In short. A plant master controller makes several generator sets behave as one power plant. It decides which sets run, starts and stops them, closes their breakers, shares load and runs the plant auxiliaries. Each set keeps its own protection and basic control. If the master is lost, the running sets must stay safe and keep sharing load, and someone must know how to run the plant by hand.
Who this page is for: For control engineers, plant managers and consultants on multi-generator plants for factories, hospitals and data centres.
Key facts
- The master coordinates; each set controller protects its own set.
- Jobs: availability, start and stop sequencing, synchronising, kW and kVAr sharing, auxiliaries, alarms.
- Central, peer-to-peer and hybrid architectures each trade simplicity against single points of failure.
- Load sharing should continue between set controllers if the master fails.
- Auxiliaries such as fuel transfer, ventilation and chargers are part of the plant, not extras.
- Test master failure at SAT.
What the master coordinates
- Which sets are available, running, loaded or on standby.
- Start and stop sequences. See sequencing and dispatch.
- Synchronising and breaker closing. See synchronising.
- kW and kVAr sharing.
- Plant auxiliaries: fuel transfer, cooling, ventilation, battery chargers, dampers.
- Plant alarms and summary status to SCADA.
Architecture options
| Option | How it works | Trade-off |
|---|---|---|
| Central master | One controller commands all sets | Simple, but a single point of failure |
| Peer-to-peer | Set controllers communicate and agree | No single master; more tuning |
| Hybrid | Peer sharing with a master for dispatch and reporting | Common in practice |
Worked example: four sets, load-dependent start and stop (illustrative)
A plant has four 1000 kVA (800 kW) sets. The master starts the next set before the running sets are too heavily loaded. With only two sets running, a set trip above 800 kW still needs load shedding, so the shedding scheme covers that case.
| Load | Sets running | Loading per set | Rule |
|---|---|---|---|
| 900 kW | 2 | about 56% | Start a third set if load exceeds 80% of running sets (1280 kW) |
| 1400 kW | 3 | about 58% | Stop one set if load stays below 55% of the remaining sets (880 kW) for 10 minutes |
| 2100 kW | 4 | about 66% | No standby set left: if one set trips, the other three carry about 88%; shed priority-3 loads only if load is above 2400 kW |
The start and stop thresholds are well apart, with a time delay, so sets do not cycle on and off. In a SAT test the master was powered off at 1400 kW: the three running sets kept sharing through their own controllers, and the operator confirmed from the procedure how to start the fourth by hand if load rose.
Do not let the plant depend on the master for protection or for load sharing between running sets. If the master fails, sets should keep running and sharing, and operators must have a written manual procedure.
If the master fails
- Running sets keep sharing through their own controllers.
- No new starts or stops until manual action or recovery.
- Alarm to operators with the manual procedure. See control philosophy.
See PMS architecture and state machines.
Start and stop settings
| Setting | Value |
|---|---|
| Start next set above (percent of running capacity) | |
| Stop a set below (percent of remaining capacity) and delay | |
| Spinning reserve rule | |
| Behaviour on master failure |
What makes a set available
The master can only dispatch sets it knows are ready. Each set reports a single available signal, built from conditions that must all be true:
| Condition | Why it matters |
|---|---|
| Controller in automatic mode | A set in manual will not respond to start commands |
| No shutdown or lockout active | A set with an unreset fault cannot be started |
| Breaker racked in, charged and in remote | The set may start but could never close onto the bus |
| Fuel above the minimum level | A start that runs out of fuel within minutes is worse than no start |
| Starting battery healthy, charger on | Predicts whether the set will crank |
| No maintenance lock or permit on the set | Prevents an automatic start while someone is working on it |
The master counts available sets, compares them with what the reserve rule needs and alarms the shortfall at once. A plant that discovers an unavailable set only when it fails to start has been running with less reserve than anyone thought.
Worked example: sizing the fuel transfer (illustrative)
All four 1000 kVA sets in the example above run at about 66%, about 525 kW each. At a typical 0.26 litres per kWh at that loading, each burns about 525 × 0.26 ≈ 137 litres an hour, so the plant burns about 4 × 137 ≈ 548 litres an hour.
| Item | Working | Result |
|---|---|---|
| Day tank of 1000 litres, full | 1000 ÷ 548 | about 1.8 hours of running with no transfer |
| Transfer pump capacity | Consumption plus at least 50% margin | at least about 825 litres an hour, so a pump of 1000 litres an hour |
| Low-level alarm | One hour of consumption left | at about 550 litres |
| Pumps | Duty and standby, on different supplies | Automatic changeover on failure |
The master starts and supervises the transfer pumps like any other plant item. A transfer pump fed only from the mains, or a pump failure that is not alarmed, turns a long outage into a fuel starvation event about two hours in.
Ventilation and dampers
A generator room depends on its air path: inlet louvres, radiator outlet dampers and room fans. If dampers stay closed, the room heats within minutes and the sets shut down on high temperature, all at once. The master should open dampers on any start command, prove them open by limit switches within a set time, and alarm if they do not open; many plants use dampers that open by spring on loss of power, so a control failure leaves them open rather than closed. Room temperature should be measured and alarmed well before any set reaches its own high-temperature limit.
