In short. Automatic dispatch runs only as many generators as the load needs while keeping enough reserve to survive the largest credible event. Start and stop thresholds, delays, priority rotation and fail-to-start handling must be tuned together. Set them carelessly and the plant either hunts, starting and stopping sets every few minutes, or runs without enough margin when a set trips.
Who this page is for: For plant engineers, commissioning engineers and operators of multi-generator plants with automatic start-stop and power management.
Key facts
- Start the next set when load exceeds an upper threshold of running capacity for a set delay.
- Stop a set only when the remaining sets would run well below the start threshold.
- The gap between start and stop points (hysteresis) prevents cycling.
- Keep reserve for the loss of the largest running set, or a fast load-shed scheme.
- If a set fails to start, call the next one automatically and alarm.
- Avoid long periods of light loading; plan loaded running.
Dispatch rules
| Rule | Purpose |
|---|---|
| Start threshold and delay | Add a set before the running sets overload, but not on brief peaks |
| Stop threshold and delay | Remove a set only when the rest can carry the load with margin |
| Hysteresis | Prevent repeated starts and stops |
| Priority and rotation | Balance run hours |
| Reserve rule | Survive the largest step or the loss of a set |
| Fail-to-start replacement | Call the next set without waiting for an operator |
Worked example: setting thresholds that do not hunt (illustrative)
Three sets of 1000 kVA (800 kW each) supply a plant.
| Setting | Value | Check |
|---|---|---|
| Start second set | Above 80% of one set (640 kW) for 10 s | Brief motor starts do not trigger it |
| Proposed stop | Below 40% of two sets (640 kW) for 5 min | After stopping, one set carries 640 kW = 80%: exactly the start point, so the plant cycles |
| Revised stop | Below 520 kW for 5 min | One set then carries at most 65%, well below the 80% start point |
The revised setting leaves a 15-point gap between where a set stops and where the next one starts. The plant now changes sets a few times a day instead of every few minutes. If a running set trips while the others are near the start threshold, the next set starts at once and low-priority loads are shed until it is on the bus. See PMS architecture.
Do not set the stop point at or near the start point. Check what loading the remaining sets will see after a stop, and keep it well below the start threshold, or the plant will hunt and wear its engines and breakers.
Sequence on a mains failure (illustrative timings)
| Step | Event | Typical time |
|---|---|---|
| 1 | Mains failure detected and confirmed | 1 to 3 s |
| 2 | All standby sets start | Immediately |
| 3 | First set at voltage and frequency closes to the dead bus | About 8 to 15 s |
| 4 | Other sets synchronise and close | A few seconds each |
| 5 | Load added in priority steps | Seconds apart |
| 6 | Surplus sets stop | After a minimum run time |
Only one breaker may close to a dead bus. See dead-bus and live-bus logic.
Start and stop sequences
Start: demand → start command → crank → voltage and frequency acceptable → sync check → breaker close → load ramp → sharing active, with a timeout on each step. Stop: condition held → unload ramp → breaker open → cool-down → stop → standby, never leaving the plant below its reserve.
Engine considerations
Large steps such as motor starts are not covered by dispatch alone; enough capacity must already be running. See large-motor starting. Long periods at light load cause wet stacking; plan periodic loaded running or load-bank tests. See load bank testing.
Dispatch settings sheet
| Setting | Value | Loading after the action (%) |
|---|---|---|
| Start next set: threshold and delay | ||
| Stop a set: threshold and delay | ||
| Minimum run time | ||
| Reserve rule | ||
| Fail-to-start time and next set |
Worked example: dispatching sets of different sizes (illustrative)
With sets of different ratings, the dispatch can choose the combination that keeps the running sets best loaded, not simply add the next set in a fixed order. A plant with two 1000 kVA (800 kW) sets and one 500 kVA (400 kW) set, starting a combination when load reaches 85% of the current one:
| Load range | Combination | Capacity | Loading at the top of the range |
|---|---|---|---|
| Up to 340 kW | 500 kVA set alone | 400 kW | 340 ÷ 400 = 85% |
| 340 to 680 kW | One 1000 kVA set | 800 kW | 680 ÷ 800 = 85% |
| 680 to 1020 kW | 1000 kVA plus 500 kVA | 1200 kW | 1020 ÷ 1200 = 85% |
| 1020 to 1360 kW | Both 1000 kVA sets | 1600 kW | 1360 ÷ 1600 = 85% |
| Above 1360 kW | All three | 2000 kW | Up to the plant rating |
Each change of combination swaps sets rather than only adding one, so the logic must start and synchronise the incoming set before unloading the outgoing one, and must check the reserve rule at every step. The stop points sit below these start points by the same kind of margin as in the worked example above, so the plant does not hunt between combinations.
Worked example: how long the running set can wait for help (illustrative)
The start delay must be shorter than the time the running sets can safely carry the load while the next set comes on line. A set with a prime rating commonly has an overload allowance of about 10% for one hour in twelve, but nothing beyond that.
| Event on one 800 kW set | Loading | Action |
|---|---|---|
| Load rises to 760 kW | 95% | Start the next set after the start delay; about 15 to 25 s to be on the bus |
| Load rises to 860 kW | 107.5% | Within the short overload allowance; start the next set at once |
| Load jumps to 950 kW | about 119% | Beyond the allowance: shed at least 150 kW immediately, then start the next set |
A plant whose start delay is tuned only to avoid nuisance starts can leave a set overloaded for 30 seconds or more while it waits; a plant that sheds at once for a step beyond the allowance never asks the engine for more than it can give.
