In short. Power quality is about whether electricity is fit for the load, not only whether it is present. Each problem has its own tool: stabilisers for sustained voltage variation, UPS for sags and short breaks, surge protection for transients, filters for harmonics, phase protection for imbalance, isolation for noise and earth problems, and generators for long outages. Measure first, then match the tool to the measured cause, and check how everything behaves on generator supply.
Who this page is for: For owners, facility managers and engineers starting to diagnose or plan power quality and critical power protection for a site.
Key facts
- Problems are defined by depth and duration: drift, sags, transients, harmonics, imbalance, outages.
- A week of recording usually reveals the real problem; guesses are often wrong.
- Each device fixes one class of problem and none fixes all.
- Critical loads usually need layers: surge protection, voltage correction, UPS and generator.
- Generators have higher source impedance than the grid, so problems can look worse on generator.
- Verify every fix with a second recording.
Problems and first-line tools
| Problem | Typical cause | First-line tool |
|---|---|---|
| Sustained low or high voltage | Weak supply, long feeders, heavy loads | Servo stabiliser |
| Sags and short interruptions | Faults, switching, motor starts | Online UPS |
| Transient surges | Lightning, switching | Surge protection |
| Harmonics | Drives, rectifiers, LED drivers, UPS | Harmonic mitigation |
| Imbalance and phase loss | Uneven loads, open phase | Phase protection |
| Noise and earth-loop problems | Shared neutrals, long earth runs | Isolation transformers |
| Long outages | Utility failure | Generator with changeover. See architecture |
Worked example: one site, three problems (illustrative)
A diagnostic centre reported scanner resets, hot air-conditioner units and a failed controller after a storm. A one-week recording found:
| Finding | Class | Tool chosen |
|---|---|---|
| Evening voltage down to about 190 V (L-N) | Sustained drift | Servo stabiliser for the air-conditioning |
| Dips to about 75% for 0.2 s several times a day | Sags | Online UPS for the scanner console and controllers |
| Surge damage after storms | Transients | Layered surge protection at entry and at sensitive boards |
| Outages of up to two hours | Long outage | Generator with changeover behind everything |
No single device would have solved this. The recording decided which tool went where, and a second recording confirmed each fix. See the problem-to-technology guide and integrated critical-load architecture.
Do not buy power quality equipment from symptoms alone. A stabiliser cannot cure sags, a UPS is a poor match for big motors, and surge protection does nothing for low voltage. Record first.
Measure first
A recorder over a week or more shows voltage range, sags, harmonics and imbalance. See power quality monitoring.
On generator supply
Check stabilisers, UPS input windows and power factor capacitors on generator supply as well as on the grid. See UPS and DG and DG and stabiliser.
Site power quality checklist
One factory, filled in across a week of recording and then again after the work. The fourth column is the one most sites never complete, and it is the only one that proves the money was well spent.
| Problem seen | Recorded evidence | Tool | Verified after |
|---|---|---|---|
| Lights dim when the press starts | 11% dip lasting 1.4 s, six times a shift | Servo stabiliser on the lighting and control board | Dip down to 2%, re-recorded for a week |
| Drives tripping on undervoltage, about twice a week | Sags to 78% for 180 ms, present on the incoming supply | Ride-through on the drive, control supply on a UPS | No trips in 30 days |
| Electronic boards failing after storms | Four surge events, highest 1.8 kV line to neutral | Surge protection at the incomer and at the sub-board | No further failures through one monsoon |
| Computers restarting on changeover | 7 s gap at the transfer switch | Online UPS on the server and office board | Clean transfer, no restarts |
| One motor running hot, only on generator | 3.8% voltage imbalance on generator, 0.9% on grid | Single-phase load spread across all three phases | Imbalance down to 1.1% on generator |
Five problems, five different tools, and not one of them would have been fixed by the stabiliser the site originally asked for. The last row is the cheapest fix on the sheet and cost nothing but an afternoon of moving circuits between phases.
Layers of protection for sensitive loads
| Layer | What it handles | What it does not handle |
|---|---|---|
| Surge protection | Short spikes from lightning and switching | Sags, outages, long overvoltage |
| Voltage stabiliser | Slow voltage variations | Interruptions, fast sags, harmonics |
| Isolation transformer | Common-mode noise, earth-neutral voltage | Outages, voltage variation |
| UPS | Interruptions and sags for its battery time | Long outages without a generator |
| Generator | Long outages | The seconds before it starts |
Most critical sites need several layers, chosen from measured problems rather than added by habit.
Worked example: a testing laboratory (illustrative)
A laboratory reports instrument resets and drifting readings. Recording shows evening voltage falls to about 195 V, frequent short sags from a neighbouring factory, and a high earth-neutral voltage. The solution combines a servo stabiliser on the main incomer for the evening low voltage, an online UPS for the instruments to ride through sags and outages, an isolation transformer to give a clean earth reference for the instruments, and the existing generator for long outages. Each element answers a measured problem, and the UPS is checked for compatibility with the generator.
Coordinating maintenance across layers
When one layer is taken out for maintenance, the others must still protect the load. A UPS on bypass leaves loads exposed to sags; a stabiliser on bypass passes low voltage to the UPS, which then works harder. Maintenance is planned so that only one layer is out at a time, in low-risk periods, with the generator ready.
Measures that show the system is working
- Number of equipment resets or trips per month.
- Number of events ridden through by the UPS.
- Voltage range seen at the protected load.
- UPS battery health and generator test results.
