Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

Dead-Bus, Live-Bus and Sync-Check Control Logic

How to design breaker closing logic by bus state: dead-bus permissives and lockout, live-bus synchronising, sync-check windows, voltage sensing faults and preventing double closing.

In short. Before a breaker closes, the control must know the state of both sides. A live source onto a dead bus is allowed under conditions, and only one source may do it. A live source onto a live bus is allowed only inside the synchronising window. Everything else is blocked. The classic failures are two generators racing to close onto the same dead bus, and a blown VT fuse that makes a live bus look dead, so the scheme must treat any doubtful measurement as a reason not to close.

Who this page is for: For control and protection engineers, panel builders and commissioning teams working on generator paralleling and transfer schemes.

Key facts

  • Dead bus: all phases below a low threshold (often around 10 to 20%) for a set delay.
  • Live bus: all phases above a high threshold (often around 80 to 90%).
  • Only one breaker may close to a dead bus; arbitrate with priority and a hard-wired interlock.
  • Live to live needs voltage, frequency and angle inside the sync window for a minimum stable time.
  • A VT fuse failure must block closing, never permit a dead-bus close.
  • A delay on the dead decision lets motor and capacitor residual voltage decay.

Closing cases

Source sideBus sideAction
LiveDeadClose allowed if the source is healthy, the bus has no fault or lockout, and no other breaker holds the dead-bus permission
LiveLiveClose only inside the sync-check window
DeadLiveNormally blocked (back-energising a source)
DeadDeadNothing to close; wait for a source
Uncertain (sensing fault)AnyBlocked and alarmed

Worked example: the dead-bus race (illustrative)

Two generators restart after a blackout and reach rated voltage within a fraction of a second of each other.

TimeWithout arbitrationWith priority and interlock
0 sBoth see a dead busBoth see a dead bus; set A holds priority
0.1 sBoth close: two unsynchronised sets connected, severe current and torque shockSet A closes; the interlock blocks set B’s dead-bus close
2 sDamage, tripsSet B rechecks, finds a live bus, starts synchronising
A few seconds later—Set B closes inside the sync window

A second test simulates a blown VT fuse on the bus while it is live. The scheme detects the failure (the VT fuse or MCB monitor operates, or the bus VT reads zero while a second VT or the incomer current shows the bus is energised) and blocks closing instead of treating the bus as dead.

Never let a single lost voltage signal permit a dead-bus close. A blown VT fuse is one of the classic causes of out-of-phase closing. Supervise VT fuses, compare measurements, and treat any sensing doubt as a block.

Dead-bus closing rules

  1. Confirm all phases are below the dead threshold for the set delay.
  2. Confirm no protection trip, lockout or closed earth switch on the bus.
  3. Grant the permission to one source by priority, backed by a hard-wired interlock.
  4. Close, then confirm voltage appears on the bus.
  5. Release the permission and let other sources synchronise.

Energise transformers in sequence to limit inrush. See inrush studies.

Live-bus synchronising

Require voltage, frequency and angle inside their windows, with the generator slightly fast, held for a minimum stable time before the close command. An independent sync-check relay supervises the synchroniser. See automatic synchronising.

Hard-wired and mechanical backups

For critical bus ties and dead-bus permissions, a hard-wired or key interlock backs up the software, so a program error cannot close two sources together. See interlocking and transfer logic and main-tie-main control.

Tests to run

  • Simultaneous start of all sets onto a dead bus.
  • VT fuse removed on a live bus.
  • Breaker fails to close; breaker fails to open.
  • Residual voltage from motors after a transfer.
  • Communication loss between controllers.

Closing permissive checklist

Every closing device on the same spinning mill, seven of them, against the thresholds actually set. The example above follows two sets through one dead-bus race; this is the document that settles every such race in advance, on a different and larger plant with four sets, two buses and a coupler — which is where arbitration stops being a two-way question. The mill does not run in parallel with the utility, and that single decision shapes four of the seven rows.

