In short. Connected load is the total of every rating installed. Demand load is what the site actually draws over a defined interval. Maximum demand is the highest of those demands over a period such as a billing month. Generators and transformers are sized on maximum demand, plus the starting step of the largest motor and an allowance for growth, never on connected load alone. Sizing on connected load typically buys 1.5 to more than 2 times the capacity a site needs, and the oversized set then runs lightly loaded for its whole life.
Who this page is for: For engineers, consultants and facility managers sizing a generator or transformer: turn a load list or electricity bills into a defensible maximum demand instead of a guess.
Key facts
- Connected load is the sum of all installed ratings; maximum demand is the highest measured demand over a period.
- Demand factor = maximum demand ÷ connected load.
- Diversity factor = sum of individual maximum demands ÷ combined maximum demand, always 1 or more.
- Size generators on maximum demand plus the largest motor start and planned growth.
- Sizing on connected load typically buys 1.5 to more than 2 times the capacity needed.
- Never apply diversity to fire pumps and life-safety loads.
Definitions and formulas
| Term | Meaning | What it is used for |
|---|---|---|
| Connected load | Sum of the nameplate ratings of everything installed | Upper bound and supply application forms; rarely the design figure |
| Demand load | Average load drawn over a defined interval | The basis for sizing |
| Maximum demand (MD) | Highest demand over a period, usually a 15- or 30-minute average | Utility billing, transformer and generator sizing |
| Contract demand | The demand sanctioned by the utility for the service | Tariff and minimum billing; not a measurement |
| Demand factor | Maximum demand of a group ÷ its connected load | Applied within a group of similar loads |
| Diversity factor | Sum of the individual maximum demands ÷ the combined maximum demand | Applied between groups that peak at different times; always 1 or more |
| Coincidence factor | 1 ÷ diversity factor | The same idea written as a fraction |
| Load factor | Average load ÷ maximum demand over the same period | Fuel and energy planning; shows how “peaky” the site is |
Why connected load is the wrong design figure
Loads do not all run at once. Duty and standby pumps never run together, lifts move in turns, workshop machines run one job at a time, and seasonal air conditioning peaks only in summer afternoons. A generator sized on connected load is oversized from the day it is installed. It costs more to buy, house and maintain, and then spends most of its hours below 30% load, which raises fuel use per unit and causes wet stacking. Sizing on average load is the opposite mistake: the set trips at the first peak. The design figure is maximum demand, measured or carefully estimated, with separate allowances for motor starting and growth.
What the electricity bill’s maximum demand does and does not tell you
The MD on a DISCOM bill is the highest average demand recorded in a fixed integration window, commonly 15 or 30 minutes, during the billing month. It is a useful starting point and it is free. For generator sizing it has three limits.
- It averages away short peaks. A chiller or pump that starts and runs for five minutes barely moves a 30-minute average, but a generator sees the full current instantly.
- It ignores starting current. Motor starts last seconds. They never appear on a bill, yet they often decide the generator size.
- It shows grid-hours behaviour. During an outage some loads are shed by design, while others, such as cooling, can rise. The generator’s demand is the demand during an outage, not the monthly peak on grid.
Where the bill shows only kWh and kVAh, the average power factor is kWh ÷ kVAh for the month, which helps convert kW demand to kVA.
Sources of demand data, best first
| Source | What it gives | Limits |
|---|---|---|
| Power analyser logging at 1-second to 1-minute intervals, for at least one full operating week | True peaks, the load profile, power factor, unbalance and harmonics | Must cover the busiest period: summer, peak production, full occupancy |
| Utility meter interval data, where the DISCOM provides it | Accurate 15- or 30-minute demand over months | Averaged; no starting peaks |
| Twelve months of bills | Monthly MD and seasonal pattern | One number per month |
| Clamp-meter readings at feeders during peak operation | A quick snapshot by group | Easily misses the real peak |
| Load list with demand factors (new buildings) | The only option before the site exists | Depends on honest factors; refine after commissioning |
Build the list in the load list builder or follow the load list and load schedule guide.
