In short. A utility-to-generator transfer is a timed sequence. It detects the failure, confirms it is real, starts the set, confirms the set is acceptable and transfers. Later it retransfers without causing a second, needless outage. Each timer and permissive exists to prevent one specific failure, so none should be set by habit or removed to make the sequence “faster”.
Who this page is for: For control engineers, panel builders and facility managers designing or tuning automatic transfer between the grid and a generator.
Key facts
- Sequence: fail detected, fail confirmed, start, stable, transfer, utility back, return confirmed, retransfer, cool-down, standby.
- The mains-fail delay stops starts on brief dips.
- Start attempts with rests protect the starter and allow retries.
- The generator-stable delay stops the set being loaded before it is ready.
- The return-confirm delay stops retransfer onto unstable mains.
- Cool-down protects the engine after load.
Timers and why they exist
| Timer | Prevents | Typical (illustrative) |
|---|---|---|
| Mains-fail delay | Starts on brief sags and blips | 2 to 5 s |
| Start attempts and rest | Starter damage; allows retries | 3 × 10 s with 10 s rests |
| Generator-stable delay | Loading before voltage and frequency settle | 2 to 5 s |
| Return-confirm delay | Retransfer onto unstable mains | 2 to 5 min |
| Cool-down | Engine heat soak after load | 3 to 5 min |
Worked example: a timeline with a failed first crank (illustrative)
| Time | Event |
|---|---|
| 0 s | Utility fails |
| 3 s | Failure confirmed; first crank |
| 13 s | No start; rest |
| 23 s | Second crank; set fires at 25 s |
| 31 s | Voltage and frequency stable |
| 34 s | Stable delay ends; transfer |
| Later | Utility returns; stays healthy for 3 min; retransfer; 5 min cool-down; stop |
The UPS on the critical load had 10 minutes of battery, so a failed first crank cost nothing. A site with only 30 seconds of UPS would have dropped the load. Size UPS autonomy for the failed-start case, not the normal one. See ATS transfer studies.
Do not shorten the return-confirm delay to “save fuel”. Retransferring onto mains that fail again a minute later gives every load two extra breaks and wears the switch.
Open or closed transition
Open transition has a brief dead time; closed transition avoids it with a momentary parallel. See closed transition and ATS and AMF logic.
Transfer timer record
| Timer | Setting | Reason |
|---|---|---|
| Mains-fail delay | ||
| Start attempts and rest | ||
| Generator-stable delay | ||
| Return-confirm delay | ||
| Cool-down |
What the controller treats as a mains failure
A transfer starts with a decision that the utility supply has failed, and that decision is only as good as what the controller measures. A controller that watches one phase-to-neutral voltage will miss a blown fuse on another phase, and one that looks only at voltage will miss a supply whose frequency has drifted or whose phases have been reversed after utility work. Each condition below needs its own threshold and its own confirmation time.
| Condition | Typical setting (illustrative) | Why it matters |
|---|---|---|
| Under-voltage, any phase | Below 85% of nominal for 2 to 5 s | Motors stall and contactors drop out on a sustained low supply |
| Over-voltage, any phase | Above 110 to 115% for 2 to 5 s | Protects electronics from a lost neutral or a tap-changer fault upstream |
| Phase loss | Any phase absent for 1 to 2 s | A single blown fuse leaves three-phase motors single-phasing and overheating |
| Phase sequence | Reversed sequence, immediate block | Motors run backwards; pumps and fans fail to deliver |
| Voltage unbalance | Above 2 to 3% for several seconds | Unbalance heats motors far more than its size suggests |
| Frequency | Outside about 47.5 to 52 Hz for 2 to 5 s | A collapsing grid often shows frequency trouble before voltage trouble |
Sense all three phases, phase to neutral and phase to phase, and confirm that the controller treats any one abnormal phase as a failure. A supply with two good phases is not a healthy supply for a three-phase plant.
Pick-up and drop-out: why the two thresholds differ
If the controller declared the mains failed at 85% and healthy again at the same 85%, a supply hovering around that level would be declared failed and healthy over and over. The cure is hysteresis: the supply must rise clearly above the failure threshold before it counts as restored.
On a 415 V system, a failure threshold of 85% is about 353 V phase to phase, and a restore threshold of 92% is about 382 V. Phase to neutral on 240 V, the same settings are 204 V and about 221 V. Together with the return-confirm delay, the gap between the two thresholds stops a weak evening supply from pulling the load back and forth between the utility and the set.
Worked example: how long the load is without supply
Every timer in the sequence adds to the break the load sees. Adding them up shows whether the UPS and the loads without UPS can live with the result. The example is an open-transition change-over with the timers in the table above.
| Stage | Time (illustrative) | Running total |
|---|---|---|
| Mains-fail confirmation delay | 3 s | 3 s |
| Crank, fire and run up to rated speed and voltage | 6 s | 9 s |
| Generator-stable delay | 3 s | 12 s |
| Transfer switch operation | 0.2 s | 12.2 s |
Loads without UPS are therefore off for about 12 seconds on a good start, and for about 32 seconds if the first crank fails and the second succeeds after a 10 s crank and a 10 s rest. On the return, the load sees a second, shorter break in an open-transition scheme: the switch operation plus any time it deliberately spends in the neutral position, often 1 to 3 s where motors are connected. A closed-transition scheme avoids that second break by briefly paralleling the two sources. See closed-transition and momentary paralleling control.
Retransfer between two live sources
The return to the utility is a transfer between two live sources that are not synchronised. If the switch moves quickly while large motors are still running, the motors’ residual voltage and the incoming supply can be well out of phase at the instant of reconnection, giving a current and torque surge well above a normal start. Three methods deal with this.