BreakerDead threshold and delayLive thresholdPriorityHard-wired interlockTests passed
G1, set breaker on Bus AAll three phases below 62 V, held 500 msAbove 353 V on all phases; sync check within 5%, 0.2 Hz and 10 degrees, stable 500 ms1 on Bus AYes — against a G2 dead-bus close, and against Bus A protection operatedFAT 12, SAT 07, SAT 08
G2, set breaker on Bus AAll three phases below 62 V, held 500 msAs G12 on Bus AYes — against a G1 dead-bus close, and against Bus A protection operatedFAT 12, SAT 07, SAT 08
G3, set breaker on Bus BAll three phases below 62 V, held 500 msAs G1, referred to Bus B1 on Bus BYes — against a G4 dead-bus close, and against Bus B protection operatedFAT 12, SAT 07, SAT 08
G4, set breaker on Bus BAll three phases below 62 V, held 500 msAs G1, referred to Bus B2 on Bus BYes — against a G3 dead-bus close, and against Bus B protection operatedFAT 12, SAT 07, SAT 08
Q1, transformer incomer to Bus AAll three phases below 62 V, held 500 ms. This is the only way Q1 may closeNo live close. The mill never parallels with the utility, so a live Bus A must be given up firstDead close only, and only after the operator confirms the returnYes — against any set breaker closed on Bus A, and against Q5 closedFAT 15, SAT 09
Q2, transformer incomer to Bus BAs Q1, referred to Bus BNo live closeDead close only, operator confirmedYes — against any set breaker closed on Bus B, and against Q5 closedFAT 15, SAT 09
Q5, bus couplerDead-bus closing blocked entirely. Q5 is never the device that energises a dead busBoth buses above 353 V; sync check between Bus A and Bus B within 5%, 0.2 Hz and 10 degrees, stable 500 msNone. Q5 takes no part in dead-bus arbitrationYes — against either bus protection operated, and against Q1 or Q2 closedFAT 21, SAT 14
      
      

Two buses turn arbitration from a race into a pair of races, and the useful consequence is that priority is written per bus rather than per plant. G1 and G3 both hold priority 1, because they are competing for different dead buses and there is no reason to make one wait for the other. Each interlock is therefore written against the one set it genuinely conflicts with. The mistake this layout avoids is a single plant-wide priority list, which would hold G3 back behind two Bus A sets for no electrical reason and would add about ten seconds to the time Bus B spends dead.

The third column earns its place through the two rows where the answer is “no live close”. Because the mill never parallels with the utility, Q1 and Q2 can only ever close to a dead bus, and returning from island is therefore an open transition: the sets come off, the buses go dead, and only then do the incomers close.

That costs the mill a short interruption on the way back, which is accepted and planned for, and in exchange it removes an entire class of failure — there is no setting, no sync relay and no permissive anywhere on this plant whose malfunction could parallel 2000 kW of generation with the grid. Writing “no live close” in a cell is a cheaper and more durable protection than a correctly set sync check that somebody could change.

Q5 is the row most worth copying. A bus coupler is the obvious device to energise a dead bus from the healthy one, and that is exactly why its dead-bus close is blocked outright here: during a blackout the coupler would connect two dead buses and both sets of priority logic would then be arbitrating over one combined bus, with each bus’s own sets racing across the coupler.

Blocking it keeps the two races independent, as the priority column assumes. Q5 then does what a coupler is actually good for — joining two live, synchronised buses once both have their own generation — and its interlock against Bus A or Bus B protection stops it being used to re-energise a bus that has just had a fault on it.

One point on the thresholds themselves. 62 V is 15% of 415 V and 353 V is 85%, which leaves a wide band between dead and live where nothing closes at all — and that gap is deliberate. The 500 ms hold on the dead decision does the same job in time rather than in voltage: it lets the mill’s motor load and its power factor capacitors finish feeding the bus before anything is declared dead, which on a spinning mill with hundreds of motors is not a short interval. A dead-bus decision taken in 50 ms would be taken while the bus is still being driven by the plant itself.

