every layer must fail safe and be tested against its written sequence.

Who this section is for: For consultants, control engineers and facility managers specifying or upgrading generator, transfer and power management controls.

Key facts

  • Protection must not depend on the control system.
  • Write the sequence of operation before choosing hardware.
  • Synchronising and load sharing need matched governors and regulators.
  • Control power must survive the outage it is managing.
  • Alarms need priorities and defined responses.
  • Test every sequence at the factory and again on site.

How this section is organised

GroupQuestions it answersStart with
ArchitectureWhich layers and controllers?Control hierarchy
Generator plant controlStart, sequence and share loadSequencing and dispatch
SynchronisingWhen is it safe to close?Automatic synchronising
TransfersMains, generator and tie switchingChangeover logic
Load control and recoveryShed, restore, island, black startLoad-shedding logic
Battery and hybrid controlCharge, discharge and dispatchHybrid dispatch
SupervisionWhat operators see and doSupervisory systems
Safety and testingInterlocks, fail-safe, acceptanceAcceptance testing

Worked example: writing the sequence before the panel is built (illustrative)

StepSequence
1Mains fails; after 3 s all sets start
2First set at voltage closes onto the dead bus; others synchronise
3Changeover connects the bus; loads restore in four steps
4Any set trip: non-essential feeders shed at once
5Mains stable for 5 minutes: return to mains; sets cool down and stop

The factory test should follow this sequence line by line; that is where a missing permissive on step 2 is found, before the panel leaves the works. See sequence engineering and dead-bus logic.

Do not let the control system be the only thing standing between a fault and the equipment. Protection relays must trip on their own, even if the controller has failed.

Where to start

If your question is…Start with
Which automation does my site need?Requirement to automation
Upgrading old controlsControl modernisation
Too many alarmsAlarm rationalisation
Keeping control alive in an outageControl power and fail-safe

Sequence sheet

Two columns, because at the specification stage that is all anyone can honestly fill in. The example above is a five-step sequence for one plant, written in the order the steps happen; this sheet is the list that such a sequence gets written from — every event the site can produce, in no particular order, each with the response it requires. The completed sheet below is for a textile spinning mill with four 625 kVA sets on two buses, 1580 kW. Fifteen events, and the discipline is that a sequence may not be designed until every one of them has an answer.

EventRequired response
Utility fails on one bus onlyOpen that incomer. Start all four sets. Form an island on the affected bus; the healthy bus stays on the utility and the coupler stays open
Utility fails on both busesOpen both incomers. Start all four sets. One dead-bus close per bus, by priority, then synchronise the other two
Utility returns and stays healthyNothing automatic. Ask the operator, then return by an open transition: sets off, buses dead, incomers closed, shed stages restored in reverse with a gap
A set fails to startAlarm with the set identified. Carry on with the sets that did start and recompute capacity. Do not hold the sequence waiting for it
A set trips while carrying loadOpen its breaker on the hard-wired path. Recompute capacity. Shed the next stage if the load now exceeds it
Two sets lostShed to 740 kW on the two that remain. Alarm at high priority. No automatic restart attempt of the tripped sets
Frequency falls below 48.5 Hz on a live busShed the next stage in order, within 155 ms, by a relay wired direct to the contactor. Then wait 10 s before assessing again
Frequency recovers above 49.5 HzHold for 10 s, then stop shedding. Restore nothing automatically; restoration waits for the operator and happens stage by stage with 20 s between
Bus protection operatesBlock every close to that bus and block the coupler. Latch it, and require a reset by hand rather than by the controller
A bus VT fuse or MCB failsBlock dead-bus closing on that bus and inhibit its sync check. Treat the absence of a healthy signal as unhealthy
The coordinating controller fails, or restartsNothing in the hard-wired layer changes: protection, stage 1 shedding and every closing interlock carry on. On restart, read every breaker position and set state before asserting a single output
The network to the supervisory system failsNothing in the plant stops. Operators work from the board instruments and the set panels. Alarm, and mark every value on screen as stale rather than holding the last reading
An operator asks to stop the last running setRefuse, with a message. Accept it only while the remaining capacity still covers the must-keep 380 kW
A tie or bus coupler is found closedAlarm at high priority. The coupler is padlocked open in normal running, so a closed coupler means the two buses are no longer independent
Fuel reaches low-low on a day tankAlarm, on two sensors agreeing for 30 s. Stop nothing: stopping a healthy set during an island is worse than running a supervised one low
  
  

Fill this in before choosing any hardware, and three things fall out of it that a sequence written first will miss.

The architecture is already decided by the time the sheet is full. Row seven needs a response in 155 milliseconds, which no scan-based controller can promise, so that line has written itself a relay wired direct to a contactor. Row five needs a breaker opened whether or not anything else is working, so that line has written itself a trip coil on a hard-wired path. Row six needs capacity arithmetic across four sets, which is the first row on the sheet that genuinely requires a coordinating controller. Nobody chose a three-layer architecture; the events chose it, and the sheet is the evidence.

A third of the rows are refusals. Rows three, eight, eleven, thirteen and fifteen all specify something the system must not do: no automatic return, no automatic restoration, no output before reading the plant, no stopping the last set, no stopping for low fuel. These are the lines that never appear in a sequence of operation, because a sequence describes what happens next and these describe what must not. They are also, consistently, the lines that cause outages when they are left unwritten — and they are the reason a specification is a list of events rather than a flowchart.

Every row becomes a test. The fifteen events here produced the ten site acceptance cases this section describes, and the awkward rows produced the interesting ones: row thirteen became the refusal test, row eleven became the controller power-cycle test, row nine became the injection that found an interlock wired to the wrong relay. An event with no answer in the second column is an event nobody will test, and an event nobody tests is the one that arrives at three in the morning.

The forty-two guides below take each of these rows apart in turn. If you are specifying a control system, start here, fill both columns for your own site, and send it with the enquiry: a completed sequence sheet tells us more about what you need than a panel schedule does.

What to send us

Send your single-line diagram and how the system should behave. WhatsApp 98852 01608 or use the application engineering enquiry.

All 42 guides in this section

Questions engineers ask

What is a power management system?

A PMS supervises several generators and sources: it starts and stops sets to match load, shares load, sheds non-essential loads when capacity is short, and restores them in order. It also keeps sets at a healthy load, rotates duty to balance running hours, and records events, so the plant runs efficiently and operators can see what happened after any disturbance.

What should a control system do if its PLC fails?

Fail safe: generators and breakers should stay in a safe state, with local manual control available. This is designed in through control-power and fail-safe architecture. Each controller keeps working on its own if the network fails, protection stays local, and a written procedure tells operators how to run the plant by hand until the system is restored.