In short. Modern generator, UPS, ATS and relay controllers are networked. That brings visibility and also risk. An operational technology (OT) network for critical power should do four things. It should be split into zones, be redundant where control depends on it, and control remote access tightly. Above all, local power control must keep working when the wider network is down, misconfigured or under attack.
Who this page is for: For control engineers, IT and security teams and consultants designing networks for generator plants, substations and data centres.
Key facts
- Zones: control, supervisory, a demilitarised zone (DMZ) and enterprise IT, with only needed flows between them.
- Control must not depend on the internet; monitoring may use it, control stays local.
- Remote access goes through a controlled gateway with named accounts, multi-factor authentication and logging.
- Critical control paths get ring or dual networks.
- No shared or default passwords; change them at commissioning.
- Keep an asset list and a patch plan; test patches before applying them.
Zone model
| Zone | Contents | Access |
|---|---|---|
| Control | PLCs, relays, generator and ATS controllers | Most protected; minimal access |
| Supervisory | SCADA servers, historian, HMI | Restricted flows to control zone |
| DMZ | Data brokers, remote access gateways | Only point of contact with IT and outside |
| Enterprise IT | Business systems | No direct access to control |
Worked example: a flat network made safe (illustrative)
| Found | Risk | Change |
|---|---|---|
| Generator controllers, UPS cards and office PCs on one network | An office virus or a misconfigured PC can reach controls | Separate control and supervisory zones with a firewall |
| Vendor remote access by a permanently open tunnel | Unknown access at any time | Gateway in the DMZ with multi-factor login, enabled per visit, logged |
| Default passwords on four controllers | Anyone on the network could change settings | Unique passwords, stored securely |
| One network switch for all controllers | Switch failure blinds SCADA and stops load sharing messages | Ring network for set controllers; sharing lines checked to work without SCADA |
A test after the changes unplugged the supervisory network: the sets kept running and sharing, and SCADA recovered when the network returned.
Do not let a generator or ATS controller be reachable directly from the internet or the office network. Control access must pass through a controlled gateway, and local control must work with the network down.
Design principles
- Segment with firewalls and VLANs; allow only needed flows.
- Control stays local; remote monitoring may use the internet through the DMZ.
- Redundancy for critical paths. See high availability.
- Named accounts, logging and time-limited remote access.
- Asset list, backups of configurations, and a patch plan.
See SCADA and degraded modes.
OT network review sheet
| Item | Status |
|---|---|
| Zones defined and firewalled | |
| Remote access method and logging | |
| Default passwords removed | |
| Critical paths redundant | |
| Local control tested with network down |
Worked example: the firewall between zones (illustrative)
A firewall between the supervisory and control zones should allow a short, written list of flows and deny everything else. For a generator plant with SCADA, a historian and an engineering workstation, the list might be:
| From | To | Protocol and port | Why |
|---|---|---|---|
| SCADA servers | Generator and ATS controllers, power instruments | Modbus TCP, port 502 | Polling measurements and status, sending permitted commands |
| SCADA servers | Protection relays | IEC 61850 MMS, port 102, or DNP3, port 20000 | Events, measurements and records |
| Time server | All control devices | NTP, port 123, or PTP | Common time for event correlation |
| Engineering workstation, via the jump host only | PLCs and relays | Maker programming ports | Setting and program changes, when authorised |
| Historian | DMZ data broker | One outbound port | Copying history to business users |
| Anything else | Anything else | Denied and logged | Default rule |
Write the list from the point list and the remote access design before buying the firewall, review it once a year, and remove any rule nobody can explain. Rules added during commissioning “just for now” are the ones most often left open for years.
How fast each kind of traffic must arrive
| Traffic | Typical time requirement | Network treatment |
|---|---|---|
| Protection trip and interlock messages between relays | A few milliseconds | Own VLAN, highest priority, zero-recovery redundancy or hard-wired backup |
| Fast load shedding signals | Tens of milliseconds | High priority, redundant paths |
| Load-share and controller coordination | Tens to hundreds of milliseconds | Control VLAN, ring network |
| SCADA polling and operator commands | About a second | Supervisory zone |
| History, reports, remote monitoring | Seconds to minutes | DMZ and enterprise side |
Mixing all of these on one flat network means a large file copy or a broadcast storm can delay a trip message. Separating them by VLAN and priority, and keeping the fastest functions on their own physical paths where possible, is what lets the network carry protection traffic safely at all.
Remote access that stays controlled
- The vendor or engineer requests access for a stated task and time.
- A site person enables the session on the gateway in the DMZ.
- The user logs in with a named account and a second factor.
- The session lands on a jump host, never directly on a controller, and is recorded.
- The session ends automatically at the agreed time, and the site person disables access.
The process takes minutes and removes the commonest route by which control networks are compromised: a permanently open connection that nobody remembers setting up.
What the asset list should hold
| Field | Why it is needed |
|---|---|
| Device, location and function | Know what each address is and what stops if it fails |
| Make, model and firmware version | Check against maker security notices |
| Network address and zone | Confirm it is where the design says |
| Accounts and who holds them | Remove leavers and shared logins |
| Last configuration backup | Recover quickly after a failure or an attack |
Patching without stopping the plant
Control systems cannot be patched like office computers. Check each patch against the maker’s approval for the control software, test it on a spare machine or test bench first, apply it during a planned window with a rollback ready, and patch redundant servers one at a time. Where a device cannot be patched, because it is old or the maker no longer supports it, add compensating measures: tighter firewall rules around it, no remote access to it, and closer monitoring.