Worked example: rotating the lead set (illustrative)
Three equal sets share about 6000 running hours a year between them.
| Policy | Set A | Set B | Set C |
|---|---|---|---|
| Fixed priority A, B, C | about 4000 h | about 1500 h | about 500 h |
| Lead rotated weekly | about 2000 h | about 2000 h | about 2000 h |
| Rotated, with a deliberate offset | about 2200 h | about 2000 h | about 1800 h |
Perfect equality has a drawback: all three sets reach their major overhaul in the same month, leaving the plant short of capacity while they are serviced. A small deliberate offset staggers the overhauls. Fixed priority, the default on many controllers, wears one set out while another sits idle and may not be fit to run when needed.
Fail-to-start: when to give up and call the next set
A controller set for three cranking attempts of 10 s with 10 s rests can take about 50 s to declare a failure, which is too long if the plant is overloaded or the mains has failed. On a multi-set plant, call the next set as soon as the first attempt fails, while the first set keeps trying; whichever is ready first closes, and the other stops or joins as the reserve rule requires. Raise an alarm for every failed attempt, not only for the final failure, because a set that needs two attempts today may need four next month.
Minimum run time and cool-down
- Minimum run time: commonly 30 minutes or more, so the engine reaches full temperature and moisture is driven out of the oil and exhaust.
- Cool-down: a few minutes unloaded before stopping, so turbocharger and engine temperatures fall gradually.
- Minimum stop time: a short delay before a stopped set may be called again, avoiding a restart into a hot, unsettled engine.
These timers belong to the engine, so take them from the engine maker and enter them in the dispatch, not only in the generator controller, so the dispatch knows when each set is truly available.
Testing the dispatch before trusting it
| Test | Pass when |
|---|---|
| Raise load slowly through each start point with a load bank | The next set starts after the delay and loading after the start matches the design |
| Lower load slowly through each stop point | A set stops only when the rest land well below the start point; no hunting over an hour |
| Apply a step beyond the overload allowance | Shedding acts at once and the next set is called |
| Block a set from starting | The next set is called after the first failed attempt and an alarm is raised |
| Trip a running set at high load | Capacity-based shedding acts and the standby set restores capacity |
| Rotate the lead set | The changeover happens without a load disturbance |
Record the loads, times and frequencies for each test. These records become the baseline for the yearly check, and they settle arguments about whether a later trip was a setting problem or an equipment one.
Reviewing the settings as the site changes
Dispatch settings are written for the load profile on the day of commissioning, and loads change. Review the start and stop points, the reserve rule and the priority order at least once a year against the logged loads and the number of starts per set. A plant that has started making many more starts a day than it used to, or whose sets now spend long hours below half load, is telling you that its thresholds no longer fit the site.
Common mistakes
- Start and stop thresholds too close.
- Start delays longer than the running sets can carry the overload.
- No automatic replacement for a set that fails to start.
- Stopping sets below the reserve needed.
What to send us
Send the load profile, generator data and present dispatch settings. WhatsApp 98852 01608 or use the enquiry form. See also N+1 design.
Evidence note. Thresholds and timings are illustrative; engine and controller makers’ limits govern.
Questions engineers ask
How should generator sets of different sizes be dispatched?
By choosing the combination that keeps the running sets best loaded. With two 800 kW sets and one 400 kW set, the small set can run alone up to about 340 kW, one large set up to 680 kW, a large and a small set up to 1020 kW, both large sets up to 1360 kW, and all three above that, each change made at about 85% loading.
When should the next set be called after a failed start?
As soon as the first cranking attempt fails, not after all attempts. Three attempts of 10 s with 10 s rests take about 50 s, too long when the plant is overloaded or the mains has failed. Start the next set in parallel while the first keeps trying, close whichever is ready first, and alarm every failed attempt.
Why do sets keep starting and stopping?
Because the stop point is too close to the start point, or the delays are too short. After a set stops, the remaining sets must sit well below the start threshold; if they land on it, the next small rise starts the set again. Lower the stop point until the remaining sets would be about 15 points below the start threshold, and lengthen the stop delay.
Should I rotate priority?
Usually yes, so running hours are spread across the sets and every set is exercised. With three sets sharing 6000 hours a year, fixed priority can leave one at about 4000 hours and another at 500. Rotate the lead set, and keep a small deliberate offset so that major overhauls fall in different months rather than all at once.
How much reserve?
Enough to survive the worst credible event without losing essential load: commonly the loss of the largest running set, or the largest load step such as a big motor start. Where holding that much spinning capacity costs too much fuel, a fast load-shedding scheme can cover the gap instead, provided it is designed, tested and kept up to date.
Can dispatch use load forecasts?
Yes, usually through an energy management system that starts a set before a predicted peak instead of waiting for the threshold. The forecast only sets targets; the PMS still enforces the reserve rule, the start and stop thresholds and the engine timers, so a wrong forecast costs some fuel but never leaves the plant short.
Values are illustrative. Tune on site.