In short. An interlock stops an action that must never happen, such as the grid and a generator closing onto the same bus, or a breaker closing onto an earthed section. A permissive is a condition that must be true before an action is allowed, such as the generator voltage and frequency being in range before its breaker closes. Safety-critical interlocks are built in layers: mechanical first, then hard-wired electrical, then software. Software alone is never the only guard. Every interlock is tested in the blocked direction, by trying to make the forbidden action happen.
Who this page is for: For panel builders, consultants and maintenance engineers: design, document and test changeover and switchboard interlocks so that two sources can never close together.
Key facts
- An interlock prevents an unsafe action; a permissive allows an action only when every condition is true.
- Safety-critical interlocks need independent layers: mechanical, hard-wired electrical, then software.
- Software alone is never the only guard against closing two sources together.
- Loss of a signal or a broken wire must block the action, not allow it.
- Every interlock is tested in the blocked direction, one layer at a time.
Interlock, permissive and lockout
| Term | What it does | Example |
|---|---|---|
| Interlock | Prevents an unsafe action, whatever the operator or the controller asks for | Mains and generator breakers cannot both be closed in an open-transition changeover |
| Permissive | Allows an action only when every listed condition is true | Generator breaker may close only when voltage and frequency are in their windows |
| Trip and lockout | Forces a safe state and holds it until a person resets it | A differential or earth-fault trip locks the breaker out from reclosing |
Three layers, in order of trust
| Layer | How it works | Strengths | Weaknesses |
|---|---|---|---|
| Mechanical | A physical linkage between two breakers or contactors, or trapped keys that release only in sequence | Works with no power, cannot be defeated by a software fault | Only between devices that are physically close or share a key scheme |
| Hard-wired electrical | Auxiliary contacts of one device wired in series with the closing coil of the other | Fast, simple, independent of the PLC or controller | Can be defeated by a wrong wire, a jumper or a welded contact |
| Software | Logic in the generator controller, PLC or power management system | Flexible, can show the reason for a block on the HMI | Depends on power, inputs, the program and its version control |
The rule is simple. The more severe the consequence, the more independent layers are needed. Closing two unsynchronised sources together can damage the alternator, the engine coupling and the breakers in a fraction of a second, so a changeover always has at least a mechanical or hard-wired layer under the software.
What must be interlocked on a generator installation
- Mains and generator incomers in an open-transition changeover: never closed together.
- Paralleling with the grid, where it is allowed at all: only through a sync-check and only in an approved paralleling mode with the DISCOM’s permission.
- Main–tie–main boards: no more than two of the three breakers closed when the two sources are not paralleled. See main–tie–main transfer control.
- Earthing switches: no closing onto an earthed section, and no earthing a live one.
- Bypass switches on ATS and UPS systems: operated only in the correct order.
- Switchgear doors and racking: door cannot open with the breaker in service, and a breaker cannot rack in when closed.
- Generator start inhibit during maintenance, so the set cannot start under automatic control while someone is working on it.
- Neutral switching on four-pole changeovers, so that the neutral is never left floating or shared in the wrong way between sources.
Design rules
- Rank the hazards before drawing the logic, and give the severe ones independent layers.
- Use positive position feedback. A breaker’s auxiliary contacts tell the logic whether it is really open or closed. A command sent is not proof of position.
- Design for fail-safe. A broken wire, a lost signal or a failed relay must block the action, not allow it.
- Do not feed the hard-wired and software layers from one power supply. If the control supply fails, the mechanical layer must still hold and no unsafe close may follow on restoration. See control power and fail-safe architecture.
- Add time where physics needs it. An open-transition changeover should hold a dead time of a few seconds so that motor residual voltage decays before the second source closes.
- Document every interlock in one schedule: cause, effect, layers and test.
- Control bypass keys and override switches under a permit, with a log of who used them and why.
