Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

Automatic Load Restoration and Restart Control

How to restore loads after an outage or shed event: staged restart sequence, step sizes, delays, motor residual voltage, permissives, manual holds and verification that the source stays stable.

In short. Restoring everything at once can undo the recovery. A good restart sequence returns loads in stages, each sized to what the source can accept. It waits for voltage and frequency to recover between stages, holds motors until their residual voltage has decayed, and starts the largest motors when the most capacity is free. It checks that each step worked before moving on.

Who this page is for: For control engineers, plant managers and consultants setting up restart after an outage or a generator transfer.

Key facts

  • Restore critical loads first, then essential, then the rest.
  • Keep each step within the generator’s block-load capability.
  • Wait for voltage and frequency to settle between steps.
  • Delay motor restarts until residual voltage has decayed.
  • Start the largest motor while the most capacity is free.
  • Give operators a manual hold for loads that need checks.

Sample stages

StageLoadsReason
1UPS, control power, emergency lightingSafety and visibility first
2Ventilation, fire systems, critical pumpsLife safety and process protection
3Largest motor (chiller or motor)Most capacity available
4Other essential loadsWithin remaining capacity
5Comfort and deferrable loadsLast, if capacity allows

Worked example: restart on a 1000 kVA set (illustrative)

The set is 800 kW, and it accepts steps of about 35% (280 kW) while staying within its frequency limit.

StepLoad addedRunning totalWait before next
1 at transferUPS input and emergency loads, 180 kW180 kW5 s
2Fire pumps and ventilation, 150 kW330 kW5 s
3Chiller, starting equivalent about 260 kW, running 120 kW450 kW20 s
4Process pumps, 140 kW590 kW10 s
5Lighting and offices, 100 kW690 kW (86%)Hold the rest

Before the sequence was set, everything restarted at transfer, and the set tripped on underfrequency within a minute. See load-step response and motor starting.

Do not let motors restart automatically the instant the supply returns. Re-closing onto a motor that is still spinning with residual voltage can produce damaging current and torque. Use a restart delay.

Check each step

  • Voltage and frequency back within limits.
  • No protection pickup.
  • Breaker feedback confirms the step.
  • If a step fails, stop and alarm; do not continue blindly.

Transformers also have large switch-on currents. See transformer energisation, load shedding and sequence design.

Restoration plan

StepLoadskW added (or starting kW)Delay
1   
2   
3   
4   

Sizing a step that includes a motor

A restoration step is usually limited by its largest motor, not by its total running load, because a motor draws several times its running current while it accelerates. The generator sees that starting current as a sudden reactive load, and its voltage dips until the voltage regulator catches up. The same motor can be a small step or a large one depending on how it is started, so the starting method belongs in the restoration plan alongside the motor’s rating.

Take a 75 kW motor with an efficiency of 92% and a power factor of 0.86. Its running input is 75 / (0.92 × 0.86), about 95 kVA. The table compares three starting methods on a 1000 kVA generator that is already carrying 400 kVA, using the screening estimate dip = Sstart / (Sstart + (1000 − 400) / X″d), with a subtransient reactance X″d of 0.15 per unit.

Starting methodStarting current (multiple of running)Starting kVAEstimated voltage dip
Direct on lineAbout 656912.5%
Soft starter set to 3 times32846.6%
Star-deltaAbout 2 (one third of direct on line)1904.5%

On this set, the motor started direct on line needs a step of its own, with nothing else in it, and should be started while the most capacity is free. Started through a soft starter, it can share a step with other loads. The estimate is a screening figure; the generator maker’s transient data and a motor-starting study decide the final plan. See the motor-starting generator capacity calculator and large motor starting on diesel generators.

How long to wait for residual voltage to decay

When an induction motor loses its supply, it keeps turning and its rotor flux keeps generating a voltage at its terminals. That residual voltage falls away over a time set by the motor’s open-circuit time constant, which for low-voltage motors is commonly between about half a second and a few seconds, longer for large machines. If the supply is reconnected while the residual voltage is still high and out of phase with the supply, the motor can see a current and torque well above a normal start.

The decay is close to exponential, V = V0 × e−t/T. A widely used criterion is to reconnect only after the residual voltage has fallen to about 25% of rated, which takes T × ln 4, about 1.39 time constants.

Open-circuit time constant TTime to fall to 25%Restart delay to set (with margin)
0.5 s0.69 s2 s
1 s1.39 s3 s
2 s2.77 s5 s
3 s4.16 s7 s

The time constant is a motor property, so ask the motor maker for it on large machines rather than assuming. Where a motor must restart quickly, for example a process pump that cannot stop for long, a residual-voltage relay that permits reconnection once the measured voltage has decayed is better than a fixed timer, because it does not wait longer than necessary. Most restoration sequences have far longer gaps between steps than these delays, so the risk is usually confined to motors whose contactors stay closed through a short break and reconnect the moment the supply returns.

Writing restoration as a state machine

A restoration sequence written as a list of timed outputs works when every step succeeds and fails badly when one does not. Written as a state machine, each step has a defined way in, a check it must pass and a defined way out if the check fails. That structure also makes the sequence easy to test, because each state and transition can be exercised on its own.

StateWhat the controller doesLeaves when
IdleNothing; supply not available or restoration not requiredSupply healthy and loads waiting: go to Armed
ArmedConfirms the source is stable and records which loads to restoreSource stable for its set time: go to Issue step
Issue step nCloses the breakers or releases the contactors for step nCommands sent: go to Verify step n
Verify step nChecks breaker feedback, voltage, frequency and protection pickupsAll good after the wait: next step, or Complete. Any check fails: go to Hold
HoldStops issuing steps, alarms the operator, keeps what is already restoredOperator releases or aborts
AbortLeaves the plant as it is and returns control to the operatorOperator resets
CompleteRecords the restoration and its durationReturns to Idle

Two rules keep the machine safe. Every state has a timeout, so a breaker that never reports closed cannot leave the sequence waiting forever. And a loss of supply in any state sends the machine back to Idle immediately, so a second outage part way through restoration starts the process again from the beginning instead of resuming from a step that no longer matches the plant. See control state machines and sequence engineering.

