Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

Control-Power and Fail-Safe Architecture

How to design control power: DC and UPS supplies, battery sizing, redundancy, monitoring, earth-fault detection and the fail-safe state of each device when power or signals are lost.

In short. Control power is the supply that lets protection, breakers and controllers act when the main supply has gone. If it fails, the plant cannot trip, close or start. It is often the real single point of failure. A good design has redundant chargers or batteries, monitored battery health and supervised trip circuits, and it defines a safe state for every device on loss of power or signal.

Who this page is for: For protection, control and maintenance engineers on generator plants, substations and critical facilities.

Key facts

  • A breaker that needs power to trip cannot trip with a dead control battery.
  • A generator with a flat starting battery has zero capacity.
  • Use redundant chargers, and battery sets sized for the outage duty.
  • Monitor battery voltage, charger status, earth faults and trip-circuit health.
  • Define the safe state of each device on loss of control power.
  • Test batteries under load, not only by float voltage.

Architecture

ElementGood practice
DC systemTwo chargers with one battery, or two battery sets, sized for trip, close and control load through the outage
DistributionSeparate, protected circuits for each panel
MonitoringBattery voltage, charger fail, DC earth fault
Trip circuitsSupervised for continuity
Generator startingOwn batteries and chargers, monitored. See starting systems

See DC control power and trip circuits.

Worked example: sizing a switchboard battery (illustrative)

LoadWorkingEnergy
Standing load (relays, controls, indication)4 A × 3 h12 Ah
Breaker trips at start of outage (6 coils)6 × 10 A, briefPeak 60 A; negligible Ah
Breaker closes during restoration (6, one at a time)15 A close coil, then spring-charging motor about 5 A for about 10 s, per breakerPeak about 20 A; negligible Ah
Allowance for ageing and temperature× 1.25 on 12 Ah, then corrected for the 3-hour discharge rate15 Ah at the 3-hour rate, about 20 Ah nominal; chosen 24 Ah

The battery must also deliver the 60 A trip peak at the start, and each breaker’s close and spring-charging current at the end of the 3 hours, without the voltage falling below the coils’ minimum. That check against the maker’s short-time discharge data, not the 15 Ah figure alone, decided the 24 Ah choice. See single points of failure.

Do not trust a DC system because the charger is running. Test the battery under load, supervise trip circuits, and alarm charger and earth faults; a failed battery is discovered otherwise only when a breaker will not trip.

Safe states

  • Protection trips must work from the battery with the charger off.
  • Decide for each breaker whether loss of control power holds it, opens it or blocks closing.
  • Controllers on loss of power go to a defined state on restart. See degraded modes.

Control power check sheet

ItemValue or status
Battery capacity and last load test 
Chargers: number and alarm 
DC earth fault monitoring 
Trip circuit supervision 
Generator starting batteries tested 

Worked example: will the coils still work at the end of the outage? (illustrative)

A breaker coil must operate at the lowest voltage the DC system will deliver, after the battery has discharged and after the voltage drop in the cable. Switchgear standards commonly require shunt trip coils to operate down to about 70% of rated voltage and closing coils down to about 85%. Take a 110 V lead-acid battery of 55 cells, discharged to 1.8 V per cell, feeding a breaker 80 m away through 2.5 mm² copper.

CheckWorkingResult
Battery at end of discharge55 × 1.899 V
Loop resistance, 2.5 mm²160 m × 0.0074 Ω/mabout 1.18 Ω
Trip coil, 10 A, needs 77 V99 − 10 × 1.18 ≈ 87.2 VPasses
Close coil, 15 A, needs 93.5 V99 − 15 × 1.18 ≈ 81.2 VFails
Close coil with 10 mm², 0.00183 Ω/m160 × 0.00183 ≈ 0.29 Ω; 99 − 15 × 0.29 ≈ 94.6 VPasses, just

The trip circuit passes and the close circuit does not: after a three-hour outage the breakers would trip correctly but could not be closed again to restore supply. Larger cable, a closer distribution point or a battery with more cells solves it. Do this check for the furthest breaker on every DC circuit, at the end-of-discharge voltage, not the float voltage.

Why the second DC earth fault is the dangerous one

DC control systems are normally unearthed, so a single earth fault on either pole draws no current and changes nothing; the system keeps working. That is exactly why it is dangerous to leave: a second earth fault on the other pole, or in the right place on the same pole, can bypass a contact and energise a trip or close coil by itself, or short a supply so that nothing can operate. DC earth-fault monitoring detects the first fault while it is harmless. Find it promptly by switching off circuits one at a time while watching the monitor, during a planned window.

Worked example: sizing the charger (illustrative)

The charger must carry the standing load and recharge the battery within an acceptable time after an outage. For the 24 Ah battery above with a 4 A standing load, recharging the 24 Ah plus about 10% for charging losses within 8 hours needs 24 × 1.1 ÷ 8 ≈ 3.3 A. Adding the standing load gives about 7.3 A, so a 10 A charger is chosen. With two chargers each able to do this alone, either can fail without the battery running down.

Battery types for control power

TypeStrengthsWatch for
Vented lead-acidLong life, condition visible, tolerant of abuseTopping up, ventilation for hydrogen, a dedicated room
Valve-regulated lead-acidSealed, compact, little maintenanceShorter life, very sensitive to high temperature, failure can be sudden
Nickel-cadmiumWide temperature range, very long life, tolerant of deep dischargeMore cells for the same voltage, disposal rules

In hot switchrooms, life falls sharply with temperature: a sealed lead-acid battery that might last its design life at 20 to 25 degrees Celsius can lose roughly half of it for every 10 degrees above that. Cooling the battery space, or choosing a chemistry that tolerates heat, is usually cheaper than replacing batteries early.

