In short. Every control system will eventually fail in some way: a PLC, a network, SCADA, control power, a sensor or the software. The design question is what happens next. Degraded modes define, for each failure, which functions continue, which stop safely and what operators must do. A failed controller or network should never turn into an unplanned outage.
Who this page is for: For control engineers, consultants and operations managers designing or reviewing critical power controls.
Key facts
- List each control function and what it depends on.
- For each failure, decide what continues, what stops and what operators do.
- Protection must be independent of supervisory and coordination controls.
- A bad sensor should block an action rather than cause one: use plausibility checks and voting.
- Watchdogs put a failed controller into a defined safe state.
- Test every degraded mode at SAT and in drills.
Failure modes and responses
| Failure | Lost | Designed response |
|---|---|---|
| PLC fault | Coordination functions | Device controllers continue; manual sequences available |
| Network loss | Remote and PMS commands | Local automatic operation |
| SCADA loss | Visibility | Plant continues; local panels used |
| Control power loss | Breaker operation | Backed-up supply. See control power |
| Sensor fault | Correct decisions | Voting or plausibility checks; block rather than act |
| Software error | Expected behaviour | Safe state on watchdog; independent protection |
Worked example: a degraded-mode table for load shedding (illustrative)
| Failure | Shedding behaviour | Operator action |
|---|---|---|
| Shedding PLC fails | Feeders stay as they are; underfrequency relays on non-essential feeders still shed by themselves | Alarm; manual shedding from the board if a set trips |
| One of two frequency sensors disagrees | PLC ignores the outlier and uses the other plus generator data | Alarm to replace sensor |
| Both sensors lost | PLC blocks automatic shedding (does not shed blind); underfrequency relays on non-essential feeders still shed by themselves | Manual shedding by procedure |
| Network to SCADA lost | Shedding continues locally | Watch local panel |
Before this review, a single frequency transmitter failing low would have shed every non-essential feeder on a healthy plant. Adding a second sensor and a plausibility check closed that path. See load shedding logic.
Do not let a single sensor or a single controller be able to trip or shed a healthy plant. Use plausibility checks, voting or a backup path so that a failed input blocks action instead of causing it.
Defining degraded modes
- List each control function and its dependencies.
- For each failure, decide which functions remain.
- Define manual procedures and who performs them.
- Make each degraded state visible with an alarm.
- Test each one. See FAT and SAT.
See redundant PLCs.
Degraded-mode sheet
The whole control system of a textile spinning mill with four 625 kVA sets on two buses, function by function. The example above is the degraded-mode table for one function, load shedding, worked through its sensor failures; this sheet asks the same questions of all eight functions, on a different and larger plant with four sets and two buses, and the value of doing it that way is the ordering it exposes. The third column is written as what continues, not as what breaks, because that is the sentence an operator needs at two in the morning.
| Function | Depends on | If lost, what continues | Manual action |
|---|---|---|---|
| Generator protection, each set | That set’s own relay, its current and voltage inputs and its trip coil wiring. Nothing else on the plant | Everything. It is independent of the PLC, the network, the master clock and SCADA, and it acts whether or not anyone is watching | None. There is nothing to do and nothing to enable |
| Underfrequency shedding, stage 1 | The Bus A incomer relay and a hard-wired link to the ring frame line 2 contactor | Continues with the PLC in stop, the network down and SCADA dark. Proved that way in SAT 04 | None for stage 1 |
| Shedding, stages 2 to 4 | The plant PLC and its capacity arithmetic | Stops if the PLC fails. Stage 1 still sheds by itself, which holds the mill at 1160 kW on three sets | Shed stages 2 to 4 by hand at the boards, in order, if a second set is lost |
| Dead-bus arbitration and priority | The set relays, the networked interlock between each pair, and hard-wired interlocks behind it | Continues on the hard-wired interlocks if the network stops. A lost message blocks a close rather than permitting one | Close one set to a dead bus by hand at the panel if arbitration is unavailable, then synchronise the rest |
| Island sequence, states 2 to 7 | The plant PLC | Stops if the PLC fails. Sets can still be started and closed by hand, and every closing permissive is still enforced in hardware | Form the island manually: start the sets, close one to each dead bus, synchronise the other two, then watch the loading |
| Capacity count | The plant PLC and its links to the four generator controllers | Degrades safely. A set whose link has failed is counted as unavailable, so the figure reads low rather than high | Confirm capacity from the set panels before restoring any shed stage |
| Sequence of events and event ordering | The master clock and the time distribution to the seven relays | Relays keep recording, with a degraded time-quality flag. Ordering to better than a millisecond is lost until synchronisation returns | Note the loss in the incident file. Do not grade records across the gap without carrying the flag |
| SCADA display and alarm presentation | The SCADA server and the control network | Nothing in the plant stops. Operators lose the overview, the alarm list and the trends | Work from the board instruments and the set panels, which between them show everything needed to run the island |
Filled in for every function rather than one, the sheet sorts itself into four layers, and the order is the architecture. Protection depends on nothing and survives everything. The hard-wired layer — stage 1 shedding and the closing interlocks — survives the loss of the PLC and the network. The PLC layer carries the coordination that makes the plant efficient rather than merely safe: stages 2 to 4, the island sequence, the capacity arithmetic.
SCADA carries nothing at all, which is the correct answer and is often a surprise to the people who paid for it. Two of eight rows read “stops if the PLC fails”, and both of them are in the third layer, which is how it should be; a row in the first two layers reading that way would be a finding.