Worked example: interlocking an AMF changeover (illustrative)
A 250 kVA set backs up a commercial building through an AMF panel with two four-pole contactors: K1 for mains and K2 for the generator. The interlocks are built in three independent layers.
| Layer | Implementation | What it prevents |
|---|---|---|
| Mechanical | Mechanical interlock fitted between K1 and K2 | Both contactors closing, even if both coils are energised |
| Hard-wired | Normally-closed auxiliary contact of K1 in series with the coil of K2, and of K2 in series with the coil of K1 | Either coil being energised while the other contactor is closed |
| Controller | AMF logic opens K1, waits a 3-second dead time, checks K1 open by feedback, then closes K2 | A close command while the other source is still connected, and residual-voltage closing |
The acceptance test removes one layer at a time. With the mechanical link removed on the bench, the hard-wired contacts must still block the second close. With the auxiliary contact wiring temporarily jumpered by the tester, the mechanical link must still block it. With both physical layers in place, forcing the controller’s outputs must not close both contactors. Only when each layer blocks on its own is the panel accepted. See AMF panels and ATS and AMF control logic.
Never bypass, jumper or remove a changeover or paralleling interlock to restore power. Closing two unsynchronised sources together can destroy equipment and injure people. Call an engineer instead.
Writing the permissive matrix
A permissive matrix lists every controlled action and every condition that must be true for it. It becomes the specification for the programmer and the checklist for the tester.
| Action | Permissives (all must be true) |
|---|---|
| Close generator breaker onto a dead bus | Generator voltage and frequency in window; bus confirmed dead by two independent measurements; no other source closing; no trip or lockout active; mode allows it |
| Close generator breaker onto a live bus | Sync-check healthy (voltage, frequency and phase angle in window); generator healthy; no lockout; paralleling mode selected |
| Close bus tie | Both sides healthy; no bus fault trip; total demand within the running capacity |
| Return to mains | Mains voltage and frequency stable for the full return delay; generator breaker confirmed open, or sync-check healthy for a closed-transition return |
| Start generator automatically | Start inhibit not active; no shutdown alarm latched; fuel and battery healthy |
For the sync-check and dead-bus conditions in detail, see dead-bus, live-bus and sync-check logic. Each blocked action should show its reason on the HMI, for example “Gen CB close blocked: bus earthed”, so operators do not try to defeat a block they do not understand. See HMI and mimic design.
Testing interlocks and permissives
| Test | Method | Pass condition |
|---|---|---|
| Permitted action | Make every permissive true and command the action | Action completes |
| Each permissive removed | Make one condition false at a time | Action blocked, reason shown |
| Signal loss | Disconnect each input wire in turn | Action blocked, not allowed |
| Wrong position feedback | Simulate “open” feedback on a closed breaker | Discrepancy alarm; dependent action blocked |
| Each layer alone | Defeat the other layers under controlled test conditions | The remaining layer blocks the action |
| Control power failure | Switch off the control supply | Mechanical layer holds; no unsafe close on restoration |
Test at commissioning, after any wiring or program change, after a controller is replaced, and periodically during planned shutdowns. Integrated tests for critical sites are covered in critical power testing.
Interlock schedule template
| ID | Action prevented or permitted | Cause (conditions) | Layers | Test method | Last tested and by whom |
|---|---|---|---|---|---|
| IL-01 | Mains and DG incomers closed together | Either incomer closed | Mechanical, hard-wired, software | Defeat-one-layer test | Date and signature |
| IL-02 | Auto start during maintenance | Start-inhibit key removed | Hard-wired, software | Simulate mains failure with key removed | Date and signature |
| PM-01 | Close DG breaker to dead bus | See permissive matrix | Software, with hard-wired dead-bus relay | Remove each permissive | Date and signature |
Exceptions and special cases
- Closed-transition changeover. A make-before-break transfer deliberately parallels the sources for a short time. It needs a sync-check permissive, a strict overlap time limit, protection against a failure to open, and the DISCOM’s agreement.
- Multi-generator plants. Dead-bus closing must allow only one set onto a dead bus at a time. See synchronising and paralleling switchgear.
- Retrofits. Old relay-logic panels often have interlocks that exist only in a wiring diagram nobody has. Trace and test them before adding new controls.
