In short. Choose automation by requirement, not by product. One standby set needs an AMF controller and an ATS. Several sets need synchronising, sharing and sequencing. Load shedding needs feeder control, and critical or hybrid plants need a power management system with designed degraded modes. Add an energy management system and analytics only when there is something real to optimise. Each step up adds cost, complexity and things to test.
Who this page is for: For owners, consultants and project engineers deciding what level of control and automation a power system actually needs.
Key facts
- Start from the functions the site needs, then pick the simplest architecture that delivers them.
- One standby set: AMF controller with ATS.
- Two or more sets in parallel: synchronising, load sharing and paralleling switchgear.
- Generator smaller than the load: automatic load shedding and restoration.
- Battery, solar and generators together: PMS with battery control and a microgrid controller.
- Every added layer needs its own degraded mode and test.
Requirement to architecture
| Requirement | Architecture | See |
|---|---|---|
| One standby generator, automatic start and transfer | AMF controller and ATS | ATS and AMF logic |
| Two or three sets in parallel | Synchronising and load-sharing controllers, paralleling switchgear | synchronising |
| Load shedding and restoration | PLC or PMS with feeder control | load shedding |
| Two utility sources | Main-tie-main logic | main-tie-main |
| UPS plus generator for critical loads | Coordinated ATS, UPS settings and integrated tests | UPS and ATS coordination |
| Battery or solar with generators | PMS with battery control and microgrid controller | microgrid controller |
| Operator visibility and records | SCADA with event recording | SCADA |
Worked example: three sites, three answers (illustrative)
| Site | Requirement | Architecture chosen | Not chosen, and why |
|---|---|---|---|
| Apartment block, one 250 kVA set | Automatic backup for lifts, pumps, common areas | AMF controller, ATS, remote alarm | PMS: nothing to coordinate |
| Factory, three 750 kVA sets, load sometimes above two sets | Parallel running, start on load, shed if a set trips | Synchronising and sharing controllers plus a PLC for shedding | EMS: one tariff, no battery |
| Hospital campus with battery and solar | No-break critical loads, peak shaving, island operation | PMS, battery control, microgrid controller, SCADA, with UPS on no-break loads | Nothing removed: each layer has a job |
The apartment block was first offered a PLC-based plant controller. It would have added a single point of failure and a programming dependency for a job one AMF controller does well.
Do not buy a higher level of automation than the requirement needs. Every added controller, network and program is another thing that can fail, needs a degraded mode and must be tested and maintained.
Steps
- Write the functions the site must perform, and what happens if each fails.
- Pick the simplest architecture from the table that covers them.
- Define degraded modes for each controller.
- Plan FAT and SAT. See FAT and SAT.
Requirement sheet
One site taken function by function, rather than three sites compared. The example above sets an apartment block, a factory and a hospital campus side by side and picks an architecture for each; this sheet does the opposite cut through the same question — a single installation, a textile spinning mill with four 625 kVA sets on two buses, with every function it needs listed separately and an architecture written against each. Nine functions. Two of them are answered by something that is deliberately not a controller, and one is answered by nothing at all.
| Function needed | Consequence if it fails | Architecture |
|---|---|---|
| Trip a faulty set without depending on anything else | The set, and possibly the busbar, is damaged. Everything else on this sheet becomes irrelevant | A protection relay on each set, with its own inputs and its own trip coil wiring. Deliberately not a controller function, at any price |
| Start the sets and get one onto each dead bus within 20 s | The mill stays dark. Ring frame ends break across both lines and the shift is lost to piecing | Set relays with dead-bus and sync-check permissives, arbitrated per bus by a priority order and a hard-wired interlock between each pair |
| Bring the other two sets onto a live bus | Capacity stops at 1000 kW, so two shed stages stay off and half the mill stays down | Sync check in the set relays, with governors and voltage regulators matched across the four sets |
| Shed 420 kW within 155 ms of the frequency crossing 48.5 Hz | The island collapses. Everything stops, humidification included, and recovery starts from a blackout | An underfrequency relay wired direct to the contactor. Deliberately not a controller function: the timing will not survive a scan |
| Shed the remaining three stages in order, with capacity arithmetic behind the decision | The island survives the loss of one set but not two | A coordinating PLC. This is the first function on the sheet that genuinely requires one |
| Hand the island back to the utility without ever paralleling with it | 2000 kW of generation could be connected to the grid by a setting error | No synchronising equipment on the incomers at all. An open transition, and a closing permissive that offers no live close from any location |
| Order events to better than 1 ms so that a trip can be explained afterwards | Investigations end in opinion, and the same fault recurs | A master clock with holdover, and precision time distribution to all seven protection relays |
| Show the operator the plant and keep the alarm list | Operators work from board instruments and set panels. Slower, and harder at night, but nothing stops | Supervisory software and a network. Nothing in the plant depends on it, which is a design decision rather than a limitation |
| Peak shaving, tariff optimisation, battery dispatch | Nothing. The mill has one tariff and no battery | Not chosen. An energy management layer was offered and declined: there is nothing here for it to optimise, and it would add a dependency to a plant whose whole design is about having fewer of them |
Read the third column down the sheet and the architecture assembles itself in layers, in the order the functions demanded them: protection, then permissives and the fast shed, then coordination, then supervision. Nobody picked that arrangement. It is what nine honest answers to the second column add up to, which is why this sheet is worth filling in before anybody is shown a panel drawing.
