UPS / STS / ATS Control Coordination

How UPS, static transfer switches and ATS interact: transfer timing, source acceptance windows, rectifier walk-in, battery recharge, bypass control and coordination tests for critical loads.

In short. The UPS protects the instant, the ATS handles the move between utility and generator, and a static transfer switch (STS) protects single-corded loads against the failure of one source. All three must be coordinated on timing, voltage and frequency windows, synchronisation and settings. Most real failures happen at the interfaces between them, such as a UPS rejecting generator voltage or an STS transferring onto an unsynchronised source.

Who this page is for: For data-centre, hospital and facility engineers coordinating UPS, STS and ATS on critical power systems.

Key facts

  • UPS: no-break supply from battery, acting instantly.
  • STS: electronic transfer between two sources within about a quarter cycle (around 4 to 5 ms at 50 Hz).
  • ATS: mechanical transfer between utility and generator in cycles to seconds.
  • The UPS input window must accept the generator’s voltage and frequency, measured, not assumed.
  • An STS should transfer only between sources that are in phase, unless the load tolerates a break.
  • Test the whole chain together, with a failed start included.

Roles

DeviceJobSpeed
UPSNo-break supply from batteryInstant
STSFast electronic transfer between two sourcesAbout a quarter cycle (4 to 5 ms)
ATSMechanical transfer between utility and generatorCycles to seconds

Worked example: three interface faults found in one test (illustrative)

FindingCauseFix
UPS stayed on battery after the generator came onUPS frequency window ±2%; generator recovering from load step at 48.6 HzWindow widened to suit the set within the UPS maker’s limits; rectifier walk-in confirmed
STS refused to transfer to the B source during the outageB source (second UPS) on bypass and not in phase with AUPS B returned from bypass to inverter, with its output synchronised to UPS A; STS phase window checked
ATS retransfer caused a second UPS battery dischargeOpen transition with 10 s dead time back to mainsAccepted, as the UPS rides through it; battery discharge on each retransfer now recorded

Each device passed its own commissioning; only the integrated test showed the interface faults. See system studies.

Do not assume the UPS will accept the generator. Measure the generator’s voltage and frequency during a real load step at the UPS input, and compare them with the UPS window before relying on the chain.

Coordination points

  • Source acceptance: UPS window against generator behaviour.
  • Synchronisation: UPS outputs and bypass sources in phase where STS transfer is needed.
  • Timing: ATS delays against UPS battery runtime, including a failed first start.
  • Harmonics: UPS input current against the generator alternator. See UPS and non-linear loads.
  • Interlocks between bypasses and transfer switches. See interlocking.

See utility and DG transfer control.

Coordination sheet

ItemSettingMeasured
UPS input voltage and frequency window  
Generator dip and recovery on largest step  
STS phase window  
UPS battery runtime vs failed-start transfer time  

Worked example: UPS runtime against a failed first start (illustrative)

The UPS battery must carry the load until the generator is on line, and the realistic case is not a perfect first start. With a standby set whose controller allows three cranking attempts of 10 s with 10 s rests:

EventElapsed time
Mains fails; UPS on battery0 s
First attempt fails after 10 s cranking and 10 s restabout 23 s, after a 3 s confirm delay
Second attempt starts the set; run-up and stabilisingabout 41 s
ATS transfers; UPS rectifier walks in over about 15 sabout 57 s

The UPS battery must therefore cover about one minute with margin, at the end of the battery’s life, not just the 15 seconds of a clean start. A battery sized for 5 minutes when new and allowed to fall to about 80% capacity still gives about 4 minutes, which covers this case comfortably and leaves time for a second set to be called. A battery that has been allowed to age to 30 seconds of runtime covers only the perfect start.

Sizing the generator for a UPS load

A UPS rectifier draws distorted current, and the alternator’s voltage waveform suffers in proportion to its own impedance. Older six-pulse rectifiers commonly need the generator rated at about 1.5 to 2 times the UPS load, or more, to keep voltage distortion and regulator behaviour acceptable; modern UPS units with active, low-distortion input stages are commonly served by a set of about 1.25 to 1.5 times the load.

The recharge current after an outage adds to this: a UPS recharging its battery at its maximum rate can draw noticeably more than its rated output for a time. Agree the generator size with the UPS maker’s data and confirm it with a load test on site. See power quality.

Keeping the STS sources in phase

A static transfer switch moves a load from one source to the other within a quarter cycle, and it can only do that without a break if the two sources are close in phase, typically within about 15 degrees. Two UPS systems feeding the A and B sides drift apart unless their inverters are synchronised to a common reference, usually a synchronisation link between them or both locked to the same bypass supply.

Check the angle across every STS in every operating mode: both UPS on inverter, one on bypass, both on generator. A mode in which the angle is out of the window is a mode in which a transfer will cause a break or be refused.

The static bypass when the generator is supplying

When the UPS transfers to static bypass, the load is fed directly from the source behind it, which on generator supply means the generator’s voltage and frequency excursions reach the load unfiltered. Many sites block automatic transfer to bypass while on generator unless the bypass supply is within a tight window, and alarm any bypass operation on generator. Set the UPS bypass window deliberately for generator operation, and record the setting.