- In-phase monitor: the controller waits until the two sources are close in phase and frequency and then operates the switch, anticipating the switch’s own operating time.
- Delayed transition: the switch pauses in the neutral position long enough for motor residual voltage to decay before connecting to the new source.
- Closed transition: the two sources are synchronised and paralleled for a fraction of a second, so the load never sees a break.
The in-phase monitor has to allow for the angle that changes while the switch is moving. With the two sources 0.5 Hz apart, the angle between them changes by 0.5 × 360 = 180 degrees every second. A switch that takes 100 ms to move therefore lands 18 degrees away from where it started; at a 0.2 Hz difference the change is 7.2 degrees, and with a 50 ms switch at 0.5 Hz it is 9 degrees. That is why the monitor permits a transfer only when the frequency difference is small, and starts the operation slightly early so that contact is made close to zero angle.
What the sequence does when something goes wrong
The normal sequence is the easy part. The design is judged by what happens on the bad day, and each failure needs a defined response that is written down, programmed and tested.
| Event | Response |
|---|---|
| Set fails to start after all attempts | Lock out and alarm; stay off the generator; keep watching the utility so the load returns if it recovers |
| Generator breaker or switch fails to close | Alarm with the position feedback that failed; do not retry endlessly; leave the set running for a manual attempt |
| Set trips while carrying the load | Return to the utility at once if it is healthy; otherwise alarm and wait |
| Utility returns while the set is cranking | Finish the start, run the cool-down, and do not transfer; or cancel the start if the controller allows it cleanly |
| Utility fails again during the return-confirm delay | Restart the delay from zero; the load stays on the set |
| Both sources fail | Open both sides; on recovery, follow the normal sequence with restoration in stages |
Exercise, test and test-on-load modes
A standby set that only runs when the utility fails is a set nobody knows will start. Most transfer controllers offer three ways to run it on purpose, and each has a different effect on the load.
- Exercise without load: the set starts and runs for a set time on a schedule, often weekly, while the load stays on the utility. It proves the starting system and the engine, but not the alternator under load or the transfer itself.
- Test on load: the set starts and the controller transfers the load to it as if the utility had failed, then returns it after a set time. It proves the whole chain, at the cost of two breaks for open-transition loads.
- Simulated mains failure: a test switch opens the controller’s utility sensing so it behaves exactly as in a real failure. It tests the logic, but not the sensing circuit it bypasses.
Choose the mode for each test deliberately, tell the occupants when a test on load will cause breaks, and make sure every mode times out and returns the plant to automatic. A controller left in test or manual after a Saturday exercise is one of the most common reasons a set fails to take the load on the following Monday.
What the transfer controller should report
The transfer controller holds information the rest of the site needs. At minimum it should report, to the building management or SCADA system and to a local panel: utility healthy or failed, which source is supplying the load, the set running, and every lockout with its cause. It should also report whether it is in automatic, because a controller in manual is effectively disabled. Time-stamped events for each stage, from failure detected to transfer complete, turn every real outage into a free test record and show at once if a timer has been changed. See SCADA architecture for power systems.
Testing the transfer sequence
Test with a real loss of supply, not only with the test switch, at least once at commissioning: open the incoming breaker upstream and let the controller detect the failure as it would in service. Record the time of each stage against the break budget. Then test the failure paths: block the fuel solenoid so the first start fails, hold the generator breaker open, and remove one utility phase only.
A controller that passes a clean test but has never been asked to handle a failed start, a single missing phase or a utility that flickers during the return has not been tested. Keep the record with the timer sheet, and repeat the tests after any change to the controller or its settings.
Common mistakes
- Timers set by habit, not reason.
- UPS autonomy sized for a perfect first start.
- Return delay too short.
- No test of a failed crank.
What to send us
Send the timer settings, the UPS autonomy and any transfer logs. WhatsApp 98852 01608 or use the application engineering enquiry. See ATS service.
Evidence note. Timings are illustrative; each site’s design governs.
Questions engineers ask
What voltage should a transfer controller treat as a mains failure?
A common starting point is any phase below about 85% of nominal for 2 to 5 seconds, with restoration only above about 92%, so a weak supply does not cause repeated transfers. On 415 V that is about 353 V to fail and 382 V to restore. The controller should also act on phase loss, reversed phase sequence, unbalance and frequency, and must sense all three phases, not one.
How long is the load without supply during an automatic transfer?
Add up the timers. With a 3 s mains-fail delay, about 6 s to start and run up, a 3 s stable delay and 0.2 s for the switch, loads without UPS are off for about 12 seconds on a good start, and about 32 seconds if the first crank fails. An open-transition return adds a second short break; a closed-transition return avoids it.
What mains-fail delay is right?
Long enough to ride through brief dips and the upstream utility reclose, so the generator is not started for every disturbance, and short enough for loads without UPS. Typical values are a few seconds, often 2 to 5 s. Set it slightly longer than the utility reclose dead time unless the loads cannot wait.
Why a return delay?
Because a returning utility supply is often unsteady for some minutes, with further dips or reclose operations. A return delay, often several minutes of continuously healthy supply, prevents transferring back onto a supply that fails again, which would give the load a second break and stress motors and switchgear.
Does cool-down matter?
Yes, especially for turbocharged engines. After the load is removed, running unloaded for a few minutes lets turbocharger and exhaust temperatures fall gradually; stopping a hot engine at once can damage the turbocharger bearings and seals. Follow the engine maker cool-down time and keep it in the sequence, including after tests.
Can we skip retransfer delay?
Not safely. Without it, a site can bounce between utility and generator with every utility disturbance, giving the load repeated breaks and the generator repeated load steps. If a second break on return is the concern, use closed-transition retransfer with synchronising and utility agreement rather than removing the delay.
Values are illustrative. Set timers to site requirements.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.