Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

DG + BESS Hybrid Dispatch Control

How generators and batteries are dispatched together: loading targets, battery covering steps and peaks, reserve, recharge rules, mode transitions and limits that keep the plant stable.

In short. In a generator and battery hybrid, the generator supplies bulk energy in its efficient band while the battery handles fast changes, peaks and light-load hours. The dispatch control decides, moment to moment, which does what. It must keep enough reserve to ride a trip of either source, stop the generator running light for long periods, never hand the generator a step it cannot accept, and recharge the battery before it runs out.

Who this page is for: For control engineers, plant operators and owners commissioning or tuning a DG and BESS hybrid.

Key facts

  • The generator is best at sustained energy; the battery at instant response.
  • Start the generator at a minimum state of charge; stop it at a recharge target.
  • Keep the generator above its minimum healthy load whenever it runs.
  • Limit the step the generator can see if the battery trips.
  • Define which source forms voltage and frequency in each mode.
  • If the battery is empty or faulty, the generator must carry the critical load alone.

Roles

SourceBest atLimited by
GeneratorSustained energy and long outagesStep acceptance, minimum efficient load, start time
BatteryInstant response, peaks, ramps, short gapsStored energy and power rating

Dispatch strategies

StrategyHow it works
Load followingGenerator follows load; battery smooths steps
Peak shavingGenerator at a set point; battery covers peaks
Charge on generatorGenerator runs in its efficient band and the surplus charges the battery
Generator offBattery carries light load alone; generator starts on state of charge or load
Reserve substituteBattery holds reserve instead of an extra running set

Worked example: a night cycle on a 250 kVA set with a 300 kWh battery (illustrative)

A site’s night load is about 40 kW. The 250 kVA (200 kW at 0.8 power factor) set should not run below about 40% (80 kW) for long.

PhaseRuleWhat happens
Battery onlyGenerator off while state of charge is above 30%Battery carries 40 kW
Generator startState of charge reaches 30%, or load exceeds the battery’s limitSet starts and synchronises
Charge on generatorSet runs at about 140 kW: 40 kW to the load, about 100 kW chargingSet at about 70%, a healthy band
Generator stopState of charge reaches 80%Set unloads and stops after cool-down

The usable band between 30 and 80% is about 150 kWh, nearly four hours at 40 kW, so the set runs for about an hour and a half, a little longer allowing for charging losses, every five hours or so, always well loaded, instead of all night at 20%. The thresholds must leave enough charge to carry the critical load while a set that fails to start is replaced. See the hybrid screening tool.

Do not set the generator start threshold so low that a failed start leaves the battery empty. Keep enough charge in reserve to carry the critical load through a second start attempt or the start of a standby set.

Control rules

  • Keep the generator in a loading band that avoids long light-load running.
  • Define start and stop state-of-charge thresholds with hysteresis.
  • Limit battery discharge so the generator never faces a larger step than it can accept if the battery trips. See load-step response.
  • Define which source forms the grid in each mode.
  • Define the response if either source trips.

Testing

  1. Step the load in each mode and record frequency and voltage.
  2. Trip the battery inverter while it carries load.
  3. Trip the generator while the battery is low.
  4. Run a full night cycle and log state of charge and generator loading.

Dispatch settings sheet

SettingValue
Generator start: state of charge and load thresholds 
Generator stop: state-of-charge target 
Minimum generator loading while running 
Critical-load reserve kept in the battery 
Grid-forming source in each mode 

Worked example: the step the generator sees if the battery trips (illustrative)

When both sources share the load, a battery inverter trip hands its whole output to the generator in an instant. Suppose the 250 kVA (200 kW) set in the example above can accept a single step of about 50% of rating, 100 kW, without its frequency falling below the shedding threshold; the maker’s step-load data govern the actual figure.

Operating pointSet outputBattery outputStep if the battery tripsAcceptable?
Peak shaving, battery discharging hard60 kW120 kW120 kW, 60%No
Battery discharge limited to the set’s step capability80 kW100 kW100 kW, 50%Yes, at the limit
With fast shedding of 40 kW of non-essential load on a battery trip60 kW120 kW120 − 40 = 80 kW, 40%Yes

Either the dispatch limits battery discharge to what the set can pick up, or a fast shed tied to the inverter trip signal removes the excess. Without one of the two, the battery that was meant to make the plant more resilient becomes the event that trips it.

Worked example: what the hybrid saves overnight (illustrative)

The site uses about 400 kWh over a ten-hour night at about 40 kW. Typical fuel figures for a diesel set are about 0.40 litres per kWh near 20% load and about 0.27 litres per kWh near 70%; energy routed through the battery loses about 10% on the round trip.

OptionWorkingFuel per night
Set alone all night at about 20%400 × 0.40about 160 litres
Hybrid, worst case with all energy through the battery400 × 0.27 ÷ 0.9 = 400 × 0.30about 120 litres

The saving is at least about 40 litres a night, about a quarter, and in practice a little more because part of the energy goes straight from the set to the load while it charges. The engine also runs well loaded instead of slowly fouling at light load, which is often worth more than the fuel. Use the maker’s fuel curve and a logged load profile before relying on any figure.

