Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

ATS and Transfer-System Study Engineering

How to study an automatic transfer system: transfer types, timing, sensing and delays, neutral switching, fault rating, motor and transformer residual voltage, bypass and test procedures.

In short. An automatic transfer switch moves load between the utility and the generator. A transfer system study covers six things: the transfer type, the sensing and delay settings, the fault and withstand ratings, motor residual voltage, neutral switching, and making sure the ATS cannot itself become the reason the site goes down. It turns an equipment purchase into a design that works on the day of an outage.

Who this page is for: For consultants and engineers designing or reviewing transfer systems for buildings, hospitals and plants.

Key facts

  • Transfer type: open, delayed or closed, chosen from the loads.
  • Withstand: the ATS must survive the fault level until upstream protection clears it.
  • Motor loads may need delayed transition or residual voltage checks.
  • Neutral switching (3 or 4 poles) follows the earthing study.
  • Timers balance nuisance starts against outage length.
  • An ATS on a critical load needs a bypass or a second path.

Transfer types

TypeBehaviourTypical use
Open transitionBreak before make, brief outageMost standby systems
Delayed transitionPause in neutral positionLarge motors and transformers
Closed transitionMomentary parallelCritical loads, no-break retransfer

Worked example: withstand check (illustrative)

ItemValueResult
Prospective fault at the ATS30 kA 
Upstream breaker clearing time at 30 kAabout 0.05 s (instantaneous) 
ATS withstand rating30 kA for 0.1 sOK on grid supply
Upstream setting changed for selectivity0.3 s short-time delayExceeds ATS withstand: fails
DecisionATS with a 30 kA short-time rating of 0.5 s chosen, covering the 0.3 s delay plus breaker opening time, keeping selectivity

The upstream setting and the ATS rating had been chosen by different people. The study put them together. See fault current studies.

Do not choose the ATS and the upstream protection separately. An ATS rated only for fast upstream clearing can fail violently if the upstream breaker is later set with a delay for selectivity.

Study items

  • Transfer type from load types.
  • Sensing levels and timers. See ATS and AMF logic.
  • Withstand and coordination with upstream protection.
  • Motor residual voltage and delayed transition for motor loads.
  • Neutral switching. See earthing studies.
  • Bypass and failure modes. See changeover switchgear.

See ATS service and electrical studies.

ATS study sheet

ItemValue
Fault level and upstream clearing time 
ATS withstand rating 
Transfer type and reason 
Poles and earthing 
Bypass or second path 

Sensing and timer settings, and why each exists

An ATS decides from what it measures, so the sensing and timers are as much a part of the design as the switch itself. The values below are typical starting points; the study sets each one from the loads and the generator.

SettingTypical rangePurpose
Normal source undervoltage, dropoutAbout 80 to 90% of nominalDetects a failed or very low supply
Normal source overvoltage, dropoutAbout 110 to 115%Protects loads from a high supply
Phase loss and phase sequenceAll three phases sensedDetects a single blown fuse or reversed rotation
Engine start delayAbout 1 to 5 sRides through brief dips without starting the set
Generator acceptanceAbout 90 to 95% of voltage and frequencyTransfers only to a stable source
Retransfer delayAbout 5 to 30 minutesProves the grid has really returned
Neutral position delayAbout 0.5 to 3 sLets motor residual voltage decay
Engine cool-downAbout 3 to 5 minutesRuns the set unloaded before stopping

Settings that are too sensitive start the set for every flicker; settings that are too slow leave loads off for longer than they can tolerate. The study writes each value down with its reason, so that later changes are made knowingly.

Worked example: the first twenty seconds of an outage (illustrative)

TimeEvent
0 sGrid fails; ATS sees undervoltage on all phases
3 sStart delay ends; start signal sent to the set
About 4 to 6 sEngine cranks and fires
About 10 to 12 sVoltage and frequency inside the acceptance band
About 12 sATS opens the normal side, waits 1 s in neutral, closes on the generator
About 13 to 20 sLoads restart in stages to suit the set’s step capability

About 13 s of interruption is acceptable for lighting, pumps and general loads, but not for IT, controls or medical equipment, which need a UPS to bridge it. Shortening the start delay saves only a little; the engine run-up dominates. Where loads need a faster supply, the answer is a UPS or a battery system, not a more aggressive ATS. See utility and DG transfer control architecture.

Motor residual voltage on transfer

When supply is removed from a running induction motor, it keeps generating a decaying voltage for a short time, while its speed and frequency fall. If the ATS reconnects the motor to a new source while that residual voltage is large and out of phase, the motor sees up to about twice normal voltage across its windings, with a current and torque surge that can damage couplings, shafts and driven equipment, and can trip the protection that has just been reconnected.

A common rule is to reconnect only when the residual voltage has fallen below about 25%, or to transfer within a narrow phase window using an in-phase monitor. Delayed transition, with a timed pause in the neutral position, is the simple and reliable way to achieve the first.

