In short. In a closed transition, the second source connects before the first disconnects, so loads see no break. That brief overlap puts two sources in parallel. It needs synchronism before closing, a strict limit on how long the parallel lasts, protection that stays active throughout, and the utility’s permission when the utility is one of the sources. If the first breaker fails to open in time, the control must trip one source to end the parallel.
Who this page is for: For control and commissioning engineers and facility managers who want no-break transfers for tests and retransfer.
Key facts
- Sequence: both sources healthy, synchronise, close the second breaker, open the first, confirm.
- Typical parallel time limit: well under a second.
- A parallel timer must trip a breaker if the overlap lasts too long.
- Fault level rises while two sources are in parallel; check switchgear ratings.
- Utility approval and suitable interconnection protection are needed for parallel with the grid.
- Earthing arrangements must suit both sources in parallel.
Sequence
- Both sources healthy.
- Synchronise: voltage, slip and angle within limits. See synchronising.
- Close the second breaker; parallel timer starts.
- Open the first breaker.
- Confirm transfer; timer stops.
- If the first breaker has not opened at the time limit, trip a breaker to end the parallel.
Worked example: retransfer after an outage (illustrative)
| Check | Setting or finding |
|---|---|
| Utility parallel permitted? | Yes, momentary only, with interconnection protection approved |
| Synchronising window | Voltage within 5%, slip under 0.2 Hz, angle under 10 degrees |
| Parallel time limit | 200 ms |
| Fault level in parallel | Utility plus generator contribution: within the main board’s rating after a study |
| Test result | Overlap measured at about 120 ms; no flicker on the load |
| Failure test | Generator breaker held closed for the test: parallel timer tripped the utility breaker at 200 ms, ending the parallel |
The fault level check was the deciding item: a smaller board on the same site was found to be under-rated for the parallel condition, so closed transition was limited to the main board only. See fault current studies.
Do not enable closed transition without a parallel time limit that trips a breaker on its own, a fault level check for the parallel condition and, for the utility, written permission. A stuck breaker otherwise leaves two sources in parallel indefinitely.
Why it is used
- Tests and maintenance transfers without a load outage.
- Retransfer from generator to utility after an outage, without a second break.
See interconnection studies, utility and DG synchronisation and earthing studies.
Closed transition settings
| Item | Value |
|---|---|
| Utility permission and conditions | |
| Synchronising window | |
| Parallel time limit | |
| Fault level check in parallel | |
| Failure test result |
Worked example: where the 200 ms limit comes from (illustrative)
The parallel time limit has to be longer than a healthy transfer and shorter than the time the system can safely stay in parallel. A healthy overlap is set by the breakers.
| Time from close command | Event |
|---|---|
| 0 ms | Close command to the incoming breaker; parallel timer armed |
| about 70 ms | Incoming breaker closes; sources in parallel; open command to the outgoing breaker |
| about 70 + 50 = 120 ms | Outgoing breaker opens; overlap of about 50 ms from contact to contact |
| 200 ms | Parallel timer: if both are still closed, trip a breaker |
The measured 120 ms in the worked example above is the time from the close command to the end of the transfer. A timer at 200 ms leaves room for normal breaker variation and still ends a stuck parallel before the utility’s own limit. Take the breaker times from timing tests on the actual breakers, and re-check them each year, because a slowing mechanism eats into the margin.
Worked example: what an imperfect close draws (illustrative)
Closing with a phase angle between the sources drives a current set by the voltage difference across the two sources’ reactance: about 2 × sin(angle ÷ 2) per unit of voltage, divided by the total reactance. With a generator subtransient reactance of 0.12 and the grid behind it about 0.03, on the generator’s base, the total is about 0.15 per unit.
| Close angle | Voltage difference | Closing current |
|---|---|---|
| 5 degrees | 2 × sin 2.5° ≈ 0.087 per unit | 0.087 ÷ 0.15 ≈ 0.58 times rated |
| 10 degrees | 2 × sin 5° ≈ 0.174 per unit | about 1.2 times rated |
| 20 degrees | 2 × sin 10° ≈ 0.347 per unit | about 2.3 times rated |
The current comes with a matching torque step on the shaft and coupling. A 10 degree window keeps it to about rated current, a jolt the set handles every day; a close at 20 degrees more than doubles it. That is why the synchronising window is tight, why the synchroniser compensates for breaker closing time, and why an independent sync-check relay must permit every close.
Open, hard closed and soft closed transition compared
| Type | What the load sees | Parallel time | Needs |
|---|---|---|---|
| Open transition | A break, from a fraction of a second to several seconds | None | Interlocks only |
| Delayed open transition | A longer break, letting motor voltages decay | None | Interlocks and a timer |
| Hard closed transition | No break; a load step on the incoming source | Well under a second | Synchronising, sync-check, parallel timer |
| Soft closed transition | No break and no step; load ramped across | Seconds to minutes | All of the above, plus load control and full parallel protection |
Soft transfer is gentler on the generator, which takes its load gradually, but the longer parallel usually brings the utility’s full parallel-operation requirements with it, including loss-of-mains protection. Hard transfer is the common choice where the aim is simply no break on retransfer.
