In short. An ATS moves the load between the utility and the generator. The design choices are the transition type, the switch rating and number of poles, the sensing and timing logic, and whether a bypass is provided for maintenance. Transition can be open, delayed or closed. The aim is a transfer that is safe and fast enough, and that never connects the two sources by accident.
Who this page is for: For electrical engineers, contractors and facility managers specifying or reviewing automatic changeovers.
Key facts
- Open transition: break before make, with a brief interruption.
- Delayed transition: a set pause in neutral position, so motors and transformers decay before reconnection.
- Closed transition: momentary parallel, needs synchronising and the utility’s approval.
- Rate the switch for load current, fault withstand and the switching duty.
- Pole count (3 or 4) follows the earthing design.
- A bypass lets the ATS be serviced without an outage.
Transition types
| Type | Behaviour | Typical use |
|---|---|---|
| Open (break before make) | Brief interruption | Most standby systems |
| Delayed (neutral position) | Pause with both sources off | Large motor or transformer loads |
| Closed (make before break) | No interruption; brief parallel | Critical loads, retransfer without a break |
Worked example: why delayed transition (illustrative)
A pump station’s ATS transferred back to utility with an open transition in about 100 ms. The 110 kW pumps were still spinning and generating residual voltage out of phase with the returning supply.
| Item | Open transition | Delayed transition |
|---|---|---|
| Dead time | About 0.1 s | About 3 s |
| Motor residual voltage at reconnection | High, out of phase | Decayed |
| Result | Current surge, breaker trips, shaft stress | Clean reconnection |
The longer pause cost a few seconds of interruption but ended the trips. See ATS and AMF logic.
Do not choose an ATS by current rating alone. Check its fault withstand at the point of installation, its transition type against the load, and the pole count against the earthing design.
Rating and selection
- Continuous current and load type.
- Fault withstand and the upstream protection it relies on.
- Pole count. See neutral-earth architecture.
- Interlocking. See interlocking.
- Bypass and isolation for maintenance.
See AMF basics, ATS service and switchboard architecture.
ATS specification sheet
| Item | Value |
|---|---|
| Load current and type | |
| Fault level at the ATS | |
| Transition type | |
| Poles (3 or 4) and reason | |
| Bypass |
Utilisation categories: what the switch is rated to switch
A transfer switch’s current rating means nothing without its utilisation category, which states the kind of load it can make and break at that current. The standard for transfer switching equipment, IEC 60947-6-1, defines the categories below. A switch rated 800 A in category AC-31 is not an 800 A switch for a motor-heavy load.
| Category | Load type | Typical installation |
|---|---|---|
| AC-31 | Non-inductive or slightly inductive loads | Heaters and resistive loads only |
| AC-32 | Mixed resistive and inductive loads, including moderate overloads | General commercial loads without large motors |
| AC-33 | Motor loads, or mixed loads including motors, resistive loads and up to 30% incandescent lamps | Most standby generator installations |
| AC-35 | Electric discharge lamp loads | Lighting boards with discharge lamps |
| AC-36 | Incandescent lamp loads | Incandescent lighting boards |
For a typical generator installation feeding pumps, lifts, air-conditioning and mixed loads, specify AC-33 at the full load current, and ask whether the rating applies at the panel’s internal temperature.
PC class and CB class switches
Transfer switches also come in two classes. A PC-class switch can make and withstand short-circuit current but is not designed to break it; it relies on a breaker or fuses upstream to clear the fault. A CB-class switch is built from circuit breakers with overcurrent releases and can interrupt the fault itself. Changeovers built from two motorised moulded-case breakers are CB-class in function, while dedicated transfer switches are usually PC-class. Both are valid, but the protection scheme must match: a PC-class switch needs an upstream device that clears the fault within the switch’s withstand rating.
Worked example: frame size and fault withstand
A load of 600 kW at a power factor of 0.85 draws about 600 ÷ (0.85 × 1.732 × 0.415) ≈ 982 A at 415 V. A 1250 A switch looks generous, but mounted in a panel whose internal temperature reaches 50 °C, a derating factor of about 0.9 brings its usable rating to about 1125 A: still enough, with less margin than the nameplate suggests.
Next, the fault level at the switch: if the utility side can deliver 25 kA, the switch must either carry a short-time withstand rating at or above 25 kA for the clearing time of the upstream breaker, or carry a conditional short-circuit rating tested with the specific breaker or fuse that protects it. A switch with a 20 kA withstand rating is not acceptable at a 25 kA point, however generous its current rating. See short-circuit and fault-level engineering.
Three poles or four: the neutral question
Whether the neutral is switched depends on how each source’s neutral is earthed. If the utility transformer and the generator are each earthed at their own star point and the neutral is not switched, the two neutrals are permanently joined through the switch, and neutral current returns partly through the earth connections.
An earth-fault or residual current relay then sees part of the normal neutral current as an earth fault, and trips without any fault, or fails to see a real one because the fault current divides between two return paths. A four-pole switch separates the neutrals so that each source has one neutral-to-earth bond in service at a time. A three-pole switch is correct where the system has a single neutral-to-earth bond shared by both sources. Decide this from the earthing drawing, not by habit. See neutral protection and neutral earthing.
Bypass and isolation arrangements
| Arrangement | What it allows | Limitation |
|---|---|---|
| No bypass | Lowest cost | Every service visit to the switch is an outage |
| Manual bypass switch | The load is fed from one source while the transfer switch is isolated | No automatic transfer while bypassed |
| Bypass-isolation transfer switch | The switch can be withdrawn while the load stays supplied; bypass can be to either source | Higher cost; the bypass itself needs interlocking |
| Two switches in series or parallel paths | Redundancy for critical loads | More complex control and interlocking |
Whichever is chosen, the bypass must be interlocked so that it cannot parallel the two sources, and the operating procedure must be posted at the switch. See bypass-isolation ATS.