Worked example: dead and live thresholds on a 415 V bus (illustrative)

DecisionSettingOn 415 V line to lineDelay
DeadAll three phases below 20%Below about 83 VAbout 1 s, so motor residual voltage decays
LiveAll three phases above 85%Above about 353 VAbout 0.5 s stable
UncertainBetween the two, or phases disagreeingAbout 83 to 353 VBlock closing and alarm

The gap between dead and live is deliberate. A bus at 200 V is neither safe to close onto as dead nor fit to synchronise to as live; it usually means motors still running down, a failing source or a sensing fault, and the only correct action is to wait or alarm. Requiring all three phases for both decisions also catches a single blown VT fuse, which shows one phase low while the others are healthy.

Ways to give only one breaker the dead bus

MethodHow it worksWatch for
Hard-wired permission lineA single signal that only one controller can take; taking it blocks the othersTest what happens if the line breaks: it must block, not permit
Fixed priority with a delay ladderSet A may close at once, set B only after a delay and a fresh dead-bus checkThe delay must exceed A’s closing time plus margin
Controller network arbitrationControllers agree over their link which one closesLoss of the link must fall back to a safe rule, never to all closing

Critical plants combine two: network arbitration for normal operation and a hard-wired permission line as the independent backstop, as in the worked example above.

Commissioning checks for closing logic

  • Each source closes onto a dead bus alone, and the others are blocked while it holds permission.
  • Two sources reaching voltage together: only one closes, by test, not by assumption.
  • A bus in the uncertain band: every close is blocked and alarmed.
  • A VT fuse removed on the bus and on each source: closing is blocked.
  • Live to live outside the sync window: blocked; inside it: permitted only after the stable time.

Record each result with the voltages and times seen. These are the tests that find the faults which otherwise appear only after a real blackout.

Common mistakes

  • No arbitration between sets for the dead bus.
  • No VT fuse supervision.
  • Software-only interlocks on critical ties.
  • No delay for residual voltage.

What to send us

Send the single-line diagram, the VT and sensing arrangement and the present closing logic. WhatsApp 98852 01608 or use the enquiry form.

Evidence note. Thresholds and times are typical values for illustration; controller and switchgear makers’ data govern.

Questions engineers ask

What voltages define a dead bus and a live bus at 415 V?

A common approach is dead when all three phases are below about 20%, about 83 V line to line, for about 1 s, and live when all three are above about 85%, about 353 V, for about 0.5 s. Anything between, or phases disagreeing, is uncertain: block every close and alarm, because it usually means motors running down or a sensing fault.

How is only one breaker allowed to close onto a dead bus?

By arbitration: a hard-wired permission line that only one controller can hold, a fixed priority with a delay ladder and a fresh dead-bus check for the others, or network arbitration between controllers. Critical plants combine network arbitration with a hard-wired line as an independent backstop, and test two sources reaching voltage together.

How low is “dead”?

Low enough that closing onto it cannot meet a voltage that matters, commonly all three phases below about 20% of nominal, about 83 V line to line on 415 V, held for a delay of about a second so motor and capacitor residual voltage has decayed. Anything between the dead and live thresholds is treated as uncertain and blocks closing.

Why a time delay?

Because running motors and charged capacitors keep a decaying voltage on a disconnected bus for a short time, and that voltage drifts in phase. Without a delay, the bus can be declared dead while a residual voltage is still present, and a source closing onto it meets an out-of-phase voltage. A delay of about a second, or a residual-voltage check, avoids that.

Can software alone prevent double close?

Not for critical ties. Software can fail, be changed or be fed a wrong signal, so the last guard against two sources closing onto the same dead bus, or two unsynchronised sources paralleling, must be a hard-wired permission line or a mechanical interlock that works whatever the controllers do. Software is the extra layer.

What about black start?

Black start is the case where the dead-bus logic matters most, because every source may start at once after a blackout. The black-start sequence names the first source, which closes onto the dead bus through this logic, and the others then synchronise to it. Test it with the grid isolated, including two sources reaching voltage together.

This guide gives general principles. Confirm with a project-specific design.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.

CallWhatsAppEnquire