How to frame a generator application engineering question on sizing, motor starting, transfer, paralleling or changes, and which data makes the review quick.

In short. An application engineering enquiry starts with the decision you need to make and the condition that prompted it: a motor that will not start, a voltage dip that resets equipment, a planned load addition, a transfer that drops the UPS, or a choice between paralleling and one larger set. Send the existing system details, load data and drawings, and say which figures are measured and which are assumed. The review then targets the real question.

Send your enquiry

Fields marked * are required. Give a phone number or an email address, whichever you prefer.

Your details are used only to respond to this enquiry (privacy notice). Photographs, nameplates and documents can be shared by email or WhatsApp after we reply. Prefer to talk? Call 98852 01608 or WhatsApp us.

Begin with what the power system must achieve

A generator should never be selected as an isolated machine. It works inside an electrical system and must respond to the actual load, its starting characteristics, power factor, harmonics, duty cycle, the environment, the changeover philosophy and the protection system. So the useful first question is not which generator, but what the power system must achieve and what is stopping it today. Application engineering is the structured review that turns that question into a technical direction before equipment is bought, installed, hired, upgraded or repaired.

Typical questions we are asked

Problem or decisionWhat the review examinesTypical outcome
Motor will not start or set trips on startStarting kVA, starting method, alternator reactance, governor responseSoft starter or VFD, staged starting, or larger alternator
Voltage dip resets equipmentLoad step size, AVR response, sensitive loadsLoad sequencing, AVR or PMG upgrade, UPS ride-through
Load addition on existing setMeasured demand, spare capacity, deratingConfirm headroom, add a set, or load shedding
Single large set or paralleled setsRedundancy, load profile, maintenance windowsN+1 arrangement or single set with rental backup
UPS drops load on transferTransfer time, UPS input window, generator frequency stabilityAdjusted transfer delays, UPS settings, governor tuning
Generator overheating or deratingAmbient, ventilation, altitude, exhaust back-pressureRoom airflow changes or a different set

The hardest moment, not the final load

The generator must support the hardest credible operating moment, not just the final steady load. That moment is usually a large motor start or a block load applied after transfer.

Starting kVA = sqrt(3) × V × I(start) / 1000

V is the line voltage in volts and I(start) is the motor’s starting current in amperes. Worked example (illustrative): a 37 kW pump motor at 415 V with a full-load current of about 68 A, started direct-on-line at around 6.5 times full-load current, draws about 440 A, so starting kVA is about 1.732 × 415 × 440 ÷ 1000, roughly 316 kVA. On a 250 kVA set that will cause a deep voltage dip, while a soft starter limiting current to about three times full load cuts the starting demand to roughly 150 kVA. The detailed method is in motor starting and the dip consequences in voltage dip.

Existing basis: measured, specified or assumed

Include the load schedule, equipment identities, single-line diagram and supply arrangement. Then label each figure. A measured value from a power analyser is evidence; a nameplate value is a specification; a guessed diversity factor is an assumption. Mixing them without labels produces a confident wrong answer. Where records are incomplete, say what is missing so that the next step closes the gap instead of treating an estimate as confirmed. For existing generators, the engine and alternator nameplates, controller model and recent run data are as important as the load figures; see generator engine architecture.

Derating for Telangana conditions

Generator ratings are normally stated at reference conditions defined by the manufacturer, often around 25 to 40 °C ambient and near sea level. A set in a hot, poorly ventilated room in Hyderabad in May can see intake air well above 45 °C, and the engine may need to be derated by a few percent or more according to the manufacturer’s curve. Tell us where the set stands, how air reaches it and the hottest conditions on site, because derating can move a marginal selection to the next rating.

What the assessment delivers

An enquiry begins a discussion about inputs, deliverables and responsibilities; it does not produce an automatic design or a technical sign-off. Depending on scope, the output may be a short technical note answering one question, a sizing recommendation with stated assumptions, a list of studies required, or a site visit with measurements. Where a formal load flow, short-circuit or protection coordination study is needed, we say so and explain why. Mechanical and electrical integration, ventilation, fuel, earthing and controls are reviewed as applicable, and testing or commissioning requirements are identified. Related support is listed under application assessment and engine service.