Replacing an old changeover with an automatic transfer switch
Many sites still change over with a manual switch or a pair of contactors added years ago. When it is replaced, check more than the current rating. Measure the fault level at the point of installation, because the supply may have grown since the original switch was fitted. Trace the neutral and earth connections on both sources before deciding on three or four poles.
Confirm that the generator controller can accept a start signal from the new switch and report its status back, and that the new timers are set from the load list rather than from the old switch’s habits. Plan the cut-over so that the site is not left without either supply while the new switch is wired in.
Maintenance checks that keep the switch reliable
- Operate the switch under load on a schedule, not only on a no-load exercise, so that contacts and mechanism are proven at their working current.
- Measure contact resistance or temperature rise at the terminals; a thermal image under load finds loose connections before they fail.
- Check the operating mechanism, the motor or solenoid and its supply, and the auxiliary contacts that report position to the controller.
- Confirm that the timers and sensing thresholds still match the settings sheet.
- Record every transfer, with the time taken, so that a slowing mechanism shows up as a trend before it fails to transfer.
Transfer time and what the loads can tolerate
The time a switch takes to move from one source to the other, plus any deliberate pause, is a break that every load without UPS experiences. Different loads tolerate very different breaks, and the transition type should be chosen from the load list, not from the catalogue.
| Load | Typical tolerance (illustrative) | Suitable transition |
|---|---|---|
| Lighting, heaters, general sockets | Seconds | Open |
| Running induction motors, pumps, fans | Brief breaks, but not reconnection while residual voltage is high | Delayed, or open with an in-phase monitor |
| Variable-speed drives | A few cycles before tripping on undervoltage | Open with restart enabled, or closed |
| Computers and controls without UPS | About 10 to 20 ms | Closed, or a UPS in front of them |
| Medical and life-safety loads | Set by the applicable code | As the code requires, often with a dedicated switch |
Sensing and the switch’s own control supply
A transfer switch is only as dependable as the voltage it senses and the supply that operates it. The controller must sense all three phases of both sources, and its own control supply must be available whichever source is live: typically taken from both sources through its own small changeover, or from a battery. A motor-operated switch whose motor is fed only from the utility side cannot transfer to the generator after the utility has failed. Test the switch with each source removed in turn, and confirm the controller and the operating mechanism remain powered.
Extra requirements for closed-transition switches
A closed-transition switch parallels the two sources for a fraction of a second, so it needs more than a standard switch. The controller must confirm synchronism before closing: voltage, frequency and phase angle within tight limits. The overlap must be time-limited, typically to around 100 ms, with a backup that opens one source if the overlap is exceeded. The fault level during the overlap includes both sources, and the switchgear must be rated for it. The utility’s approval for momentary paralleling is usually required. See closed-transition and momentary paralleling control.
What a transfer switch specification should state
- Rated current at the panel’s internal temperature, and utilisation category.
- PC or CB class, and the short-time withstand or conditional short-circuit rating with the protective device named.
- Number of poles, with the earthing drawing that justifies it.
- Transition type and the timers it needs.
- Sensing, control supply and the signals sent to the building management or SCADA system.
- Bypass and isolation arrangement, and the interlocking that goes with it.
- Tests required at the factory and on site.
Common mistakes
- Fast open transition on large motor loads.
- Fault withstand not checked.
- Pole count chosen by habit.
- No bypass on a critical supply.
What to send us
Send the load list, single-line diagram and fault levels. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. Times are illustrative.
Questions engineers ask
What utilisation category should a generator ATS have?
For most generator installations, AC-33, which covers motor loads and mixed loads including motors, resistive loads and some incandescent lighting. AC-31 is only for non-inductive or slightly inductive loads, so a switch rated in AC-31 at a given current is not suitable for a motor-heavy load at that current. Check that the rating applies at the panel internal temperature.
When does an ATS need four poles?
When the utility transformer and the generator each have their own neutral-to-earth bond. If the neutral is not switched in that case, normal neutral current divides between the two earth bonds, and earth-fault or residual current relays trip falsely or fail to see real faults. A three-pole switch is correct only where both sources share a single neutral-to-earth bond. Decide from the earthing drawing.
Open or closed transition?
Open transition breaks the load briefly while switching between sources; it is simpler, needs no synchronising and is used on most standby sites. Closed transition parallels the sources for a fraction of a second so the load sees no break, but it needs synchronising, a sync-check relay, a fail-safe timer, utility approval and switchgear rated for the combined fault level.
Why a delay before retransfer?
Because a returning grid supply is often unstable for some minutes, with dips, interruptions or auto-reclose operations. A retransfer delay, often several minutes, confirms the supply is steady before the load is moved back, avoiding repeated transfers that stress motors and switchgear. A cool-down run after retransfer then lets the engine cool before stopping.
Do I need a bypass?
For critical loads, yes. A bypass isolation arrangement lets the transfer switch be isolated, maintained or replaced while the load stays supplied from one source. Without it, servicing the switch means shutting down the load it protects, so the maintenance tends to be postponed. Interlock the bypass so it cannot parallel the two sources.
Can a contactor replace an ATS?
For small loads, a pair of contactors with mechanical and electrical interlocks is common and can work well. Check that the contactors are rated for the utilisation category and fault level, that the interlock prevents both closing, and that the arrangement meets the relevant transfer switch standard where one is required. For larger or critical loads, a purpose-built transfer switch is usually the better choice.
This guide gives general principles. Selection should follow the applicable standards.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.