The method, step by step
- Decide what the generator must carry. Whole site, essential loads only, or critical loads only. See critical load classification.
- Group the loads by board and by behaviour: lighting, air conditioning, pumps, lifts, process motors, UPS and IT, and so on.
- Apply a demand factor to each group, justified by how the site operates. Measured values beat typical ones.
- Apply diversity between groups only where they genuinely peak at different times.
- Convert to kVA using each group’s power factor, not one assumed figure for the site.
- Add growth that is actually planned, typically 10 to 20%.
- Choose the rating so that the design kVA sits at about 70 to 80% of the set’s rating for prime running.
- Check the largest motor start against the chosen set’s voltage dip, separately. See motor starting on generators.
Typical demand factors (starting points only)
| Load group | Typical demand factor | Notes |
|---|---|---|
| Lighting in offices and common areas | 0.7 to 0.9 | Close to 1 at night for security and street lighting |
| Air conditioning and chillers | 0.7 to 0.9 in summer | Use the summer figure in Telangana and Andhra Pradesh |
| Lifts (several in a building) | 0.3 to 0.5 | Higher where lifts are few and busy |
| Water pumps, duty and standby | 0.5 or lower | Count only the duty pumps that run together |
| Workshop machine tools | 0.2 to 0.4 | Many machines, few running at once |
| Continuous process motors | 0.8 to 1.0 | Little diversity in a running line |
| UPS and IT | Use the UPS input at design load, plus battery recharge | Do not apply generic diversity |
| Fire pumps and life-safety loads | 1.0 | Never apply diversity to life-safety loads |
Worked example: a gated community of 240 flats (illustrative)
A four-block community in Hyderabad wants generator backup for common services and limited backup to each flat. The load list is grouped and factored like this.
| Group | Connected kW | Demand factor | Demand kW | PF | Demand kVA |
|---|---|---|---|---|---|
| Common-area and street lighting | 40 | 0.9 | 36.0 | 0.95 | 37.9 |
| Lifts, 8 × 11 kW | 88 | 0.4 | 35.2 | 0.80 | 44.0 |
| Water pumps, 8 × 15 kW (4 duty + 4 standby) | 120 | 0.5 | 60.0 | 0.85 | 70.6 |
| Sewage and water treatment | 45 | 0.7 | 31.5 | 0.85 | 37.1 |
| Clubhouse air conditioning | 90 | 0.8 | 72.0 | 0.85 | 84.7 |
| Flat backup, 240 × 1.5 kW | 360 | 0.35 | 126.0 | 0.90 | 140.0 |
| Total | 743 | 360.7 | 414.3 |
The overall power factor is about 313.7 kW ÷ 360.3 kVA ≈ 0.87. The largest motor is a 15 kW pump started direct-on-line, about 120 kVA of starting demand. On a 500 kVA set with a transient reactance of 0.25 per unit, the dip is about (0.25 × 0.24) ÷ (1 + 0.25 × 0.24) ≈ 6%, comfortably inside the usual 15 to 20% limit.
The connected load converts to about 850 kVA. A set chosen on connected load at the same 80% loading would be about 1065 kVA, more than twice the 500 kVA the demand needs. The difference is capital, room space, and years of light-load running. For more on this kind of site, see generators for apartments and gated communities.
Checking the estimate against measurement
After the first summer on the new set, compare the estimate with logged data. In the example above, a 30-minute bill MD of 340 kVA with a 1-minute logged peak of 385 kVA would confirm the estimate. The 500 kVA set then runs at about 68 to 77% at peak, which is a healthy loading. If the logged peak were near 450 kVA, the demand factors were optimistic and load management or a second set needs planning before growth is added.
The outage view: what the generator really carries
Normal-day maximum demand and outage demand are different numbers. During an outage, non-essential loads may be shed through the changeover or a load-shedding scheme, but cooling loads that were idle can start together when the set comes on. Several air-conditioning units restarting at once can exceed the steady demand. Stagger their restart with timers or a building management system, or include the combined restart in the sizing. For critical-load-only backup, use the critical subtotal and its own diversity. See generator sizing.
