Power-Quality Problem → Technology Selection Guide

A practical map from symptom to cause to technology: voltage drift, sags, surges, harmonics, imbalance, noise, outages. Which device fits, what it will not fix, and what to measure first.

In short. Start from the symptom, find its cause in measurements, then choose the technology that acts on that cause. Each device has a defined job and a defined limit. A stabiliser does not cover outages, a UPS is a poor choice for big motors, and a filter does not fix voltage level. Using the wrong one hides the problem instead of solving it.

Who this page is for: For facility managers, maintenance engineers and consultants who have a power quality symptom and need to choose the right fix.

Key facts

  • Measure before you buy: symptom, then recording, then diagnosis, then fix, then re-measure.
  • Sustained high or low voltage is a stabiliser problem; dips and short breaks are a UPS problem; long outages need a generator.
  • Hot transformers and neutrals usually mean harmonics, which need filters or reactors.
  • Noise and earth problems need isolation and earthing work, not voltage correction.
  • Many sites have two or three problems at once and need layered answers.
  • Check every device’s behaviour on generator supply as well as on the grid.

Symptom to technology

SymptomLikely causeTechnologyWill not fix
Motors overheat or trip at low voltageSustained undervoltageServo stabiliserOutages
Resets or lost data during dipsSags, short interruptionsOnline UPSLong outages
Failed electronics after stormsSurgesSurge protectionSustained overvoltage
Hot transformers and neutralsHarmonicsFilters, reactorsVoltage drift
Motor heating with uneven phasesImbalance, phase lossPhase protection, independent-phase regulationThe load imbalance itself
Measurement noise, earth problemsCommon-mode noise, earth loopsIsolation and earthingVoltage level
High bills, power factor penaltiesLow power factorAPFCHarmonics
Long outagesSupply failureGenerator with ATSShort breaks on its own

Worked example: a workshop with nuisance trips (illustrative)

A machining workshop has CNC controllers resetting and motors tripping. A one-week recording at the main board shows:

FindingDiagnosisFix chosen
Line voltage 360 to 440 V over the daySustained drift; the low end is well outside the ±6% of 415 V (about 390 to 440 V) that motors preferServo stabiliser on the machine bus
About 20 dips a day to 80% for 0.1 to 0.3 sSags from neighbouring industrySmall online UPS on each CNC controller
Transformer and neutral running hotHarmonics from drivesLine reactors on drives, then a filter study. See harmonic studies

After the stabiliser and UPS units were fitted, trips and resets stopped. The transformer heating remained until the reactors went in, because it was a separate problem with a separate cause. One device would never have fixed all three.

Do not replace failed equipment, or buy a protection device, before finding the cause. A device that does not act on the cause leaves the problem in place and adds cost.

The diagnostic path

  1. Define the symptom. What failed, when, how often, and what else was running?
  2. Check the basics. Earthing, loose connections, undersized cables, overloaded circuits.
  3. Measure. Voltage, current, harmonics and events at the supply and at the load. See monitoring.
  4. Classify each event by depth and duration, using the table above.
  5. Choose the technology that acts on the identified cause; check it on generator supply.
  6. Verify by measuring again under similar conditions.

Combined problems, layered answers

CombinationLayered answer
Drift plus outagesStabiliser, UPS and generator. See stabiliser plus UPS
Harmonics plus resonance riskDetuned APFC with filters
Noise plus driftStabiliser and isolation transformer
Surges plus outagesSurge protection, UPS, earthing improvement. See UPS and DG

For a whole-site view, see integrated critical-load architecture.

Cost and benefit

Estimate the yearly cost of the problem: lost production, damaged equipment, service calls. Compare it with the life cost of each fix. Do not buy the most expensive option by default, and do not buy the cheapest without checking it acts on the cause.

Problem diagnosis sheet

That second workshop’s five symptoms carried all the way through, which is a different site from the machining workshop in the example above: what was recorded, what was done, and what the second recording showed. The fourth column is the one that turns an opinion into a result.

SymptomMeasured causeTechnology chosenResult after
Drives trip at randomSags to 78% for 180 ms, nine in a week, present on the incoming supplyRide-through configured on the drives, control supplies on a UPSNo trips in 30 days
Lights dim six times a shift11% dip for 1.4 s on every 11 kW coolant pump startStar-delta starting on the pump — fixed at the sourceDip down to 3%, re-recorded for a week
Motor on sub-board 3 runs hot4.5% voltage unbalance on generator, 0.5% on gridSingle-phase load rebalanced across the three phasesUnbalance down to 1.1% on generator
Transformer and neutral run hot28% current distortion; neutral carrying 310 A against a 220 A phase averageLine reactors on the drivesDistortion to 9%, neutral current to 95 A
Boards fail after stormsFour transients, highest 1.8 kV line to neutralSurge protection at the incomer and at the sub-boardNo further failures through one monsoon
    
    
    

Five symptoms, five causes, five different answers — and not one of them is the stabiliser the site was originally quoted. That is the whole argument for measuring first. A single large stabiliser would have corrected the one problem not on this sheet, the afternoon drift, and left all five of these exactly as they were.

Two rows cost almost nothing. Rebalancing the single-phase load in row three was an afternoon’s work with a clamp meter and a few circuit moves. Row two was a starting method on one machine. Between them they account for two of the five complaints, and neither would have been found without a recording that logged current alongside voltage.