Sizing the battery for generator-off hours

The longer the set should stay off, the larger the usable battery energy must be. Usable energy is the capacity times the operating band; with a band from 30 to 80%, half the capacity is usable. To keep the set off for six hours at 40 kW needs 40 × 6 = 240 kWh usable, so 240 ÷ 0.5 = 480 kWh of installed capacity.

The 300 kWh battery in the example gives about 150 kWh usable, nearly four hours, which is why its set starts twice in a long night. Widening the band gives more hours, but at the cost of battery life and of the reserve kept for a failed start.

Who forms the grid in each mode

ModeForms voltage and frequencyThe other source
Battery onlyBattery inverter, grid-formingGenerator stopped
Generator startingBattery inverterGenerator synchronises to the battery-formed bus
Both runningUsually the generator; the inverter switches to grid-followingBattery follows power set points
Generator stoppingBattery takes over forming before the generator breaker opensGenerator unloads and opens

Each handover must be bumpless and must be tested with load on, including the case where the handover fails halfway. A plant where two sources both try to form the grid, or neither does, hunts or collapses.

State of charge is an estimate

The battery management system calculates state of charge from current, voltage and temperature, and the estimate drifts over days of partial cycling. A dispatch that starts the generator at 30% may in fact be starting it at 22 or 38%. Schedule a full charge periodically, often weekly, so the estimate is recalibrated, and set the start threshold with enough margin that the drift cannot eat into the reserve for a failed start.

Keep the battery cool

Battery ageing roughly doubles for every 10 degrees Celsius above about 25 degrees, a widely used rule of thumb across chemistries. In a hot climate, a battery container running at 35 degrees can lose a large part of its life compared with one held at 25. Air conditioning for the battery space is part of the hybrid design, it must itself be supplied in every mode, and its consumption belongs in the energy balance.

What to log in a hybrid plant

Log the generator’s loading, starts and running hours, the battery’s state of charge, charge and discharge energy, temperature and cycle count, and every mode change and handover with its time. Weekly review of these figures shows whether the generator is staying in its healthy band, whether the battery is cycling more deeply than planned, and whether the start and stop thresholds still suit the load as it changes over the seasons. A hybrid that is not reviewed drifts back towards the generator running light, which is exactly the condition it was installed to avoid.

Maintaining the hybrid without losing either source

Plan maintenance so the plant is never left with only one source and no margin. When the generator is out of service, the battery carries the load only until its reserve is reached, so maintenance of the set should fit within the hours the battery can cover, or a temporary set should be connected. When the battery is out of service, the generator must carry the load alone at its full minimum-loading and step-acceptance limits, which may mean running loads that are normally shifted.

Common mistakes

  • Generator left running light because the stop threshold is too high.
  • Start threshold so low that a failed start empties the battery.
  • No hysteresis, so the set cycles.
  • No test of a battery trip under load.

What to send us

Send the generator and battery data, the load profile and present control settings. WhatsApp 98852 01608 or use the enquiry form. See also DG plus BESS architecture.

Evidence note. Thresholds are illustrative; battery and generator makers’ limits govern.

Questions engineers ask

How large a step can the generator see if the battery trips?

The whole battery output at that moment, in an instant. If a 200 kW set can accept a 100 kW step and the battery is discharging 120 kW, a battery trip exceeds what the set can take. Either limit battery discharge to the set step capability or shed non-essential load on the inverter trip signal, for example 40 kW, leaving an 80 kW step.

How much fuel does a battery hybrid save overnight?

Often around a quarter or more where the night load is light. A site using 400 kWh at about 40 kW might burn about 160 litres with a set running all night near 20% load. With a battery, the set runs near 70% and even with all energy through the battery uses about 120 litres. Logged load and fuel curves decide.

Does a battery always cut fuel use?

Only where the load profile leaves the generator lightly loaded for long periods, such as nights or weekends, or where peaks would otherwise need an extra set running. With a steady load near the set rating, round-trip battery losses can make fuel use slightly worse. Log the load for a few weeks and model it before relying on a saving.

Can the generator be smaller?

Sometimes. If the battery covers motor starts and short peaks, the generator can be sized for the sustained load instead of the largest step. A study must still show that the generator alone can carry the critical load when the battery is empty, faulty or being maintained, and that it can accept the step if the battery trips.

What if the battery is empty?

The generator must then carry the critical load alone, so the dispatch must start it early enough to leave a reserve in the battery for a failed start, and the generator must be sized and set up to accept the loads it would pick up. Non-critical loads that the generator alone cannot carry should be shed automatically.

Who sets priorities?

The owner of the control philosophy, usually operations with engineering advice, decides which loads matter most, how much battery reserve is kept and when the generator should run. The PMS enforces the limits, such as minimum generator load and battery state of charge, so a priority choice can never push either source outside its safe range.

Values are illustrative. Hybrid dispatch needs project-specific design.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.

CallWhatsAppEnquire