Demand worksheet
| Column | What to enter |
|---|---|
| Board and group | Where the load is fed from and what kind of load it is |
| Connected kW | Sum of nameplates in the group |
| Demand factor and its basis | Measured, from operations, or typical (say which) |
| Demand kW and power factor | Demand kW = connected kW × demand factor |
| Demand kVA | Demand kW ÷ power factor |
| Carried on generator? | Yes, no, or shed after a delay |
| Largest motor and starter type | For the separate starting check |
| Diversity between groups and growth | Stated once, with the reason |
Never apply diversity to fire pumps, life-safety systems or critical IT loads. Size the generator to carry them in full alongside the rest of the essential load.
Exceptions where diversity must not be used
- Fire pumps and life-safety systems. Size for their full demand with the rest of the essential load running.
- Data centres and critical IT. Use the UPS input at full design IT load plus battery recharge.
- Single large process loads. One furnace or one mill motor is not diversified by anything.
- Non-linear loads. UPS and VFD-heavy sites may need a larger alternator than the kVA demand suggests. See non-linear loads.
Checking the season before trusting a record
A demand record from a cool month understates the summer peak on sites where cooling is a large share of load, and a record taken during a production slowdown understates the busy season. Before using a recorded maximum demand for sizing, compare it with the utility’s billed maximum demand for the same months of earlier years, and scale it, with the reason stated, if the record missed the peak season. See electrical capacity expansion and future-proofing studies.
Common mistakes
- Using connected load as the design load.
- Applying diversity without operational evidence, or applying it twice: once inside groups and again between them for the same reason.
- Logging for one day that missed the real peak, or logging in the monsoon and sizing for summer.
- Taking the bill’s 30-minute MD as the peak a generator must carry.
- Forgetting the motor starting check after the steady-state sizing.
What to send us
Send twelve months of electricity bills, any logged or interval data, the load list or single-line diagram, the largest motors and their starters, and which loads must run during an outage. WhatsApp 98852 01608 or use the enquiry form. Our service engineers will turn it into a demand estimate and a generator rating you can check line by line.
Evidence note. Demand factors above are typical starting points used in practice and must be replaced by measured or operational values wherever they exist. The worked example is illustrative.
Questions engineers ask
Can a demand record from one month be used to size a generator?
Only if that month includes the true peak. A record from a cool month understates summer cooling load, and one taken during a production slowdown understates the busy season. Compare it with billed maximum demand for the same months of earlier years, and scale it, with the reason stated, if it missed the peak.
What is the difference between demand factor and diversity factor?
Demand factor is the maximum demand of a group divided by its connected load, so it is 1 or less. Diversity factor is the sum of the individual maximum demands of several groups divided by their combined maximum demand, so it is 1 or more, because the groups peak at different times.
What is a typical demand factor?
It varies widely with the type of site and load group, from close to 1 for continuous process loads and IT to well below 0.5 for groups of many intermittent loads such as workshop machines or general sockets. Measured demand is always better than a typical factor, which is only for early estimates.
How long should I record?
At least a full week covering every shift, weekend and normal operating pattern, and ideally through the busiest season. Short recordings miss the true peak. Utility billing records over a year show the seasonal maximum and help judge whether the recording period captured it, or whether the record must be scaled for the busy season.
Is maximum demand the same as peak current?
No. Maximum demand is an average over a demand interval, commonly 15 or 30 minutes, so short peaks such as motor starts are smoothed out. A generator must also handle those short peaks, which is why the largest motor start is checked separately from maximum demand, using the starting kVA and the set transient data.
Can bills show true demand?
They show the billed maximum demand at the supply point over each billing period, which is a good measure of the whole site peak on grid. They do not show demand by board, generator mode load, power factor detail or short peaks, so bills are combined with site recordings for sizing.
This guide gives general principles. Use measured data wherever possible.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.