Tracking these monthly shows whether the protection matches the problems and when a layer is weakening.
Keeping the site record
A single file holding the power quality recordings, the equipment chosen for each problem, test results and the monthly measures gives anyone reviewing the site a clear picture. It also shows quickly whether a new problem is truly new or a return of one already solved.
Common mistakes
- Buying from symptoms without recording.
- One device expected to fix everything.
- Generator behaviour never checked.
- No second recording after the fix.
What to send us
Send symptoms, any recordings and the single-line diagram. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. Readings are illustrative; site recordings decide each fix.
Which problem each tool actually fixes
Every device in this field fixes one class of problem and leaves the others untouched, which is why a site that buys the wrong one concludes that power quality equipment does not work:
| Tool | Fixes | Does nothing for |
|---|---|---|
| Servo stabiliser | Slow voltage drift and sustained high or low voltage, within its correction range | Outages, millisecond sags, harmonics, transients |
| Isolation transformer | Common-mode noise, earth reference problems, some transient coupling | Voltage level, outages, harmonics |
| Surge protection | Microsecond transients from lightning and switching | Voltage level, sags, outages |
| Online UPS | Outages and sags up to its autonomy, and conditions the output | Long outages without a generator behind it |
| Generator | Long outages | Everything that happens in under a few seconds |
| Harmonic filter or a drive with a better front end | Current distortion, neutral heating, transformer derating | Voltage level, outages, transients |
| Rebalancing single-phase load | Voltage imbalance and neutral current | Everything else — but it is free |
Read the table from the left when someone has already bought something and it has not helped, and from the middle when you have a recording and need to know what to buy. A critical load usually ends up with three or four of these in series, in that order: surge protection at the incomer, voltage correction, then the UPS, with the generator behind all of it.
How to record, so the recording settles the argument
The sheet above only works if the evidence column can be filled, and most disputes about power quality are really disputes about measurement. What to do:
- Record for a full week, not a day. The problem has a pattern — a shift, a shift change, a pump that runs at night, a neighbour’s furnace. A day of logging catches the pattern only by luck, and a site that logs for an hour and sees nothing concludes wrongly that the supply is fine.
- Log at the right place, which is usually two places. One instrument at the incomer and one at the board feeding the equipment that fails. That one comparison answers the question that decides who pays: is the disturbance arriving from outside, or is the site making it?
- Set the resolution to the problem. Ten-minute averages will show voltage drift and will hide a 180 ms sag completely. Anything involving equipment tripping needs event capture at cycle level with a timestamp; anything about transformer heating or tariff is fine on averages.
- Record the load at the same time. A voltage trace with no current trace beside it cannot distinguish a weak supply from a heavy local start, and those have opposite fixes.
- Write down what failed and when. A maintenance note saying “line stopped 14:20 Tuesday” turns a week of waveforms into a diagnosis in ten minutes.
- Record again after the work. This is the fourth column of the sheet, and it is the only proof that the equipment bought was the equipment needed.
On generator supply, repeat the recording with the set running. The source impedance is higher than the grid’s, so the same load behaves differently and a fix that works on mains can be inadequate on the set — which is exactly the situation the fifth row of the sheet records.
Questions engineers ask
Which protection layers does a sensitive load need?
It depends on measured problems. Surge protection handles spikes, a stabiliser handles slow voltage variation, an isolation transformer handles noise and earth-neutral voltage, a UPS covers interruptions and sags for its battery time, and a generator covers long outages. Most critical sites need several layers.
How was power quality solved for the illustrative laboratory?
Recording showed low evening voltage, frequent short sags and high earth-neutral voltage. A servo stabiliser on the incomer, an online UPS for instruments, an isolation transformer for a clean earth reference and the existing generator each answered one measured problem, with UPS and generator compatibility checked.
How should maintenance be planned across power quality layers?
So that only one layer is out of service at a time, in low-risk periods, with the generator ready. A UPS on bypass exposes loads to sags, and a stabiliser on bypass passes low voltage to the UPS, so taking two layers out together removes protection the load depends on.
How do I know a power quality system is working?
Track equipment resets or trips per month, events ridden through by the UPS, the voltage range at the protected load, UPS battery health and generator test results. Monthly review shows whether protection matches the problems and reveals any layer that is weakening before it fails.
Is a stabiliser a UPS?
No. A stabiliser corrects the supply voltage while the supply is present; it has no battery and stops when the supply fails. A UPS carries the load through an outage from its batteries, and a generator takes over for longer outages. Many sites use a stabiliser for voltage, a UPS for sensitive loads and a generator for duration.
Do I need all layers?
No. Each layer is added only where measured data shows a problem it solves: a stabiliser for sustained voltage variation, a UPS for loads that cannot accept a break, filters for harmonics, power factor correction for reactive demand and a generator for long outages. A logged power quality survey shows which layers the site actually needs.
Can one device fix everything?
Rarely. Each device has a defined job: a stabiliser corrects slow voltage changes, a UPS bridges breaks, an isolation transformer separates earth references and reduces common-mode noise, and a filter removes harmonics. A device sold as a cure for everything usually does each job partly, so the measured problem decides the device.
How do I prove improvement?
Measure before and after under similar conditions: the same loads, the same time of day and a similar supply, with the same analyser and logging interval. Compare voltage variation, dips, harmonic distortion, power factor and equipment trips or failures over a few weeks, so the improvement is shown by data rather than by impression.
This guide gives general principles. Selection needs site data.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.