A fault during the overlap
For the fraction of a second the sources are in parallel, a fault is fed by both. On a board fed by a 1600 kVA transformer at 6% impedance, about 2226 A ÷ 0.06 ≈ 37.1 kA, with a 750 kVA set adding about 1043 A ÷ 0.12 ≈ 8.7 kA, the prospective fault reaches about 45.8 kA. A 50 kA board passes; a 36 kA sub-board connected to the same bus during the transfer would not. Protection must stay fully active through the overlap, and the closed-transition logic should be blocked on any bus whose ratings were not checked for the combined fault.
Neutrals and earth-fault protection during the overlap
With four-pole switching and each source earthed at its own neutral, the overlap briefly connects two neutral-earth links in parallel. Neutral current then divides between them, and residual earth-fault elements on the incomers can see a false earth fault for the duration. Either the earthing design uses a single neutral-earth point common to both sources, or the affected earth-fault elements are given a delay longer than the overlap, never simply switched off. Check this before the first transfer, not after the first nuisance trip.
Use every transfer as a test
The controller can record the overlap time, close angle, closing current and any timer operation for every transfer. A rising overlap time over months points to a breaker mechanism that needs service before it becomes the stuck breaker the timer exists for. Review the records monthly, and repeat the deliberate stuck-breaker test at least once a year so the timer path itself is proved.
Commissioning closed transition
| Step | Test | Pass when |
|---|---|---|
| 1 | Phase sequence and VT wiring checked on both sources | Sync-check reads zero angle with both sources from one supply |
| 2 | Synchroniser on a dead bus or with the breaker racked to test | Close command issued inside the window, compensated for closing time |
| 3 | Sync-check relay outside the window | Close blocked at excessive slip, voltage difference and angle |
| 4 | Live transfers in both directions | Overlap time, close angle and current recorded; no load disturbance |
| 5 | Stuck-breaker test | Parallel timer trips the chosen breaker at the set time |
| 6 | Protection during the overlap | No earth-fault or reverse power trips on healthy transfers |
| 7 | Failure of one source mid-sequence | Logic aborts to a safe state with the load supplied |
Retransfer timers after an outage
After an outage the returning grid is often unsteady, so the controller waits before transferring back. A typical sequence is a mains-stable timer of a few minutes, then the closed retransfer, then a cool-down run of the engine unloaded for a few minutes before it stops. If the grid fails again during the mains-stable timer, the timer simply restarts and the load stays on the generator. Without that delay, a site can bounce between sources with every grid disturbance, and each bounce is a load step for the generator and an opportunity for a closed transition to go wrong.
When closed transition is the wrong answer
- When the loads ride through a short break anyway, for example through a UPS: open transition is simpler and needs no parallel provisions.
- When the switchgear is not rated for the combined fault level and cannot be uprated economically.
- When the utility will not permit parallel operation, or only with protection the site cannot justify.
- When the breakers are old and slow, so the overlap would be long and uncertain.
In those cases a fast open transition, with motor loads restarted in a planned sequence, usually gives most of the benefit with none of the parallel risk.
What a good transfer record looks like
For each closed transfer, the controller should log the date and time, the direction, the slip, voltage difference and angle at the close command, the measured close angle, the peak current during the overlap, the overlap time from contact to contact, and whether the parallel timer operated. Ten such records side by side make drift obvious: a close angle creeping upwards points to a breaker closing slower than the time set in the synchroniser, and an overlap creeping upwards points to the outgoing breaker. Either is a maintenance item found months before it becomes a fault.
Common mistakes
- No parallel timer.
- Fault level not checked for the parallel condition.
- Paralleling with the utility without permission.
- Stuck-breaker case never tested.
What to send us
Send the single-line diagram, switchgear ratings and the utility’s conditions. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. Settings and times are illustrative; utility conditions and studies govern.
Questions engineers ask
What current flows if a closed transition closes out of phase?
About 2 times the sine of half the angle, in per unit voltage, divided by the total reactance. With 0.15 per unit of reactance, a 10 degree close draws about 1.2 times rated current and a 20 degree close about 2.3 times, with a matching torque step on the shaft. That is why the synchronising window is about 10 degrees.
What is the difference between hard and soft closed transition?
Hard closed transition overlaps the sources for well under a second and moves the whole load in one step. Soft closed transition stays in parallel for seconds to minutes while the load is ramped across, which is gentler on the generator but usually brings the full utility requirements for parallel operation, including loss-of-mains protection.
Is closed transition always better?
No. It avoids a break, which matters for sensitive loads and for testing without an outage, but it adds synchronising, a parallel timer, a fault level check for the parallel condition, earthing changes and usually utility approval. Where the load can ride through a short break, open transition is simpler and has fewer ways to fail.
Does the utility need to approve?
Usually yes, for any parallel operation with its network, even momentary. The utility typically sets the maximum parallel time, the interface protection, the synchronising requirements and the tests it wants to witness. Generator-to-generator closed transition within a private site, with the tie to the grid open, needs no utility approval.
How long can the overlap last?
As short as the breakers allow and within any utility limit, commonly well under a second for hard closed transition. A healthy overlap is the outgoing breaker opening time after the incoming one closes, often around 50 to 100 ms. A parallel timer, here 200 ms, trips a breaker if the overlap runs past the limit.
Can generators do it alone?
Yes. Transfers between two generator buses, or between generators, use the same sequence: synchronise, close, open, confirm, with a parallel timer. No utility approval is needed, but the switchgear must still be rated for the combined fault level and the earthing must suit both sources being in parallel briefly.
This guide gives general principles. Follow the utility’s rules and local regulation.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.