Power-Control FAT / SAT / Functional Acceptance Framework

How to prove a power-control system works: test plan, FAT with simulation, SAT with live equipment, failure injection, performance measurements, punch lists, documentation and sign-off criteria.

In short. A control system is accepted on evidence, not on belief. The factory acceptance test (FAT) proves the logic against a simulated plant. The site acceptance test (SAT) proves the installed system with real equipment, including failures. Every test has a written precondition, action and expected result. The full power-loss sequence is measured with time stamps, and every failure found is fixed and retested before handover.

Who this page is for: For commissioning engineers, consultants and owners planning FAT and SAT for generator, ATS, PMS and critical power controls.

Key facts

  • FAT tests logic against simulation; SAT tests the real, integrated site.
  • Test cases come from the cause-and-effect matrix: every filled cell is a test.
  • Each case records precondition, action, expected result, actual result and signature.
  • Inject failures: lost signal, controller power cycle, network break, failed sensor.
  • Time-stamp the power-loss sequence from failure to load accepted.
  • A failed test is fixed, retested and recorded; never waived silently.

Stages

StageWhereProves
Document reviewOfficeLogic, drawings and cause-and-effect agree
FATFactory or workshopLogic and panels against simulation
Installation checksSiteWiring, polarity, calibration, insulation, earthing
SATSite, no load then loadEach function with real equipment
Integrated testSiteComplete power-loss and recovery
Performance runSite, under loadStability, sharing, temperatures

Worked example: SAT record for a mains failure (illustrative)

EventExpectedRecordedResult
T0 utility breaker opened 0.0 s 
T1 start command≤ 3 s3.0 sPass
T2 set running≤ 8 s7.1 sPass
T3 voltage and frequency acceptable≤ 12 s10.4 sPass
T4 transferred≤ 15 s11.2 sPass
T5 essential load accepted, frequency recoveredDip ≤ 10%, recovery ≤ 5 sDip 12%, recovery 6 sFail

The fail traced to two large pumps starting in the same step. The load-sequencing delay was changed to start them 5 s apart, the test repeated, and the dip fell to about 7% with recovery within 5 s. Both the fail and the retest went into the record.

Do not sign off a control system without the integrated power-loss test and at least one failure injection, such as a set that fails to start. Normal-sequence tests alone hide the faults that appear in a real outage.

What the plan includes

  • Test cases from the cause-and-effect matrix.
  • For each: precondition, action, expected result, pass or fail, signature.
  • Failure injection: lost signal, controller power cycle, network break, sensor failure.
  • Safety precautions and permits for live tests.
  • Instruments with calibration records and synchronised clocks.

See utility and DG transfer control, commissioning and load bank testing.

Test case record

The site acceptance record for the same spinning mill, case by case. The example above is a timeline — one mains failure measured step by step against a clock — and this is the other half of an acceptance pack: ten separate cases, each with its own precondition and its own verdict, on a four-set two-bus plant. Two failed and one command was correctly refused. Every case here came out of the matrix review, which is where test cases are supposed to come from.