Controlling the recharge on generator

After a long outage, a UPS battery can draw a large recharge current. On a generator that is already heavily loaded, that extra demand can push it past its rating or slow its recovery from load steps. Most UPS units allow the recharge current to be limited when the input is from a generator, often by a signal from the ATS. Use it, and set the limit so the generator keeps its reserve; the battery then recharges more slowly on generator and fully once mains returns.

The integrated test sequence

TestPass when
Mains failure at full critical loadNo break at the load; UPS accepts generator after the transfer
Failed first startUPS runtime covers the second attempt with margin
Largest load step on generatorUPS stays on rectifier; no transfer to battery or bypass
Transfer across every STS in every modeTransfer completes within its time; no break
Retransfer to mainsUPS rides through the ATS break; battery discharge recorded
UPS fault forcing bypass while on generatorBehaviour as set; alarm raised

Run the sequence with the actual load or a load bank sized to it, record waveforms at the UPS inputs and outputs, and keep the records. These are the tests that find interface faults; each device passing its own test finds almost none of them.

One owner for the settings that span devices

Each maker sets up its own equipment, and nobody owns the gaps between them unless someone is named. Appoint one engineer to hold the coordination sheet: every window, timer and synchronisation setting that one device depends on in another, the measured values that justify them, and the date they were last tested. Any change to a UPS, STS, ATS or generator setting is checked against that sheet before it is made.

Typical windows to agree before commissioning

Setting (illustrative)Grid defaultOften needed on generator
UPS input frequency windowAbout ±2%About ±5%, within the UPS maker’s limits
UPS input voltage windowAbout ±10%Checked against the measured dip on the largest step
Bypass synchronisation windowTightKept tight; bypass on generator alarmed or blocked
STS transfer angle limitAbout 15 degreesUnchanged; synchronise the sources instead
Rectifier walk-in timeA few secondsAbout 10 to 20 s so the generator is not stepped

When the UPS and the voltage regulator disagree

A heavily distorted rectifier current can upset an alternator voltage regulator that senses the waveform peak or average rather than its true r.m.s. value, causing voltage hunting or a steady error that pushes the UPS out of its window. The symptoms are a generator voltage that swings when the UPS is loaded and is steady on a resistive load bank. True r.m.s. sensing, a permanent magnet excitation supply and a larger alternator are the usual remedies, and the integrated test on the actual UPS is where the problem shows.

Learning from every outage

After each real outage, collect the UPS event log, the ATS and generator controller logs and any STS records, align them in time and note how long the UPS ran on battery, whether any device rejected the generator, and how long the retransfer took. Ten outages recorded this way show trends no single test can, such as a battery runtime that is falling or a generator that is taking longer to be accepted.

Maintenance bypass and the generator

When a UPS is on its external maintenance bypass for service, the critical load is fed straight from the switchboard and therefore straight from the generator if an outage occurs during the work. Plan UPS maintenance for times when the mains is stable, check the generator is available and in AUTO before the bypass is closed, and keep the bypass period as short as possible. Record each maintenance bypass in the same log as the outages, so the exposure is visible.

Common mistakes

  • UPS window left at grid settings.
  • STS sources not synchronised.
  • Devices commissioned separately, never together.
  • UPS runtime sized for a perfect first start.

What to send us

Send the single-line diagram, UPS, STS and ATS settings and any transfer logs. WhatsApp 98852 01608 or use the application engineering enquiry.

Evidence note. Settings and findings are illustrative; makers’ limits govern.

Questions engineers ask

How much UPS runtime is needed to cover a failed generator start?

Enough for the realistic sequence, not the perfect start. With a 3 s confirm delay, a failed 10 s crank, a 10 s rest, a second start, run-up, transfer and about 15 s of rectifier walk-in, the UPS can be on battery for about a minute. A battery sized for 5 minutes when new still gives about 4 minutes at 80% capacity.

How large should a generator be for a UPS load?

It depends on the UPS input stage. Older six-pulse rectifiers commonly need a set of about 1.5 to 2 times the UPS load or more to keep voltage distortion acceptable, while modern low-distortion inputs are commonly served by about 1.25 to 1.5 times. Battery recharge current adds to this, so agree the size with the UPS maker data and prove it on load.

Is an STS the same as an ATS?

No. A static transfer switch uses thyristors to move a load between two live, synchronised sources within about a quarter cycle, protecting single-corded critical loads against a failure of one source. An automatic transfer switch is a mechanical device that moves load between utility and generator in cycles to seconds, usually with a break.

Why does the UPS keep rejecting the generator?

Usually because the generator voltage or frequency is outside the UPS input window, often during recovery from a load step, or because waveform distortion upsets the rectifier. Measure the generator at the UPS input during a real load step, widen the window within the UPS maker limits, check rectifier walk-in, and review the generator size against the UPS load.

Should the UPS recharge on generator?

Yes, but at a limited rate, so the recharge current does not overload the generator or slow its recovery from load steps. Most UPS units can reduce their recharge current when told the input is from a generator, often by a signal from the ATS. The battery then recharges slowly on generator and fully once mains returns.

Who is responsible for coordination?

One named project engineer, with data from each maker. That engineer holds a single coordination sheet listing every window, timer and synchronisation setting that one device depends on in another, the measured values that justify them and the last test date, and checks any setting change against it before it is made.

This guide gives general principles. Follow manufacturer instructions.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.