Restoring loads after a shed without shedding them again

After a generator trip and a load-shedding event, the plant runs on fewer sets with some feeders open. When another set has started and joined, those feeders can come back. The danger is restoring a feeder that pushes the plant straight back over its limit, so that it is shed again, then restored, then shed: a cycle that wears breakers and disrupts the loads more than staying off would.

The cure is a margin and a delay. Restore a feeder only if the spare capacity exceeds the feeder’s present load plus a margin, and only after that spare capacity has been available for a sustained time. For example, a plant has 1600 kW of online capacity carrying 1250 kW, so 350 kW is spare.

The next feeder to restore last carried 220 kW, and the margin is 10% of online capacity, 160 kW. The test needs 220 + 160 = 380 kW, which is more than 350 kW, so the feeder stays off until another set joins or the load falls. Use the feeder’s load from just before it was shed, not its nameplate, and restore feeders in the reverse order of shedding, highest priority first. See load-shedding automation and priority logic.

Inhibits, holds and the operator’s place in the sequence

Automatic restoration should never be all or nothing. Some loads need a person to check them before they come back: a process line that may have stopped part way through a batch, a lift whose car must be confirmed empty, a large motor that tripped on its own protection rather than on loss of supply. Each of these needs a restoration inhibit that the sequence respects, so that the automatic steps carry on around it and leave that load for an operator to release.

  • Per-load inhibit: set by the operator or by the load’s own trip, it removes one load from the sequence until it is cleared.
  • Sequence hold: pauses the whole sequence at the current step, for example while an engineer checks a fault indication.
  • Protection lockout: any feeder that opened on its own protection stays open until reset locally, whatever the sequence wants.
  • Manual release: lets an operator bring a held load back once the controller confirms there is capacity for it.

Each of these states should show clearly on the operator screen, with the reason it was set and who set it. A sequence that finishes with three loads still held and no explanation on the screen leaves the next shift guessing whether they were forgotten or deliberately kept off.

Restoring on a generator and restoring on the utility

The same plant often needs two restoration plans. On a generator, every step is limited by the set’s step-load acceptance and transient reactance, so steps are smaller and waits longer. On a strong utility supply, voltage and frequency barely move when a step is added, so steps can be larger and the limits come from elsewhere: transformer energising currents, the utility’s own protection, and the inrush of many power supplies switched together.

A sequence tuned for the generator will be needlessly slow on the utility, and a sequence tuned for the utility will trip the generator. The controller should know which source it is restoring onto and select the matching plan, and both plans should be tested.

Testing a restoration sequence

Test the sequence on the real source with real loads, at least once on the generator and once on the utility. Record, for each step, the time it was issued, the time it was confirmed, the lowest voltage and frequency reached and the time to recover. Then test the failure paths: hold a breaker open so that its feedback never arrives, and confirm the sequence holds and alarms; remove the supply part way through and confirm the sequence returns to Idle; and restore after a shed event with the load deliberately set just above the restoration margin, confirming that the feeder stays off.

Common mistakes

  • Everything restarting at once.
  • Largest motor started last, when capacity is least.
  • No delay for residual voltage.
  • Sequence continuing after a failed step.

What to send us

Send the load list with motor ratings and starting methods and the generator data. WhatsApp 98852 01608 or use the application engineering enquiry.

Evidence note. Step sizes and delays are illustrative; generator data and studies govern.

Questions engineers ask

How long should a motor wait before it is reconnected after a break?

Until its residual voltage has decayed, commonly to about 25% of rated. The decay is roughly exponential, so that takes about 1.39 times the open-circuit time constant of the motor: around 1.4 s for a time constant of 1 s and around 4.2 s for 3 s. Set the restart delay with margin above that, or use a residual-voltage relay that measures the decay directly. Ask the motor maker for the time constant on large machines.

Can restoration be driven by the spare capacity the plant actually has?

Yes, and it should be after a load-shedding event. Restore a feeder only when online capacity minus present load exceeds the last measured load of that feeder plus a margin, and only after the spare capacity has held for a set time. For example, with 350 kW spare, a 220 kW feeder and a 160 kW margin, the feeder stays off. This stops a restored feeder being shed again straight away.

Why not restore everything together?

Because the combined starting current of motors, transformers and cooling loads restarting at once can be several times the running load, enough to pull a generator voltage and frequency down until protection trips it or contactors drop out, undoing the restoration. Steps sized to the spare capacity, largest motors first, avoid that.

How long between steps?

Long enough for voltage and frequency to recover inside their limits after each step, typically a few seconds, often 3 to 10 s depending on the step size and the generator response. Better than a fixed delay is a check: proceed when frequency is above about 49.5 Hz and voltage above about 95% for a set time.

Should restoration be automatic?

For critical loads, yes, because they must return without waiting for a person. Some loads need operator approval first, such as processes that are unsafe to restart without checks, large motors after a long outage, or equipment that may have been worked on during the event. The control philosophy lists which is which.

What after a shed event?

Hold the shed loads off until real spare capacity returns, usually a standby set coming on line, then restore them one feeder at a time when spare capacity exceeds each feeder last measured load plus a margin and has held for a set time. Restoring early just makes the scheme shed the same feeder again.

Values are illustrative. Tune on site.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.

CallWhatsAppEnquire