Signals between the master and each set
| From the master to the set | From the set to the master |
|---|---|
| Start and stop | Available, running, at voltage and frequency |
| Permit to synchronise and close | Breaker open or closed |
| Load or base-load set point | kW, kVAr, current, voltage, frequency |
| Unload and open | Common alarm and common shutdown |
| Reset request, where permitted | Fuel level, battery voltage, running hours |
Hard-wire the signals whose loss would be unsafe, such as start, breaker status and shutdown, and use the network for measurements and convenience signals. A set must stay in a safe state if any signal from the master is lost.
How peer controllers agree who closes first
Without a central master, set controllers must decide among themselves which set closes onto a dead bus, because two closing together could be out of phase. Common methods are a hard-wired arbitration line that only one controller can hold at a time, or a rule such as lowest address closes first with the others waiting a short time and checking the bus voltage before closing. Test the case where two sets reach voltage at the same moment; it is rare in normal running and common after a mains failure, when all sets start together.
The manual procedure, written before it is needed
- How to recognise that the master has failed, from the alarm and the panel indications.
- How to start a set locally, check its voltage and frequency, and synchronise it with the manual synchroniser and sync-check.
- Which loads to shed by hand if capacity is short, in what order.
- How to run the fuel transfer, ventilation and chargers without the master.
- Whom to call, and how to hand back to automatic once the master is restored.
Practise it once a year with the master switched off. A procedure that has never been followed by the people on shift is a document, not a fallback.
Starting batteries and chargers
A set that cannot crank is not available, whatever its engine condition. The master should read each starting battery voltage and charger status continuously and include them in the availability signal. Battery voltage on float says little about capacity, so add a periodic check of the voltage dip during cranking, logged at every start: a dip that grows deeper month by month warns of a battery that will fail before it does. Chargers should be fed from a supply that is restored by the generators themselves, so a long outage does not slowly flatten the batteries of the sets on standby.
The plant summary for SCADA
Operators need the plant first and the sets second. The master should give SCADA a short summary: plant mode, sets available against sets required, sets running, total load and percentage of running capacity, reserve against the reserve rule, fuel hours remaining, and one common alarm for each set. Detail for each set sits behind it. A summary that answers whether the plant can carry the next hour lets an operator act before a shortfall becomes a trip.
What the site acceptance test must prove
| Test | Pass when |
|---|---|
| Mains failure with all sets on standby | Sets start, one closes on the dead bus, others synchronise, load restored in order |
| A set made unavailable while running | Master starts a replacement and alarms |
| Day tank pump failure | Standby pump takes over; alarm raised |
| Damper fails to open on start | Alarm within the set time; plant response as designed |
| Master powered off at high load | Running sets keep sharing; operators follow the manual procedure |
Repeat the master-off test and the mains-failure test every year, with the operators on shift taking part. The first shows that the plant survives without its master; the second shows that the master still does its main job after a year of small changes to settings, sets and auxiliaries.
Common mistakes
- Start and stop thresholds too close, causing cycling.
- Load sharing that stops with the master.
- Auxiliaries left outside the control design.
- Master failure never tested.
What to send us
Send the number and rating of sets, the load profile and the control description. WhatsApp 98852 01608 or use the application engineering enquiry. See alarm design.
Evidence note. Thresholds are illustrative; plant studies and makers’ limits govern.
Questions engineers ask
What makes a generator set available to the plant master?
All of these at once: the controller in automatic, no shutdown or lockout active, the breaker racked in, charged and in remote, fuel above the minimum, a healthy starting battery and charger, and no maintenance lock. The master counts available sets against the reserve rule and alarms any shortfall straight away, before a start is needed.
How large should a generator plant fuel transfer system be?
Larger than the plant can burn, with margin. Four sets at about 525 kW each burn about 548 litres an hour at 0.26 litres per kWh, so a 1000-litre day tank lasts under two hours. Pumps of at least about 825 litres an hour, duty and standby on different supplies, with a low-level alarm at one hour of fuel, are a sound starting point.
Do identical sets simplify control?
Yes. Identical sets share load and reactive power naturally with the same settings, can be rotated freely, and need one set of spares and procedures. Mixed sizes and makes are workable, but dispatch must choose combinations by rating, droop and compensation must be set on each machine base, and governor responses may differ during load steps.
Should the master also control fuel?
It should at least monitor fuel levels and the transfer system, and in most plants it should run the transfer pumps too, because fuel is part of whether a set is available. Day tank levels, pump status and bulk tank level belong in the availability logic, with alarms early enough to act, for example at one hour of fuel remaining.
What about remote operation?
Allow it only within written authority rules: who may start, stop or change modes, from where, and with what confirmation. Many plants allow remote monitoring and starting but keep breaker closing, resets and setting changes local. Remote commands must pass through the same interlocks as local ones, and every command should be logged.
Can the master be replaced later?
Yes, if the interfaces to each set are standard and documented: hard-wired start, stop and breaker signals, and measurements over an open protocol. Replacement is then mainly reprogramming and testing. Where the master and set controllers use one maker proprietary link, replacing one usually means replacing both.
This guide gives general principles. Confirm with a project design.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.