Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

Voltage and Power-Quality Monitoring

How to monitor power quality: what to measure, where to place analysers, recording periods, event triggers and turning logs into decisions on stabilisers, UPS, filters and generators.

In short. Monitoring replaces guesswork with evidence. Record voltage, current, frequency, harmonics, sags, swells and power factor at the right points for a representative period, usually a week. Then compare the events with the equipment’s tolerance and with what the plant was doing at the time. The fix follows from the data, and a second recording proves it worked.

Who this page is for: For maintenance engineers, facility managers and consultants investigating trips, failures or poor supply, or setting up permanent power monitoring.

Key facts

  • Record at least one full operating cycle, often a week.
  • Measure at the supply, at the generator and at the affected load.
  • Set event triggers below the equipment’s tolerance so you catch what matters.
  • Synchronise the clocks of all recorders.
  • Match each event with plant activity to find the source.
  • Record again after the fix.

What to measure

ParameterWhy
Voltage per phaseRange, drift and imbalance
Current per phase and neutralLoading and unbalance
FrequencyGrid and generator stability
Sags, swells and interruptionsEvents that upset equipment
Harmonics and total distortionSources and heating effects
Power factor and kVACapacity and penalties

Where to place recorders

  • At the incoming supply, for the utility view.
  • At the generator output, for generator behaviour.
  • At the sensitive load, for what it actually sees.
  • At large non-linear loads, to identify sources.

Worked example: unexplained drive trips (illustrative)

A plant’s drives tripped a few evenings a week. The maintenance team had already replaced one drive and upsized a breaker. A week of recording at the drive panel showed:

FindingValue
Event timeAbout 6 pm on working days
EventVoltage dip to about 88% for about 0.5 s
Matching activityA neighbour’s furnace starting on the same feeder
Drive undervoltage trip setting90% with no delay

The fix was ride-through: a short undervoltage delay allowed by the drive maker and a small UPS on the control supply. Not a bigger breaker or a new drive. A second week of recording showed the dips still occurring and no trips.

Do not replace equipment or upsize protection before recording. Without data, you may spend money on parts that were never the cause.

Duration and settings

  • At least a week, covering every shift and the weekly cycle.
  • Event triggers below the equipment’s tolerance.
  • Clocks synchronised across all recorders.
  • An instrument with a recognised accuracy class.

Interpreting

  1. Establish normal behaviour.
  2. Match events with plant operations.
  3. Decide which events are harmful to which equipment.
  4. Choose the technology. See the selection guide.
  5. Record again after the fix.

Permanent monitoring

For critical sites, fixed meters with alarms and trends catch drift before failure, like condition monitoring on a generator. Monitor both utility and generator supply; they behave differently. See remote monitoring.

Monitoring plan

PointParametersTrigger levelsStart and end
Incoming supply   
Generator output   
Affected load   

What a recorder actually stores: the averaging intervals

A power quality recorder samples the voltage thousands of times a second, but it does not store every sample. It reduces them to RMS values over fixed intervals, and the interval decides what the record can show. The measurement methods used by Class A instruments, the kind whose results can be compared between instruments and with published limits, define a set of standard intervals, and a good recorder stores several of them at once.

IntervalLength at 50 HzWhat it showsWhat it hides
Half-cycle RMS10 msThe exact shape and depth of dips, swells and interruptionsToo much data to keep for long; stored only around events
10 cycles200 msShort disturbances, motor starts, fast load stepsNothing that matters for most surveys
150 cycles3 sShort-term variation, regulator and stabiliser behaviourDips shorter than a second or so are averaged away
10 minutes10 minDaily and weekly voltage profile, compliance with limitsEvery dip, flicker event and switching transient

A week of 10-minute values is 1008 readings per parameter, easy to plot and to compare with limits, and it is the record most often handed over as “the survey”. It is also the record least able to explain a nuisance trip, because a dip that lasts 150 ms leaves no trace in a 10-minute average. When the purpose of the survey is to find out why equipment trips, set the event capture to record half-cycle values around every dip and swell, and ask for the event list as well as the trend plots.

How dips, swells and interruptions are defined

The instrument decides what counts as an event by comparing the half-cycle RMS voltage with thresholds set as a share of the declared voltage. The thresholds used in the main supply-quality standards are close to universal, which makes reports from different instruments comparable if they were set the same way.

EventThresholdOn a 230 V supplyRecorded as
DipBelow 90% of declared voltageBelow 207 VDepth (lowest voltage) and duration
SwellAbove 110% of declared voltageAbove 253 VHighest voltage and duration
InterruptionBelow 5% or 10% of declared voltage, by the standard usedBelow 11.5 V or 23 VDuration, short below three minutes and long above

Two details catch people out. On a three-phase system, a dip starts when any one phase falls below the threshold and ends when all three have recovered, so a single-phase dip on one phase is still a dip on the system. And the reference voltage can be fixed or sliding: a sliding reference follows the slow changes of the supply, so that a supply sitting at 215 V all evening does not register as a continuous dip. Know which the instrument uses before comparing two surveys.

Checking dips against what equipment tolerates

A list of dips becomes useful when each one is compared with what the affected equipment can ride through. The most widely used reference for information technology equipment is a tolerance curve with three steps: the equipment should survive a complete loss of voltage for up to 20 ms, a dip to 70% for up to half a second, and a dip to 80% for up to 10 seconds, with 90% tolerated indefinitely. Many drives, contactors and control relays are less tolerant than that, and the maker’s own ride-through figures should be used where they exist.