Worked example: the welded auxiliary contact (illustrative)
A hard-wired interlock uses a normally closed auxiliary contact of the mains breaker in series with the generator breaker’s closing coil: the generator may close only while the mains breaker is open. If that contact welds closed, the wiring reports the mains breaker open whatever it is doing, and the electrical layer silently stops protecting.
| Layer | With the welded contact |
|---|---|
| Mechanical interlock between the two breakers | Still blocks the generator breaker physically |
| Hard-wired auxiliary contact | Defeated: reports open while the mains breaker is closed |
| Software comparing both auxiliary contacts | Detects that open and closed contacts both read true, alarms and blocks |
Two lessons follow. Independent layers matter because each fails in a different way. And software should read both the open and the closed auxiliary contact of each breaker, so that a contradiction, both or neither, is detected as a fault rather than trusted as a position.
A trapped-key sequence for earthing a section
- Open the incomer; its key is released only when the breaker is open and racked out.
- Use that key to unlock the earthing switch; the incomer key is now trapped there.
- Close the earthing switch; its key is released only when it is closed.
- Use that key to unlock the access door; it stays trapped while the door is open.
- Reverse the sequence to restore: the incomer cannot close until the door is shut and the earth removed.
The sequence cannot be shortened, because each key exists in only one place at a time. Keep spare keys under the control of one named person, never on a hook beside the board.
The interlock register and bypass log
Keep a register of every interlock and permissive on the site: what it prevents, its layers, how it is tested and when it was last tested. Any bypass, jumper or forced input, for testing or maintenance, is entered in a log with the reason, the person, the time it was applied and the time it was removed, and is checked at every shift handover. Most serious switching incidents involve an interlock that had been bypassed for a good reason and not restored.
Common mistakes
- Using an open contact as the “healthy” signal (one that closes only on a fault), so that a broken wire looks healthy. Design so that loss of signal blocks the action.
- Relying on the controller for the only changeover interlock.
- Testing only that the permitted action works, never that the forbidden one is blocked.
- Leaving a test jumper or bypass in place after commissioning.
- Changing a program without re-testing the interlocks it touches.
The question every design must answer
Which single failure, whether of a sensor, a contact, a cable, a power supply or a program, could allow the action this interlock exists to prevent? If any one of them could, add an independent layer.
What to send us
Send the single-line diagram, the control schematics, the operating sequences and photographs of the panels. For an existing installation, tell us what is not working or what has changed. WhatsApp 98852 01608 or use the enquiry form.
Evidence note. Safety interlocks must also follow the site’s own procedures, the equipment makers’ instructions and the applicable standards. The worked example is illustrative.
Questions engineers ask
What happens if an interlock auxiliary contact welds?
A welded normally closed contact keeps reporting the other breaker open whatever it is doing, so a hard-wired interlock relying on it silently stops working. An independent mechanical interlock still blocks the close, and software that reads both the open and the closed auxiliary contacts detects the contradiction, alarms and blocks. That is why layers must be independent.
How does a trapped-key interlock sequence work?
Each key is released only when its device is in a safe state and is then trapped in the next lock, so the steps can only be done in order. To earth a section, the incomer key is released when the breaker is open and racked out, unlocks the earthing switch, whose key in turn unlocks the access door. Spare keys are held by one named person.
Are software interlocks acceptable?
As an extra layer, yes, and they add useful checks such as comparing both auxiliary contacts of a breaker. But a safety-critical interlock, such as preventing mains and generator closing together, needs an independent hard-wired or mechanical layer as well, because software can fail, be edited or be fed a false signal.
What are key interlocks for?
To enforce a sequence across devices that cannot be linked mechanically, by releasing a key only when a device is in a safe state and trapping it in the next lock. Typical uses are earthing a section, access to switchgear compartments and changeovers between sources in separate rooms. They work without power and cannot be skipped.
Can interlocks be bypassed?
Only under a written, controlled procedure: a stated reason, authorisation, an entry in the bypass log, extra precautions while it applies and a check that it has been removed before the permit closes. Bypass facilities should be key-controlled. An interlock bypassed and forgotten is behind many serious switching incidents.
How often to test interlocks?
At commissioning, after any change to the switchgear, wiring or logic, and periodically, commonly once a year, by trying every forbidden operation one layer at a time and confirming it is blocked. Record each result in the interlock register. An interlock tested only in the permitted direction has not been tested.
This guide gives general principles. Safety interlocks must follow site procedures and standards.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.