Load-Shedding Automation and Priority Logic

How automatic load shedding works: priority tiers, fast event-based and slow shedding, under-frequency backup, shed tables, restoration and tests that prove the plant survives a source loss.

In short. Load shedding removes lower-priority loads so the remaining sources stay stable. It must act faster than the plant can collapse, shed the right amount in the right order, and never shed life-safety loads. Fast event-based shedding acts on a known loss, such as a set trip. Underfrequency shedding is the backup. Only tests with real source trips prove the scheme works.

Who this page is for: For control and protection engineers and plant managers on generator plants where load can exceed available capacity.

Key facts

  • Fast event-based shedding acts in tens of milliseconds when a known source is lost.
  • Slow overload shedding acts in seconds on measured overload.
  • Underfrequency stages are the backup if the faster schemes fail.
  • Shed in priority order; life-safety loads are never sheddable.
  • Shed enough to leave the remaining sets a margin, not just to reach 100%.
  • Restore in steps after recovery, never all at once.

Types of shedding

TypeTriggerSpeed
Fast event-basedLoss of a source or breaker, known in advanceTens of milliseconds
Slow overload-basedMeasured overload or limit exceededSeconds
UnderfrequencyFrequency below thresholds in stagesFractions of a second to seconds; backup
UndervoltageVoltage collapse in a weak systemDepends on the site

Worked example: priority table for a two-set plant (illustrative)

Two 625 kVA (500 kW) sets carry 800 kW. If one trips, 500 kW remains.

PriorityLoadskWShed when one set trips?
1 (never shed)Emergency lighting, fire pumps, UPS input180No
2Process line A, critical cooling220No
3Process line B200Yes
4Office air-conditioning, non-essential sockets200Yes
Remaining after shedding priorities 3 and 440080% of 500 kW

Fast shedding opened both feeders within about 80 ms of the set breaker opening. Underfrequency stages at 48.5 and 48.0 Hz were kept as backup. See load classification.

Never put fire pumps, emergency lighting or other life-safety loads on a sheddable feeder. And never rely on underfrequency alone for a plant where one set trip removes a large share of capacity.

Testing

  1. Trip a set at high load with the real feeders.
  2. Record time from set trip to feeder open, and the frequency dip.
  3. Block fast shedding and confirm the underfrequency backup acts.
  4. Confirm restoration in steps. See load restoration.

See load shedding basics.

Shedding table

PriorityFeederskWShed on which event
1 (never)  Never
2   
3   
4   

The timing budget from event to open breaker

A shedding scheme has to remove load before the frequency on the remaining generators falls to their trip point, which after the loss of a set in a small plant can be a matter of a few tenths of a second. The time the scheme takes is the sum of every step from the event to the opened breaker, and each step can be measured and reduced.

StepTypical timeWhat decides it
Generator breaker auxiliary contact changes state10 to 20 msBreaker mechanism and contact design
Controller input filter5 to 10 msThe input card’s debounce setting
Controller logic, up to two scan cycles40 to 100 msScan time of 20 to 50 ms; the event may arrive just after a scan began
Output relayAbout 10 msThe output card or interposing relay
Shedding breaker opens30 to 60 msShunt trip and breaker mechanism
TotalAbout 95 to 200 ms

A scheme triggered directly by the loss of a generator breaker, built like this, acts within about a fifth of a second at worst, which is usually fast enough. A scheme that waits for an under-frequency relay to measure the falling frequency adds the relay’s measuring time and the time for the frequency to fall to its setting, and is often too slow to save a small plant from a large loss; it remains valuable as a backup for events the direct scheme does not see. Shortening the scan time, using a fast interrupt-driven input for the trigger, or wiring the most important shed directly from the generator breaker’s contact bypass the slowest steps when the budget is tight.

Measure the budget rather than estimating it. During commissioning, record the generator breaker’s contact, the controller output and the shedding breaker’s position on one instrument with a common time base, trip the generator breaker, and read the times directly. The measured figure, not the sum of catalogue values, belongs in the control philosophy.

The data behind the priority table

A shedding table drawn on paper becomes, in the controller, a set of records, one for each sheddable feeder. The way those records are built decides whether the scheme sheds the right amount of load or simply the next names on a list.

FieldPurpose
Feeder identity and breakerWhat to open, and the position feedback to read
Priority numberThe order in which feeders are shed, lowest first
Measured load, liveThe actual kW the feeder carries now, from its meter
Sheddable flagWhether shedding is permitted at this moment, cleared by maintenance or process inhibits
Restore delay and conditionsHow long to wait, and what must be true, before reconnection

With these fields the controller can calculate, at the moment of the event, how much load must go and choose the lowest-priority feeders whose live loads add up to at least that amount, skipping any feeder whose flag is cleared. A table based on nameplate ratings instead of live loads sheds either too little, because the low-priority feeders happen to be lightly loaded that day, or far too much. The live figure is what makes the scheme dynamic, and it depends on every sheddable feeder having a working meter connected to the controller.

Calculating the shed at the moment of the event

The calculation the controller performs is short. It takes the total load just before the event and the capacity of the sources still running, and the difference, plus a margin, is the load to shed. It then walks the priority table from the lowest priority upwards, adding each sheddable feeder’s live load to a running total and marking it for opening, until the total exceeds the amount required. All marked feeders are opened together in one command, rather than one after another, because each extra scan cycle spent opening feeders in sequence is time the remaining sources spend overloaded.