CasePreconditionActionExpectedActual and result
SAT 04Island stable, four sets, 1580 kW, with the PLC deliberately held in stopInject a generator protection operation on G2The G2 breaker opens on its hard-wired trip path without the PLC; restart blocked; capacity recomputed to 1500 kW once the PLC is releasedPass. G2 opened in 95 ms on the direct trip relay with the PLC stopped. Stage 1 then shed as in SAT 11
SAT 09Both buses dead, all four sets stopped, utility restored and healthyOperator confirms the return; the sequence closes Q1 and Q2Each incomer closes only to a bus below 62 V after the 500 ms hold; no live close is offered or possible from any locationPass. Q1 closed at 2.1 s and Q2 at 2.4 s. The live-close command was not available on the HMI
SAT 07Mill on full load, 1580 kW, both incomers closed, all four sets stoppedOpen Q1 and Q2 on the 11 kV side to simulate a utility failureBoth buses below 62 V within 500 ms; all four sets start; G1 and G3 take their dead buses by priority; no two sets close to the same dead busPass. G1 closed at 9.4 s, G3 at 9.8 s. Capacity 1000 kW against a must-keep of 380 kW
SAT 08As SAT 07, with G1 and G3 on loadAllow G2 and G4 to synchronise and closeEach closes only within 5%, 0.2 Hz and 10 degrees, held 500 msPass. G2 closed at 23 s, G4 at 31 s. Capacity 2000 kW, mill at 79%
SAT 11Island stable, four sets, 1580 kWTrip G4 with the mill on full loadUnderfrequency below 48.5 Hz sheds stage 1; load falls to 1160 kW on three sets, 77%Fail. The stage shed correctly but frequency reached 47.6 Hz first. For the 195 ms the shed path took, three sets were carrying 1580 kW, which is 105% of their 1500 kW. Relay delay cut from 100 ms to 60 ms and the stage 1 contactor moved to the direct relay path, giving 155 ms. Retest: 48.2 Hz, recovered in 3 s. Pass
SAT 12Island stable, three sets, 1160 kW, stage 1 already offTrip G3Stage 2 sheds; load falls to 740 kW on two sets, 74%Pass. Frequency reached 48.4 Hz and recovered in 4 s. Two sets carried 1160 kW, 116%, for 155 ms
SAT 14Island stable, buses separate, Q5 openInject a Bus A bus-protection operationEvery Bus A dead-bus close blocked; Q5 blocked; alarm latched until reset by handFail. The block worked in software, but the hard-wired interlock contact in the Q5 closing circuit had been wired to the Bus B relay instead of Bus A. Rewired and reproved by injection on both buses. Pass
SAT 15Island stable, all four setsRemove the Bus B VT MCBDead-bus closing blocked on Bus B; its sync check inhibited; alarm; no spurious closePass. VT supervision operated in 120 ms and no closing was permitted on Bus B
SAT 18Island stable on one set, must-keep load only, 380 kWIssue an operator stop to the last running setCommand refused with a message on the HMI; the set keeps runningPass. Refused and logged. Repeated with two sets running and correctly accepted
SAT 21Island stable, four sets, 1580 kWPower-cycle the PLCOn restart it reads every breaker position and set state before asserting any output, enters Island stable, and operates nothingPass. 14 s to read and report. No output asserted and no breaker moved
     
     

The two failures are worth separating, because they are different kinds of failure and only one of them is a design fault. SAT 11 is a design fault: the logic did exactly what it was told and the arithmetic was wrong, because nobody had multiplied out the shed path against what three sets would be carrying in the meantime.

SAT 14 is not a design fault at all — the logic, the drawing and the settings were all correct, and a single wire was on the wrong terminal. No amount of factory testing finds that one, because at the factory the Bus A and Bus B relays are simulated by the same test set. It is the reason site acceptance exists as a separate stage rather than a repeat of the factory tests.

SAT 21 and SAT 18 are the two cases most often left out of an acceptance pack, and both test a refusal rather than an action. A controller that asserts outputs on restart before reading the plant is the classic way to turn a brief power interruption into a breaker operation nobody asked for, and the only way to know it does not is to cycle the power with the mill on load and watch.

SAT 18 is the same idea applied to a person: the test passes when the system says no, and it was repeated with two sets running to prove the refusal is conditional rather than a blanket block. A pack with no refusal tests in it has only proved that the plant does things.

Note what the last column holds for the two failures: not “fixed”, but the measurement, the change, the new figure and the retest. SAT 11 reads 195 ms, then 60 ms and 155 ms, then 48.2 Hz on the retest — which means the as-built 60 ms on the cause-and-effect sheet can be traced to the reason it is 60 and not 100. A record that said “delay adjusted, retested, pass” would leave the next engineer to rediscover all of it.

