In short. The single-line diagram (SLD) is the master map of the electrical system. Every study, protection setting, switching procedure and fault investigation depends on it. It must show sources, transformers, switchgear, cables, loads and protection accurately, with ratings, and it must match what is actually installed. An out-of-date SLD is worse than none, because people trust it.
Who this page is for: For facility managers, consultants and electrical engineers who prepare, update or rely on single-line diagrams.
Key facts
- Show every source with its rating and fault level.
- Show transformers with rating, voltage, impedance and vector group.
- Show breakers and switches with rating, breaking capacity and protection.
- Show cables with size, length and type.
- Show earthing and neutral arrangements, including changeover poles.
- Keep it under revision control and update it after every change.
What an SLD must show
| Element | Details |
|---|---|
| Sources | Utility voltage and fault level; generators with kVA, voltage, reactance |
| Transformers | kVA, voltages, impedance, vector group, earthing |
| Switchgear | Ratings, breaking capacity, protection devices and settings references |
| Cables | Size, length, type, route reference |
| Loads | Main loads with kW and starting method |
| Earthing and interlocks | Neutral arrangement, changeover poles, key interlocks |
Worked example: what an SLD audit found (illustrative)
| SLD showed | Installed | Risk |
|---|---|---|
| Generator 500 kVA | 625 kVA after replacement | Fault level and protection based on the old set |
| 4-pole changeover | 3-pole | Earth-fault study wrong |
| Feeder to block C from board 1 | Moved to board 2 some years ago | Wrong isolation during maintenance |
| No revision since 2016 | Several changes since | Every study built on it was unreliable |
The isolation error was the most serious: a technician following the drawing would have isolated the wrong board. The SLD was redrawn from a survey before any study. See brownfield studies.
Do not plan isolation or switching from an SLD that has not been checked against the site. A wrong drawing can lead someone to work on equipment they believe is dead.
Keeping it right
- One master copy, under revision control.
- Update after every change, before closing the work order.
- Survey against site at intervals.
- Use it as the input to every study. See study inputs.
See load list, load flow and short-circuit studies.
SLD check sheet
| Item | Drawing | Site | Match? |
|---|---|---|---|
| Generator rating | |||
| Transformer data | |||
| Changeover poles | |||
| Feeder routing |
What each study takes from the SLD
| Study | What it needs from the drawing |
|---|---|
| Load flow and voltage drop | Every cable size and length, transformer impedance and taps, loads and their supply points |
| Short circuit | Source fault levels, generator reactances, transformer impedance and vector group, cable data |
| Protection coordination | Every protective device, its type, rating and the settings reference |
| Arc flash | Equipment type at every board, plus everything the short-circuit and coordination studies need |
| Earth fault and earthing | Neutral earth points, changeover poles, earthing arrangement of each source |
| Switching and isolation | True feeder routing, every isolation point, interlocks |
One wrong cable length or one missing earth link does not just make one study wrong; it propagates into every study that shares the model. That is why the SLD is checked before the studies start, not afterwards.
Worked example: a revision record that works (illustrative)
| Revision | Change | Reason | Checked against site by | Studies affected |
|---|---|---|---|---|
| E | Generator 500 kVA replaced by 625 kVA | Capacity increase | Site engineer, nameplate photographed | Short circuit, coordination, arc flash |
| F | Changeover shown as 3-pole | Survey found 3-pole installed | Survey team | Earth fault, earthing |
| G | Block C feeder moved to board 2 | Drawing corrected to match site | Survey team, cable traced | Load flow, isolation procedures |
The last column is what makes the record useful: every change states which studies must be revisited, so a drawing change automatically raises the question of whether the protection settings and arc-flash labels are still valid.
Symbols and conventions
Use one consistent symbol set, such as the internationally standardised graphical symbols, and a legend on every sheet. Show normal switch positions consistently, open or closed as they stand in normal operation, and mark normally open points clearly. Give every board, breaker and cable a unique identifier that matches the labels on the equipment, so that an instruction to open breaker MB2-Q5 means one device only, on the drawing and in the switchroom.
Drawing it from a survey
- Start at each source and trace outwards, board by board, reading nameplates and breaker labels.
- Trace each outgoing cable to where it lands, rather than trusting labels or old drawings.
- Record cable size, type and an estimated or measured length for every feeder that matters to a study.
- Read protection device types and settings, and note where settings could not be read.
- Identify every neutral-earth link and the poles of every changeover device.
- Mark anything unverified as such on the draft, so nobody mistakes an assumption for a survey result.
The drawing at the switchboard
Operators switch from the copy on the switchroom wall, not from the master on a server. Keep a current, legible copy at each main board, showing at least that board’s sources, outgoing feeders, isolation points and interlocks, with the revision letter matching the master. Replace it every time the master changes, and remove the old one. A wall copy two revisions old is the commonest route by which a correct master drawing still leads to a wrong isolation.
One model for the drawing and the studies
Where studies are done in software, the network model and the SLD should be one source of truth, or at least checked against each other at every revision. A study model updated for a new generator while the drawing is not, or the reverse, recreates exactly the gap the revision process exists to close. Record in the revision log which study model version matches each drawing revision.