Row four is worth noting for the diagnosis rather than the fix. A neutral carrying 310 A on a board whose phases average 220 A is not a wiring error; it is third-harmonic current, which adds in the neutral instead of cancelling. The hot transformer and the hot neutral are the same fault seen in two places, and no voltage-correcting device addresses either.

Measuring before choosing

Every power quality decision is only as good as the measurement behind it. A short recording with a class A power quality analyser at the point where the problem appears, and ideally also at the main incomer, shows whether the disturbance comes from the supply or from the site itself. Guessing from symptoms alone often leads to buying the wrong equipment.

SymptomWhat to recordTypical recording period
Equipment resets or tripsVoltage dips, swells and interruptions with time stampsOne to two weeks, covering busy and quiet days
Overheating cables, neutrals or transformersCurrent harmonics, neutral current, load profileAt least one full production cycle
Flickering lightsFlicker severity and the timing of large load cyclesSeveral days
Low voltage at the far end of the siteVoltage at both ends, current and power factorOne week
Problems only on generator supplyVoltage, frequency and harmonics with the set running on real loadA planned test of several hours

The time stamps matter as much as the values: a dip that lines up with a large motor starting on site has a different cure from one that lines up with a fault on the utility network.

Generator-fed sites need a second look

A generator has a much higher source impedance than a utility transformer, so the same load produces deeper voltage dips and more voltage distortion on generator supply. A UPS rectifier or variable speed drive that runs well on grid can distort the generator voltage enough to upset other equipment. Where a site runs for long periods on generator, the selection is checked on both sources, and the generator alternator and voltage regulator are considered part of the solution rather than a fixed condition.

Writing the specification for the chosen technology

  • State the problem the equipment must solve, with the measured values that define it.
  • State the target after installation, such as a voltage range, a harmonic level or a ride-through time.
  • Give the supply conditions, including operation on generator where relevant.
  • Give the environment: ambient temperature, dust and available space.
  • Require a performance test at commissioning against the stated target.

A specification written this way lets suppliers offer different technologies fairly and gives a clear test of whether the chosen one works.

Verifying the result after installation

Repeat the original measurement at the same points and for a similar period once the equipment is installed. Compare the before and after records side by side. If the target is met, keep the record as the baseline for future checks. If not, the measurement shows what remains, which may be a second problem that the first was hiding, such as harmonics that became visible once the voltage dips were cured.

Keeping the solution effective

Power quality equipment ages and sites change. Filters lose capacitance, stabiliser carbon tracks wear, UPS batteries weaken and new loads are added. A short recording every year, or after any major change in load, confirms that the solution still matches the problem and catches drift before it causes another failure.

Keeping every recording, with the date and the measuring points, builds a power quality history for the site that makes each later decision faster and better founded.

Common mistakes

  • Treating symptoms: replacing equipment without finding the cause.
  • Using a stabiliser for outages, or a UPS for large motors.
  • Skipping earthing and wiring checks.
  • No measurement after the fix.

What to send us

Send recordings, the single-line diagram and a description of the failures. WhatsApp 98852 01608 or use the application engineering enquiry.

Evidence note. The recorded values are illustrative; each site’s measurements decide the fix.

Questions engineers ask

How long should power quality be recorded before choosing equipment?

Long enough to capture the problem and its cause. Trips and resets usually need one to two weeks covering busy and quiet days, overheating needs at least one full production cycle, and generator-related problems need a planned test of several hours with the set on real load.

Why do power quality problems get worse on generator supply?

A generator has a much higher source impedance than a utility transformer, so the same load causes deeper voltage dips and more distortion. Rectifiers and drives that run well on grid can upset other equipment on generator, so selection is checked on both sources before any equipment is ordered.

What should a power quality equipment specification include?

The problem with its measured values, the target after installation, supply conditions including generator operation, the environment such as temperature, dust and space, and a performance test at commissioning against the target. This lets suppliers offer different technologies fairly and gives a clear pass test.

How do I confirm the chosen power quality solution worked?

Repeat the original measurement at the same points for a similar period and compare before and after records. If the target is met, keep the record as a baseline. If not, the data shows what remains, which may be a second problem the first one was hiding.

Can one device solve everything?

Rarely. Each device solves a particular cause: a stabiliser for sustained voltage variation, a UPS for interruptions and fast sags, filters for harmonics, surge protection for transients and power factor correction for reactive demand. Measure first, then choose the device that matches the problem found.

What if I have no data?

Record first, because guessing is costly. A power quality analyser logged for at least a week shows voltage variation, dips, harmonics and events with timestamps, so the device chosen solves the real problem rather than one that was assumed from the symptoms or suggested by a sales brochure.

Do I need a study?

For complex sites, yes, especially where drives, UPS systems, capacitor banks and generators interact, because resonance and distortion depend on the whole network. A study models the site, finds resonance points and tests remedies on the model before anything is purchased or installed. See harmonic studies.

How do I confirm success?

Measure again under similar conditions, with the same loads, the same time of day and the same analyser settings, and compare the results with the original survey. Record equipment trips and failures over the following weeks, so the improvement is shown by data rather than by impression.

Values are illustrative. Selection needs site data.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.