Ten cases is not the whole pack; it is the part of it that came from the matrix review’s awkward rows and from the hard-wired paths the cause-and-effect sheet claims. The rest of the pack walks every filled cell of the matrix, and the integrated power-loss timeline — the kind of record worked through in the example above — sits alongside this sheet rather than replacing it. The two answer different questions: the timeline asks whether the plant recovers in time, and these cases ask whether it refuses what it should refuse.

Worked example: planning the FAT (illustrative)

A three-set plant with load shedding whose cause-and-effect matrix produces about 120 test cases:

ItemWorkingAllowance
Individual test cases120 × about 15 minutesabout 30 hours
Failure injections and integrated sequencesAbout 20 scenarios × 30 minutesabout 10 hours
Fixes and retestsCommonly 20 to 30% of test timeabout 10 hours
TotalAbout 50 hoursabout one working week

A FAT planned as a single day for a system of this size will either be rushed or end with tests left for site, where they cost more and carry more risk. Agree the duration from the test count, not from habit.

Classifying what the tests find

CategoryMeaningRule
ASafety or function failureFixed and retested before energising or handover
BFunction works but with a defectFixed by an agreed date, with a temporary measure if needed
CCosmetic or documentationFixed before final acceptance

Every item on the list has an owner, a date and a retest reference. Handover with open category A items is not handover.

Using a load bank at SAT

Many site tests need load the building cannot safely provide on demand: load sharing at 25, 50, 75 and 100%, step response, set-trip shedding at high load and a performance run. A temporary load bank, resistive with a reactive section where reactive sharing must be proved, lets those tests be done in controlled steps without risking production. Plan its connection point, cabling and cooling space with the SAT plan, not on the morning of the test.

What the handover pack should contain

The signed FAT and SAT records with every failure and retest, the punch list with its status, the cause-and-effect matrix, logic and HMI at the tested revision, the settings of every relay and controller as left, the as-built drawings, the degraded-mode procedures and the training record of the operators who will run the plant. Together they are the evidence on which the system is accepted, and the baseline for every future change.

Common mistakes

  • Tests written after the event.
  • No failure injection.
  • Clocks not synchronised across recorders.
  • Failed tests waived without a record.

What to send us

Send the cause-and-effect matrix, single-line diagram and your test plan. WhatsApp 98852 01608 or use the application engineering enquiry.

Evidence note. Times and limits are illustrative; each project sets its own criteria.

Questions engineers ask

How long does a FAT take?

Estimate it from the test count. A three-set plant with about 120 test cases at about 15 minutes each needs about 30 hours, plus about 10 hours of failure injections and integrated sequences and about 10 hours of fixes and retests: around 50 hours, a working week. A one-day FAT for such a system is rushed or incomplete.

What do punch list categories A, B and C mean?

Category A is a safety or function failure, fixed and retested before energising or handover. Category B is a function that works with a defect, fixed by an agreed date with a temporary measure if needed. Category C is cosmetic or documentation, fixed before final acceptance. Every item has an owner, a date and a retest reference.

Is FAT necessary?

For anything beyond a simple single-set panel, yes. Testing logic against a simulation in the factory finds programming and configuration errors where they are cheap and safe to fix, and leaves site time for wiring, equipment and integration. Faults found first on site cost more, take longer and are found with the plant at risk.

Who witnesses tests?

The owner or an engineer representing the owner, together with the contractor who performs the tests. The witness confirms each result, signs the record and agrees how failures are classified and retested. Operations staff should witness key site tests too, because they will run the plant that the tests describe.

Can tests be done at no load?

Many can: logic, interlocks, sequences, alarms and most failure injections. But load sharing, step response, shedding at high load, stability and temperatures can only be proved under load, either the building load where it is safe or a temporary load bank. Plan both stages in the SAT.

How often to retest?

After any change to logic, settings or equipment, retest the affected functions and anything that depends on them. On a schedule, repeat the integrated mains-failure test and key failure injections at least once a year, and drill the degraded modes, so that the system is proved as it is now rather than as it was at handover.

This guide gives general principles. Tests must follow site safety rules.