The yearly review
Once a year, and after any significant project, walk the main switchrooms with the drawing and check sources, transformers, changeover poles, the main feeders and the neutral-earth links against what is installed. Correct the drawing first, then ask whether any study, setting or procedure built on the old revision needs to change.
Levels of drawing, and what each is for
| Drawing | Shows | Used for |
|---|---|---|
| Overall SLD | Every source, transformer and main board, with ratings and main interconnections | Studies, planning, operating overview |
| Board SLDs | Every outgoing feeder of a board with device, rating, cable and load | Isolation, maintenance, feeder studies |
| Protection SLD | CTs, VTs, relays and their functions and trip paths | Protection settings and testing |
| Earthing diagram | Neutral earth points, earth conductors, changeover poles | Earth-fault studies and safety |
All levels carry the same identifiers and revision discipline, and a change to one checks the others.
What surveys usually find
- Generators, transformers or breakers replaced without the drawing being updated.
- Feeders moved between boards during past projects.
- Spare ways used for new loads that appear nowhere on the drawing.
- Neutral-earth links added or removed during maintenance.
- Changeover devices with a different number of poles from the drawing.
- Labels on equipment that disagree with the drawing, or with each other.
Any one of these can make a study wrong or an isolation unsafe, which is why the survey comes before the studies, not after them.
What the generator changeover must show
The changeover is where most generator-site errors start, so it deserves the most detail on the drawing: the mains and generator devices with their ratings and number of poles, the mechanical and electrical interlocks, the AMF controller and its sensing points, the generator’s neutral earth link or its absence, the loads that transfer and those that do not, and any load-shedding or restart arrangement. With that shown, the earth-fault, short-circuit and transfer studies can all be built from the drawing without a site visit to find out how the changeover really works.
The drawing at the end of every project
Make the updated SLD a deliverable of every electrical project, checked against the installed equipment before the project is closed and the final payment made. The contractor marks up the changes; the owner’s engineer checks them on site and issues the new revision. A project that leaves the drawing as it was has left a fault in every future study.
Keeping the drawing in digital form
Hold the master SLD in an editable drawing format, not only as a scanned print, and keep it in one controlled location with its revision history. Export a dated PDF for each issued revision, and make the current version easy for site staff to find, on a shared drive or printed and posted at the main switchboard. Where the site uses a study software model, link the identifiers so that the drawing and the model can be compared quickly after every change. A drawing that only one person can find or edit will fall out of date the first time that person is away.
Who signs the drawing
Each revision should name who surveyed the changes, who drew them, and who checked them on site, with dates. For changes that affect protection, earthing or the generator changeover, the check should be done by a competent electrical engineer rather than by the person who made the change. These signatures turn the drawing from a picture into a record that others can rely on when they isolate equipment or base a study on it.
A short checklist before issue
- Every source, transformer and board shown, with rating and identifier.
- Every protective device shown with its type, rating and number of poles.
- Cable sizes, lengths and conductor material on every main feeder.
- Neutral earth points and changeover arrangements drawn as installed.
- Normal open points and interlocks marked clearly.
- Revision, date, surveyor and checker recorded on the title block.
A drawing that passes this list is ready to be the base for every study on the site and for safe isolation by the people who operate it.
Common mistakes
- No revision control.
- Ratings missing.
- Earthing and interlocks not shown.
- Never checked against site.
What to send us
Send your current SLD and any changes you know about. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. Findings are illustrative.
Questions engineers ask
What information do power system studies need from the SLD?
Load flow needs every cable size and length, transformer impedance and loads; short circuit needs source fault levels, generator reactances and transformer vector groups; coordination needs every protective device and its settings reference; earthing studies need neutral earth points and changeover poles; isolation needs true feeder routing. One wrong entry spreads into every study.
How should changes to a single-line diagram be recorded?
In a revision record listing each change, its reason, who checked it against the site and which studies it affects. For example, a generator replaced by a larger one affects the short-circuit, coordination and arc-flash studies. The affected-studies column makes every drawing change raise the question of whether settings and labels are still valid.
Why does a “single line” show three phases?
Because drawing all three phases for every circuit would make the diagram unreadable. One line represents the three-phase circuit, with the phase count, neutral and earthing shown by notes and symbols where they matter, such as at changeover devices. Detailed three-line or schematic drawings cover wiring for specific equipment.
How accurate must it be?
Accurate enough that studies built on it give correct answers and switching and isolation done from it are safe. That means every source, transformer, protective device and main cable shown with its real rating, size and routing, verified against the site. Anything unverified should be marked as such on the drawing.
Who owns the SLD?
The facility owner or operator, usually through a named engineer who holds the master copy and approves every revision. Contractors propose changes, but the owner keeps the master, the revision record and the copies at the switchboards, so that the drawing outlives any one project or contractor.
Do I need separate SLDs for each mode?
Not necessarily. One SLD with the normal switch positions and clearly marked normally open points can serve all modes, provided each operating mode, grid, generator, island and maintenance, is defined in notes or a mode table and studied. Very complex sites sometimes add simplified mode diagrams for operators.
This guide gives general principles. Drawings must reflect the actual installation.