The second column is the one that does the work, and it has to be written as a consequence rather than as a severity. “Critical” tells you nothing; “ring frame ends break across both lines and the shift is lost to piecing” tells you how long you have and what it costs, and those two facts together are what justify the 20-second target in row two and the 155 millisecond target in row four.
Rows four and five are the clearest illustration: they are both load shedding, they differ only in how fast the answer must arrive, and that single difference puts one of them in a relay and the other in a PLC. A requirement sheet that said “automatic load shedding” on one line would have produced one answer and the wrong one.
Two rows are answered by something that is explicitly not a controller, and saying so in the sheet matters more than it looks. Protection and the fast shed are the two functions on which the mill’s survival rests, and both are placed where no software change, no network fault and no restart can reach them. Writing “deliberately not a controller function” rather than simply naming a relay is what stops a later upgrade from quietly absorbing them for the sake of a tidier drawing — which is the single most common way a well-designed plant becomes a fragile one.
The last row is the one most selection exercises leave out. An energy management layer was offered, considered and declined, and the reason is recorded: the site has one tariff and no storage, so there is no optimisation to perform, and the layer would have introduced a dependency into a plant whose entire architecture is built on removing them.
A sheet that only lists what was chosen reads as though nothing else was considered. Writing the declined layer in, with its reason, is what makes the rest of the sheet credible — and it is also the entry that will be looked at first on the day somebody does install a battery here.
Worked example: what each level adds to the test plan (illustrative)
Each level of automation adds functions, and every function needs proving, including what happens when it fails. A rough count of acceptance tests shows how quickly the commitment grows:
| Architecture | Typical functions | Approximate acceptance tests |
|---|---|---|
| AMF controller and ATS, one set | Mains sensing, start, transfer, return, alarms | About 10 to 20 |
| Three sets with a PLC for shedding | Plus synchronising, sharing, dispatch, shedding, restoration | About 50 to 80 |
| PMS with battery, solar and microgrid control | Plus modes, transitions, leader handover, battery limits | Often 150 or more |
The tests are not optional: an untested function is a function that will be discovered in an outage. When comparing architectures, compare the test plans as well as the equipment lists; a level of automation the site cannot afford to test properly is a level it cannot afford.
Questions to answer before choosing
- Which loads must never lose supply, and how long can each of the others wait?
- How many sources are there now, and how many are planned?
- Can one source carry the whole load, or must loads be shed?
- Will the site run in parallel with the grid, and is export allowed?
- Is there a battery or solar, now or planned?
- Who will operate and maintain the system, and what skills do they have?
- What records and remote visibility does the owner need?
The answers map almost directly to the requirement table above, and they make the choice explainable to the owner, the consultant and the suppliers alike.
Growing from one level to the next
| From | To | What to provide at the first stage |
|---|---|---|
| One set with AMF | Several sets in parallel | Controllers that support load sharing; space in the switchboard |
| Several sets | Load shedding | Motorised feeder breakers or contactors, and feeder metering |
| Generator plant | Battery and solar | A PMS-ready controller, open protocols and a planned battery connection point |
| Local operation | SCADA | Source time-stamping, a defined point list and a segmented network |
What the specification should state
The functions required, the architecture chosen and the reason for it, what each layer does when the layer above fails, the interfaces between suppliers, the hard-wired signals, and the acceptance tests. A specification that names products without stating functions and failure behaviour invites each supplier to deliver their own idea of the system, and the joins between them are then nobody’s job.
Common mistakes
- Choosing a product first.
- Over-automating a simple site.
- Under-automating a parallel plant.
- No degraded modes defined.
What to send us
Send the single-line diagram, the sources and what the site must do in an outage. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. Sites and choices are illustrative.
Questions engineers ask
How much testing does each automation level add?
Roughly 10 to 20 acceptance tests for one set with an AMF controller and ATS, about 50 to 80 for three sets with a PLC for shedding, and often 150 or more for a PMS with battery, solar and microgrid control. Every function and its failure behaviour must be proved, so compare test plans as well as equipment when choosing.
What should be asked before choosing an automation architecture?
Which loads must never lose supply and how long others can wait, how many sources there are now and planned, whether one source can carry the whole load, whether the site parallels with the grid, whether there is a battery or solar, who will operate and maintain the system, and what records and remote visibility the owner needs.
Do I need a PLC?
If several sources, transfer switches and sheddable loads must be coordinated, usually yes, or a power management controller doing the same job. A single standby set is better served by an AMF controller and ATS, which do the job reliably without adding a programming dependency and a single point of failure the site does not need.
Can I start simple and grow?
Yes, if the first stage is chosen with the growth in mind: generator controllers that support load sharing, motorised feeder breakers where shedding may follow, open protocols, space in the switchboard and a defined hierarchy. Each later layer then adds to the system instead of forcing earlier equipment to be replaced.
Is SCADA mandatory?
No. Protection, device control and plant control keep a site safe and running without it. SCADA adds a central view, event records, history and remote alarms, which become valuable as the plant grows or where the owner needs evidence of performance. Remote alarms by message are often enough for small sites.
When is EMS worth it?
When there are real choices with a cost difference: several sources, a battery or solar, variable tariffs or demand charges. Then choosing which source runs and when saves money every day. With one source and a flat tariff there is little to optimise, and an EMS adds cost and complexity without return.
This guide gives general principles. Architecture must be agreed with the site owner.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.