Backups and the time to recover
Keep current configuration backups of every controller, relay, switch, firewall and server, stored off the control network, and test a restore at least once a year. The question to answer is how long it would take to rebuild the control system after a failed server or a ransomware attack on the supervisory zone. If the answer is days, the plant must be able to run for days on local control alone, and the operators must have practised doing so.
When something looks wrong on the network
Agree in advance who may isolate the DMZ or the supervisory zone, and that doing so is safe because local control continues. Write down how operators will run the plant with SCADA unavailable, who in IT and in operations must be told, and how evidence will be kept. An incident is not the time to discover that isolating the network would also stop the generators sharing load.
Commissioning tests for the network
| Test | Pass when |
|---|---|
| Break each ring link in turn | Recovery within the design time; no control function affected |
| Power off each switch in turn | Redundant paths take over; alarm raised |
| Disconnect the supervisory zone | Generators keep running, sharing and protecting; SCADA recovers on reconnection |
| Try a denied flow through each firewall | Blocked and logged |
| Remote access session from outside | Works only when enabled, with a second factor, and is recorded |
| Flood the supervisory network with traffic | Protection and control traffic unaffected |
Wireless and cellular links
Cellular routers for remote monitoring and wireless links between buildings are convenient and often added late, outside the network design. Treat each as a connection to the outside: put it in the DMZ or behind the same firewall rules, disable any management interface reachable from the internet, change its default credentials and keep it on the asset list. A cellular modem plugged straight into a generator controller for convenience bypasses every other control on this page.
Watching the network itself
Switches, firewalls and gateways can report link failures, unusual traffic and new devices appearing. Send those alerts to someone who will look at them, and review the firewall logs regularly for denied traffic that suggests a misconfiguration or a probe. A new, unknown device on the control network is always worth an immediate question, because legitimate changes should already be on the asset list.
Physical security of the equipment
A locked switchroom protects the network as much as any firewall. Keep switches, servers and gateways in locked cabinets, disable unused switch ports, and control who may plug in a laptop. Many control network incidents start with a well-meaning person connecting a device to a spare port for a quick check.
People are part of the network design
Most incidents on control networks start with an ordinary action: a laptop plugged into the wrong port, a password shared to save time, a remote session left open after a fault was fixed. Brief everyone who works on the control system, including contractors and vendors, on the zones, the remote access process and the rule that nothing is connected without approval. Review accounts every few months and remove anyone who has left. Simple, repeated habits protect a plant better than an expensive device that people learn to bypass.
The yearly network review
Once a year, walk the network against its drawings: confirm every device on the asset list is present and no unknown ones have appeared, read the firewall rules and remove any that nobody can explain, check that backups are current and that one was restored successfully, check firmware against maker security notices, and repeat the test of disconnecting the supervisory zone. Record the findings and the actions, and keep the record with the asset list.
Common mistakes
- Flat network shared with office IT.
- Permanent vendor tunnels.
- Default passwords left in place.
- Control that stops when SCADA or the network stops.
What to send us
Send a sketch of the network, the device list and how remote access works today. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. Findings are illustrative; each site’s risk assessment governs.
Questions engineers ask
Which ports does a power control network need open?
Only those on a written list, with everything else denied and logged. A typical generator plant needs Modbus TCP on port 502 from SCADA to controllers, IEC 61850 MMS on port 102 or DNP3 on port 20000 to relays, NTP on port 123 for time, maker programming ports from a jump host only, and one outbound port from the historian to the DMZ.
How fast must protection messages travel on the network?
Protection trip and interlock messages between relays are commonly required within a few milliseconds, fast load shedding within tens of milliseconds, controller coordination within hundreds, and SCADA within about a second. Put protection messages on their own VLAN at the highest priority, with zero-recovery redundancy or a hard-wired backup, so other traffic can never delay them.
Is air-gapping realistic?
Rarely as a complete solution. Modern plants need remote monitoring, vendor support, time synchronisation and data for the business, and each of those creates a connection, often an undocumented one such as a laptop or a USB stick. It is safer to plan a few controlled, firewalled and logged connections through a DMZ than to assume an air gap that does not really exist.
Who is responsible, IT or OT?
Both, with written roles. Operations owns the control system and decides what may affect the plant; IT brings security tools, monitoring and incident skills. Agree who approves firewall changes, patches and remote access, and share one incident plan, so an IT response to a threat never stops the generators by accident.
Can vendors connect remotely?
Yes, through a controlled gateway in the DMZ, with named accounts and a second factor, landing on a jump host rather than a controller, recorded, and enabled by a site person for a stated task and time. Permanent open tunnels and shared vendor passwords are the commonest route by which control networks are compromised.
Which standards guide this?
Industrial control security frameworks such as the IEC 62443 series are widely used to define zones and conduits, security levels, and the responsibilities of owners, integrators and product makers. Power utilities may also follow sector rules and the utility interconnection requirements. A site risk assessment decides how far to apply them.
This guide gives general principles. Engage qualified security professionals for design.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.