How each device behaves when control power is lost

DeviceOn loss of control powerDesign consequence
Breaker with shunt tripStays as it is and cannot be tripped electricallyThe battery must be secure; trip circuits supervised
Breaker with undervoltage releaseTripsFails safe, but a supply dip can trip healthy circuits
ContactorDrops outLoad stops; decide whether that is safe and how it restarts
Motor-operated spring-charged breakerHolds position; cannot recharge for the next closeCheck close capability after the outage
PLC outputDe-energisesChoose energise-to-run or energise-to-trip for each output deliberately

Testing the DC system properly

Float voltage shows only that the charger is working. Test battery capacity by a timed discharge at the design load, commonly every one to three years and more often as the battery ages; trend cell or block impedance between discharge tests; check charger alarms by switching chargers off; and prove trip circuit supervision by opening a trip circuit and watching the alarm. Record every result. The worst time to learn the battery has lost half its capacity is the outage it was bought for.

DC distribution that isolates faults

A short circuit on one panel’s DC supply must not take the whole battery down. Feed each panel from its own protected circuit, using fuses or miniature breakers rated for DC at the battery voltage, since AC-rated devices can fail to interrupt DC arcs. Grade them so the circuit nearest the fault clears first, and check that the battery can deliver enough current to clear the largest device quickly at the end of its discharge. Separate the trip supply to each breaker from its close and spring-charging supply where the standard design allows, so a fault in a charging motor cannot remove the ability to trip.

Alarms every DC system should raise

  • Charger failure, for each charger separately.
  • Battery voltage low, and high for a charger fault.
  • DC earth fault, on either pole.
  • Battery circuit breaker or fuse open, which disconnects the battery while the charger keeps the voltage looking normal.
  • Trip circuit supervision failure, for each breaker.
  • Battery room or cabinet temperature high.

The battery-disconnected alarm is the one most often missing. Without it, the charger holds the voltage normal until the first outage, when the supply simply disappears.

DC or a UPS for controllers?

Protection relays and breaker coils are best supplied from a station battery, which is simple, has no electronics between battery and load, and can deliver large short peaks. Controllers, network switches and SCADA servers often need AC or low-voltage DC and are commonly fed from a UPS. That UPS then becomes part of the control power system: it needs the same thought about autonomy, bypass, alarms and testing, and its failure should not take down the protection supplied from the battery.

Charger output quality

A charger with excessive ripple on its output heats the battery and can upset sensitive electronics. Measure ripple at commissioning and when the charger ages, and check the float and boost voltages against the battery maker’s figures, corrected for temperature. A float voltage set slightly high shortens battery life quietly over years.

Record the ripple, float and boost readings with the battery tests, so a charger drifting out of adjustment is caught as a trend rather than as a failed battery.

Common mistakes

  • One charger and no alarm.
  • Battery judged by float voltage.
  • Trip circuits unsupervised.
  • Starting batteries forgotten in the maintenance plan.

What to send us

Send the DC system details, panel list and battery test records. WhatsApp 98852 01608 or use the application engineering enquiry.

Evidence note. Currents and capacities are illustrative; makers’ data govern.

Questions engineers ask

Will a trip coil operate at the end of the battery discharge?

Check it, including the cable. A 110 V battery of 55 cells discharged to 1.8 V per cell gives 99 V. Through 160 m of 2.5 mm² cable a 10 A trip coil sees about 87 V, above its 77 V minimum, but a 15 A close coil sees only about 81 V against 93.5 V needed. Larger cable, here 10 mm², fixes it.

How big should a control battery charger be?

Big enough to carry the standing load and recharge the battery within an agreed time. For a 24 Ah battery and a 4 A standing load, recharging with about 10% losses in 8 hours needs about 3.3 A, plus 4 A, about 7.3 A, so a 10 A charger. Two chargers, each able to do this alone, remove the single point of failure.

How long should control batteries last?

Long enough for the longest outage the site plans for without charger supply, plus the trips and closes needed at its end. Many sites design for several hours. Size the battery for that duty at end of life and at the lowest expected temperature, then check that every coil still operates at the end-of-discharge voltage after cable drop.

Why monitor DC earth faults?

Because control DC is usually unearthed, so a first earth fault changes nothing and goes unnoticed. A second fault can then energise a trip or close coil on its own, or short the supply so nothing operates. Monitoring detects the first fault while it is still harmless, so it can be located and cleared during a planned window.

Can control and starting batteries be shared?

Better not. Cranking pulls the starting battery voltage down sharply, which can reset relays and controllers at the moment they are needed, and a flat starting battery would also disable protection and switchgear control. Keep separate batteries and chargers, or provide isolation that is designed and tested to keep the control supply within limits during cranking.

How often to test?

Check float voltage, charger alarms and earth-fault monitoring at routine visits; trend cell or block impedance a few times a year; and run a timed capacity discharge at the design load commonly every one to three years, more often as the battery ages. Prove trip circuit supervision by opening a circuit and confirming the alarm.

This guide gives general principles. Follow manufacturer data and standards.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.

CallWhatsAppEnquire