Plot each recorded dip as a point — its duration along the bottom, its remaining voltage up the side — and draw the tolerance curve of each sensitive item over the points. Dips inside the curve should have been survived; dips outside it explain trips. If equipment tripped on a dip inside its own curve, the problem is in the equipment or its settings, not in the supply, and no supply-side improvement will cure it. That one plot settles more arguments between users, suppliers and equipment makers than any other output of a survey.

Reading the flicker figures

Flicker is the visible fluctuation of lighting caused by rapid, repeated voltage changes, and recorders report it as two numbers. The short-term severity, Pst, is measured over 10 minutes and scaled so that 1.0 corresponds to the level at which most people find the flicker of a reference lamp irritating. The long-term severity, Plt, combines twelve consecutive Pst values into a two-hour figure by taking the cube root of the mean of their cubes, which weights the worst periods heavily.

A two-hour period with Pst values of 0.6, 0.7, 0.8, 1.2, 1.5, 0.9, 0.7, 0.6, 0.5, 0.6, 0.8 and 1.0 gives a Plt of about 0.92: below 1.0 overall, although two of the ten-minute periods were above it. The usual planning aim is a Plt no higher than 1.0 for most of the week. When flicker is high, the time pattern points to the source: regular flicker that follows a production cycle comes from the site’s own welders, presses or large motors, while flicker present at night with the site idle comes from the supply.

Voltage unbalance from three readings

Recorders compute voltage unbalance from symmetrical components, as the ratio of negative-sequence to positive-sequence voltage. A close approximation can be made by hand from the three line-to-line voltages: the largest deviation from their average, divided by the average. Readings of 400, 410 and 415 V average 408.3 V; the largest deviation is 8.3 V, or about 2.0%. The supply-quality standards commonly allow up to 2% for most of the week, so this supply is at the limit. Motors feel unbalance far more than the percentage suggests, because the negative-sequence voltage drives a current that heats the rotor, and a motor on a 2% unbalanced supply runs noticeably hotter than its nameplate assumes.

Getting the connections right

More surveys are spoiled by the connections than by the instrument. Current clamps have an accurate range: a 1000 A clamp on a circuit carrying 20 A works at a small fraction of its range and reads both magnitude and phase angle poorly, which spoils power and harmonic figures. Choose clamps sized to the circuit.

Fit each clamp on the phase that its voltage lead is connected to, with its arrow pointing towards the load, and check on the instrument’s phasor display before leaving site that the three currents and three voltages appear in the correct order and that the power on each phase is positive. A survey with one clamp reversed reports nonsense power factors for a week, and the error is discovered only when the week is over.

What a useful survey report contains

The value of a survey is in the report, and a good one can be recognised by what it includes. It states the instrument, its class and calibration date, and the exact connection point of each recorder, with a photograph. It gives the declared voltage, the event thresholds and whether the reference was fixed or sliding, so that the results can be repeated. It shows the week as trend plots of voltage, current, frequency, unbalance, harmonic distortion and flicker, with the 10-minute limits drawn on them.

It lists every event with its time, phases, depth and duration, and plots them against the tolerance curves of the equipment that matters. And it ends with findings tied to evidence: which events caused which trips, which problems come from the supply and which from the site, and what measurement after the fix will show that it worked. A report that offers only a few summary pages of averages, without the event list, has left out the part most likely to explain the problem it was commissioned to solve.

Common mistakes

  • Recording for a few hours only.
  • Recording at the main board only, not at the load.
  • Clocks not synchronised.
  • No second recording after the fix.

What to send us

Send the symptoms, when they happen and any recordings. WhatsApp 98852 01608 or use the application engineering enquiry. See voltage fluctuation.

Evidence note. Values are illustrative; equipment makers’ settings and site data govern.

Questions engineers ask

Why does the 10-minute average not show the dip that tripped my equipment?

Because a dip lasting a fraction of a second is averaged away over 10 minutes. A week of 10-minute values, 1008 readings per parameter, is right for checking the voltage profile against limits but cannot explain a trip. Set the recorder to capture half-cycle RMS values around every dip and swell, ask for the event list with the depth and duration of each event, and plot those events against the tolerance curve of the equipment that tripped.

What do the Pst and Plt flicker values mean?

Pst is the short-term flicker severity over 10 minutes, scaled so that 1.0 is the level most people find irritating on a reference lamp. Plt combines twelve Pst values into a two-hour figure using the cube root of the mean of their cubes, which weights the worst periods heavily. The usual aim is Plt no higher than 1.0 for most of the week. Flicker that follows the production cycle comes from the site, and flicker at night with the site idle comes from the supply.

How long should I record?

Record a full operating cycle of the site, which is often a week, so that weekday and weekend loads, shift changes, peaks and night-time high voltage all appear. Where a fault is intermittent, the analyser stays until the event has been captured at least once, so the diagnosis rests on a recorded event.

What accuracy is needed?

Use a power quality analyser rated to a recognised measurement class, so that readings of voltage, dips, flicker and harmonics follow a defined method and can be compared with limits and with later surveys. Check its calibration date and use the right current clamps for the expected current range.

Can I use the UPS display?

It helps as a first indication, because a UPS display shows input voltage, frequency and events. A dedicated analyser gives far more detail: waveform captures of dips and transients, harmonic spectra, flicker, timestamps to the cycle and logs over weeks, which a UPS display does not keep.

Should I monitor both utility and generator?

Yes, because they behave differently. The grid supply has its own voltage variation and dips, while a generator shows larger frequency and voltage changes on load steps and higher harmonic voltage distortion. A problem that appears only on generator, or only on mains, points directly to the cause and the remedy.

Values are illustrative. Follow standards for method and limits.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.

CallWhatsAppEnquire