Worked example: a pump that will not start on generator (illustrative)

A 250 kVA set supplies a building whose 37 kW pump starts direct on line. On the mains it starts every time; on the generator the lights dip hard and the pump contactor drops out.

StepWorkingResult
Running kVA of the motor37 kW ÷ (0.9 efficiency × 0.85 power factor)About 48 kVA
Direct-on-line starting kVAAbout six times runningAbout 290 kVA, more than the whole set
Star-delta starting kVAAbout one third of direct on lineAbout 97 kVA
Soft starter, set to about three times running48 × 3About 145 kVA

The direct-on-line start asks more of the alternator than its rating, so the voltage collapses. A star-delta starter or a soft starter brings the starting demand within reach, and the remaining question, whether the dip is acceptable to the other loads already running, is checked against the alternator data. The review states which option works, with the expected dip, rather than simply recommending a larger set.

What to measure before the review

ProblemMeasurement that settles it
Motor will not start or equipment resetsVoltage and frequency recorded through the start, with the current drawn
Alternator or neutral running hotCurrent on each phase and the neutral, and the harmonic content
UPS rejects the generator supplyFrequency stability and voltage waveform at the UPS input on generator
Set overheats in summerAir temperature at the radiator intake against outside air, at full load
Planned load additionA week of load logging covering the busiest hours

One good recording is worth many estimates, and it lets the review answer the question on the first attempt.

Questions to settle before changing the system

Answering these before equipment is ordered prevents the most expensive kind of mistake, the one discovered at commissioning. See power system engineering.

What a useful review gives back

An engineering review should end in a decision the owner can act on, not a list of general advice. A useful report restates the question, lists the data used and says which figures were measured and which assumed, shows the working for each conclusion, compares the realistic options with their consequences, and names what still needs checking on site. Where the answer is that the existing set is fine with a change in settings or starting method, it says so; where it is not, it says what rating, arrangement or study is needed next.

Questions that look simple but are not

Each of these is answered properly from data on the specific installation, which is why the enquiry asks for it. See engineering guides.

Where the question involves safety, such as protection that may not clear a fault on generator supply or a changeover that could back-feed the grid, it is treated as urgent and answered before anything else, because those are the faults that harm people rather than equipment. The interim advice is written down, with what to avoid until the change is made.

Common mistakes

What to send us

Send the project location, a description of the problem or decision, the existing generator and electrical system details with nameplate photographs, the load list with starting loads and methods, control and transfer arrangements, and any drawings, single-line diagrams or analyser readings you have. Mark which figures are measured. Phone or WhatsApp 98852 01608, or contact Reddy Generators through the form with the files attached.

Questions engineers ask

Why will my motor start on mains but not on the generator?

Because the mains can supply a large starting current with little voltage drop, while a generator of limited size cannot. A direct on line start draws about six times running current, which can exceed the whole rating of the set and collapse the voltage. A star delta or soft starter, or a set with a larger alternator, brings the start within reach.

What measurements help an engineering review?

Voltage and frequency recorded through the problem event with the current drawn, the current on each phase and the neutral with the harmonic content, the air temperature at the radiator intake at full load, and a week of load logging covering the busiest hours. One good recording answers more than many estimates and lets the review get it right first time.

Do I need a site visit for an application review?

Not always. A clear problem statement with nameplates, drawings and measured data can often be answered remotely. Motor starting failures, overheating and transfer problems usually benefit from measurements on site, because the event has to be recorded as it happens, with voltage, frequency and current captured together rather than estimated afterwards.

Can you review a consultant’s generator specification?

Yes. We check the rating basis, motor starting assumptions, derating, transfer arrangement and installation requirements against the load and site, and report any gaps. The report lists each point with the reason and a suggested correction, so the consultant can amend the specification before tenders are issued rather than after offers arrive.

Is one large generator better than two smaller ones in parallel?

Two paralleled sets give redundancy and better efficiency at low load, at the cost of synchronising controls and more maintenance. A single set is simpler and cheaper, and holds a large motor start better. The load profile, the cost of an outage and the space available decide it, and the review shows each option against those three.

Can a soft starter let me use a smaller generator?

Often, because it reduces starting current, typically to around three times running current against about six for a direct on line start. The set must still handle the reduced starting kVA and any harmonics the starter produces, so the combination is checked against the alternator data and the loads already running before the smaller set is chosen.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.