Row six shows the direction a degrading measurement has to fail in. When a controller link drops, the capacity count does not freeze at its last value and it does not omit the set from the denominator — it counts that set as unavailable, so the number on the screen is lower than the truth.
An operator acting on a low figure sheds a stage that did not need shedding, which costs a line of ring frames for a few minutes. An operator acting on a high figure restores a stage the plant cannot carry, which costs the island. The two errors are not symmetrical and the sheet should say which way the arithmetic leans.
The fourth column is the part that has to be true rather than merely written, and that means two things. Every manual action named here has to be possible with the thing that failed still failed — shedding stage 2 by hand at the board does not require the PLC, and closing a set to a dead bus by hand does not require the network.
And every one of them has to have been done by the people who will have to do it, in a drill, with the mill running. An instruction to “form the island manually” is a sentence until somebody has started four sets, closed two breakers to dead buses and synchronised two more while the ring frames were stopped and the humidification was still on.
One row is worth reading as a warning rather than a reassurance. Row one says generator protection depends on nothing else, and that is only true while it stays true: the day a protection trip is routed through the PLC to get a tidier alarm, or a trip coil supply is picked up from a controlled source, that row quietly becomes false and no test on this sheet would catch it. The entry in the second column is therefore a constraint on future work as much as a description of the present, and it belongs in the change procedure as well as here.
Worked example: tracing what one function depends on (illustrative)
Fast load shedding looks like one function, but it rests on a chain of parts, any of which can fail. Listing them shows where redundancy or a degraded mode is needed.
| Link in the chain | Single point? | Degraded response |
|---|---|---|
| Generator breaker status to the PLC | Yes, one contact per breaker | Frequency-based shedding as backup |
| Bus frequency measurement | No, two sensors with plausibility check | Use the healthy one; block if both lost |
| Shedding PLC | Yes | Underfrequency relays on non-essential feeders shed on their own |
| Output relays and feeder contactors | Per feeder | Next priority group shed if one fails to open |
| 24 V supply to the PLC and outputs | No, two supplies from independent sources | Alarm on loss of either |
Two rows are single points by nature, and both are covered by a degraded mode rather than duplication. That is often the right answer: a cheap, independent backup that does the essential part of the job is worth more than a second copy of an expensive controller sharing the same weaknesses.
Setting a watchdog
A watchdog is a signal a controller must keep changing to prove it is alive, for example an output that toggles every 100 ms, read by an independent relay or by the devices it controls. If the toggling stops for longer than the watchdog time, typically a few hundred milliseconds to a second, the receiving devices go to their defined safe state: generator controllers to local automatic, permissives to blocked, shed contactors held. Set the watchdog time longer than the controller’s worst normal scan with margin, so it never trips on a busy scan, and shorter than the time the plant can run without the controller’s fast functions.
How often to drill each degraded mode
| Degraded mode | Typical drill |
|---|---|
| SCADA lost, operate from local panels | Every six months |
| Plant controller lost, manual dispatch | Every year |
| Network lost between controllers | Every year |
| Control power on battery for a long outage | With the battery capacity test |
| Black start with automation disabled | Every year |
Run drills with the people on shift, not only the engineers who designed the system, and record how long each took and what was unclear. The procedure is then corrected while there is time to do it.
A cyber incident is a degraded mode too
If the supervisory network or a server is compromised, the safest response is often to disconnect it and run on local control, exactly the degraded mode drilled for a SCADA failure. Plan it that way: decide in advance who may disconnect what, confirm that doing so leaves protection and local automatic operation untouched, and include the step in the incident plan. A plant that can run safely without its upper layers takes most of the danger out of an attack on them.
Common mistakes
- Designing only for normal operation.
- Single sensors driving trips.
- Degraded states that are silent.
- Manual procedures never drilled.
What to send us
Send the control description and the list of functions you depend on. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. The table is illustrative; each plant defines its own.
Questions engineers ask
What is a watchdog and how should it be set?
A signal a controller keeps changing to prove it is alive, such as an output toggling every 100 ms, read by independent devices. If it stops for longer than the watchdog time, typically a few hundred milliseconds to a second, they go to their defined safe state. Set it above the worst normal scan with margin.
How often should degraded control modes be drilled?
Commonly every six months for running from local panels when SCADA is lost, and every year for manual dispatch without the plant controller, loss of the network between controllers and black start with automation disabled. Run drills with the people on shift, record times and unclear steps, and correct the procedures.
Is full redundancy always needed?
No. For many functions, a well-designed degraded mode, such as local automatic operation or independent underfrequency relays, gives most of the protection of full redundancy at a fraction of the cost and complexity. Duplicate where losing the function is unacceptable and no simpler fallback exists, and design degraded modes for the rest.
Who writes manual procedures?
Engineering, with operations, because engineers know what the system does in each failure and operators know what can be done on the night. The procedures are then tested in drills with the people on shift, corrected from what the drills show, and kept at the panels where they will be used, not only in a document store.
How do I know the plant is degraded?
Through explicit alarms and a clear status display: controller failed, network path lost, sensor disagreement, standby not ready, running on one supply. The overview should show which functions are available and which are lost, so operators know immediately which manual procedures apply instead of discovering it when an automatic action fails.
What about cyber incidents?
Treat them as another failure mode with a planned response. Often the safest response is to disconnect the affected network or server and run on local control, the same degraded mode drilled for a SCADA failure. Decide in advance who may disconnect what, and confirm that doing so leaves protection and local automatic operation intact.
This guide gives general principles. Confirm with a project design.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.