Transfer switch construction and fault duty

ConstructionWhat it can do in a faultDesign consequence
Transfer switch without overcurrent releaseWithstands and makes fault current for a rated time; does not interrupt itUpstream protection must clear within the withstand time
Transfer switch rated with specific upstream breakersWithstand proven only with the named devicesThe named devices must be fitted and kept
Pair of interlocked circuit breakersInterrupts the fault itselfBreaker settings join the coordination study

The withstand and closing rating must be met on every source. A transfer switch that is safe on grid supply, where the upstream breaker trips instantly, may not be safe if a short-time delay is added later for selectivity, as the worked example above shows.

Three poles or four

The number of poles follows the earthing arrangement. Where the generator neutral is bonded to earth at the set, as a separately earthed source, a four-pole switch keeps one neutral-to-earth bond per source, so earth fault current returns on the intended path and earth fault protection measures it correctly. Where the neutral is earthed only at the transformer and carried through without a bond at the set, a three-pole switch with a solid neutral link can be correct. Mixing the two, with bonds at both sources and a three-pole switch, creates a parallel neutral path, nuisance earth fault trips and stray current in metalwork. See earthing system study architecture.

Closed transition: what it demands

A closed transition parallels the two sources briefly, often for no more than about 100 ms, so that retransfer happens without a break. It needs active synchronising within a narrow window, a timer that separates the sources if the switch fails to open, a fault level check for the moment of parallel, protection against reverse power into the grid, and in most cases approval from the supply authority. Where those cannot be met, a fast open transition is the safer choice, with a UPS covering any load that cannot accept the break.

How transfer systems fail

FailureResultDefence
Sensing on one phase onlyLoss of another phase not detected; motors single-phaseSense all three phases and sequence
Controller supply taken from one sourceController dies with that sourceSupply from both sources or a battery
Mechanism stuck in one positionLoad stays on the dead sourceAlarm on failure to transfer, bypass path
Generator start signal wired through one contactSet never startsMonitored or fail-safe start circuit
No exercise for monthsContacts and mechanism stiffenRegular on-load testing

Testing that proves the ATS

  • Monthly: an on-load transfer, timed from grid loss to load restored, with the record kept.
  • Quarterly: a check of every sensing level by injection or by a controlled supply change.
  • Annually: a full test by opening the main incomer, so that the whole chain, sensing, start, transfer and restart, is proved together.
  • After any change to the generator, the loads or the protection: a repeat of the settings review.

Record the transfer time on each test. A slowly rising time is an early warning of a weak battery, a slow engine start or a stiffening mechanism.

Several transfer switches on one generator

Large buildings often have several ATS units, each serving a different load group, all fed from one generator or one paralleled bus. If they all transfer at the same instant, the set receives the whole load as one block step. The study staggers them, by giving each ATS a different transfer delay or by having the plant controller release them in order, life-safety loads first, then critical, then general. The order and the delays are chosen so that each step stays within the set’s load acceptance, and so that the most important loads are restored first. See generator load step and frequency response.

Common mistakes

  • Withstand not checked against upstream delay.
  • Motor residual voltage ignored.
  • Poles chosen by habit.
  • No bypass on critical loads.

What to send us

Send the single-line diagram, fault levels, loads and ATS data. WhatsApp 98852 01608 or use the application engineering enquiry.

Evidence note. Ratings and times are illustrative; makers’ data and studies govern.

Questions engineers ask

How long is the load off during an automatic transfer to generator?

Typically about 10 to 15 seconds. A start delay of about 3 s rides through brief dips, the engine needs several seconds to crank and reach rated voltage and frequency, and the ATS may pause about 1 s in neutral for motor loads. Loads that cannot accept that break, such as IT and controls, need a UPS; a faster ATS setting cannot remove the engine run-up time.

Why should motors not be reconnected straight away after a transfer?

A running induction motor keeps generating a decaying residual voltage after its supply is removed. Reconnecting it out of phase can apply up to about twice normal voltage, with a current and torque surge that damages couplings and driven machines. A common rule is to wait until the residual voltage falls below about 25%, which a short pause in the neutral position achieves.

Do I need a bypass?

For critical loads, yes. A bypass isolation switch lets the ATS be withdrawn for maintenance or repair while the load stays connected to one source, so the transfer switch never becomes the reason for a planned outage. Without one, servicing the ATS needs a shutdown, and a failed mechanism can leave the load stranded on a dead source.

Why is transfer delayed?

To avoid starting the generator for brief dips, to make sure the generator voltage and frequency are stable before load is applied, and to let motor residual voltage decay before the motors are reconnected. Retransfer is delayed to prove that the grid has truly returned, so the load is not switched back and forth during an unstable supply.

What is a four-pole ATS?

A transfer switch that switches the neutral as well as the three phases. It is used where both sources have their own neutral-to-earth bond, such as a generator earthed at the set, so that each source keeps a single bond and earth fault current returns on the intended path. The earthing study decides between three and four poles.

How often should an ATS be tested?

A monthly on-load transfer with the time recorded, a periodic check of the sensing levels, and an annual test by opening the main incomer to prove the whole chain together are a sound regime, adjusted to site policy and applicable standards. A slowly rising transfer time is an early warning of a weak battery or a stiff mechanism.

This guide gives general principles. Confirm with manufacturer data.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.

CallWhatsAppEnquire