Two refinements matter in practice. The pre-event load must be captured continuously, so that the value used is the one from before the event, not a reading distorted by the event itself. And the margin should leave the remaining sources comfortably below their rating, typically by a tenth, rather than exactly at it, so that the frequency recovers rather than hovering at the edge of the next trip.

What the shedding outputs do when the controller fails

Every shedding output has a state it takes if the controller stops, loses power or loses communication with its output card, and that state must be chosen deliberately. If the shedding contacts are arranged to open the feeders on loss of signal, a controller failure sheds all sheddable load at once, which is safe for the generators but drops large parts of the site for no reason.

If they are arranged to hold the feeders closed, a controller failure leaves the plant without automatic shedding, which is invisible until a set trips. Most sites choose to hold the feeders closed and to raise an alarm on controller failure, with under-frequency relays acting independently as the backup shedding. Whatever the choice, it should be written in the control philosophy and tested by switching off the controller with the plant running.

Inhibits, overrides and the record they leave

Real plants need ways to stop the scheme shedding a particular feeder: a process at a critical stage, a feeder under maintenance, a temporary supply to a sensitive load. Each such inhibit removes load from the scheme’s reach and so reduces the amount it can shed, and too many inhibits leave the scheme unable to save the plant.

The controller should therefore show at all times the total sheddable load available against the largest single loss it must cover, and alarm when inhibits reduce the available load below that figure. Every inhibit and override should be logged with the person who set it, the reason and an expiry time, and inhibits should lapse automatically unless renewed. A scheme whose inhibits are visible and time-limited stays able to do its job; one whose inhibits accumulate quietly over months does not.

The logic for putting load back

Restoration is the part of a shedding scheme most often left to people, and the part most likely to undo the scheme’s work. Automated restoration needs its own conditions, written into the logic. A shed feeder may be restored only when the frequency and voltage have recovered and stayed within their normal band for a set time; when the running capacity, less the present load, exceeds the feeder’s last measured load plus a margin; and when no restoration has occurred in the preceding interval, so that each restored block is absorbed before the next. Feeders are restored in reverse priority order, highest priority first, one at a time.

The logic should also remember why the feeder was shed. Load shed because a set tripped can return once a replacement set is running; load shed because the plant was approaching its capacity should wait until the load has fallen. A restoration routine that does not know the reason tends to restore load straight into the condition that caused the shed, and the plant sheds again a few minutes later.

Test cases for the shedding logic

The shedding logic should be tested in the controller before it is ever connected to the plant, with simulated inputs, and then on site with real breakers. A short set of test cases covers the logic’s important behaviours.

Test caseExpected result
Loss of each generator in turn, at high loadThe calculated shed covers the loss with margin, and the right feeders are selected
Same, with the lowest-priority feeders lightly loadedThe logic moves further up the table to reach the required amount
Same, with one feeder inhibitedThe inhibited feeder is skipped and the next one selected
A shedding breaker fails to openThe missing load is detected and the next feeder is shed
Controller failure with the plant runningOutputs take their designed state and an alarm is raised
Inhibits reduce available sheddable load below the requirementAn alarm is raised before any event occurs

Record each test with the inputs used, the feeders selected and the time from trigger to output. The record becomes the baseline against which every later change to the logic is tested again.

Common mistakes

  • Underfrequency shedding only.
  • Shedding just enough to reach 100%.
  • Life-safety loads on sheddable feeders.
  • Never tested with a real trip.

What to send us

Send the feeder list with loads and priorities, and the set ratings. WhatsApp 98852 01608 or use the application engineering enquiry.

Evidence note. Loads and settings are illustrative.

Questions engineers ask

How fast can an automatic load shedding scheme act?

A scheme triggered directly by a generator breaker opening typically acts in about 95 to 200 milliseconds: 10 to 20 for the breaker contact, 5 to 10 for the input filter, up to two controller scans of 20 to 50 milliseconds, about 10 for the output relay and 30 to 60 for the shedding breaker to open. Measure the actual chain at commissioning with one instrument and a common time base. Under-frequency shedding is slower and serves as backup.

Why should load shedding use live load measurements?

Because the right amount to shed depends on what each feeder carries at that moment, not on its nameplate rating. With live kW for every sheddable feeder, the controller calculates the load that must go and selects the lowest-priority feeders whose present loads add up to at least that amount, skipping inhibited ones. A table based on nameplate ratings sheds too little when low-priority feeders are lightly loaded, or far too much.

Is under-frequency shedding enough?

Often not, because it acts only after frequency has already fallen, when a generator trip has left the others overloaded. A scheme triggered by the generator breaker opening acts in about 0.1 to 0.2 s with a calculated amount. Under-frequency relays remain valuable as the independent backup when the fast scheme or its controller fails.

How much load to shed?

Enough to bring the remaining sources within their safe loading at once, plus a margin, calculated for each event from live feeder loads: the present load minus the remaining capacity times the allowed loading. Shedding by nameplate ratings sheds too little when feeders are lightly loaded and far too much when they are full.

Who sets priorities?

The operations and safety owners decide which loads matter most and in what order they may be shed, because that is an operational judgement. Engineering then checks that each priority group can be switched, that its load is measured and that the scheme acts in time. Review the list at least once a year and whenever loads change.

How is it tested?

By simulated trips at the factory against a model, then controlled trips on site with monitoring: a running set opened at high load while the timing from breaker contact to feeder open is measured on one instrument with a common time base. Inhibited feeders, failed contactors and loss of the controller are tested too.

Values are illustrative. Shed tables must be project-specific.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.