In short. An earthing study answers three questions. Can earth-fault current return to its source safely? Will the voltages a person could touch or step across during that fault stay within tolerable limits? Will the protection operate fast enough? It starts with measured soil resistivity and the earth-fault current for every source arrangement, including generator supply. It then designs the electrodes, grid, conductors and neutral arrangement, and proves the design by calculation first and measurement after construction.
Who this page is for: For consultants, plant engineers and project teams planning the earthing for a substation, a generator plant or a large industrial site, and for anyone asked to accept an earthing design.
Key facts
- Soil resistivity is measured, not assumed: the Wenner method gives ρ = 2π × a × R.
- Ground potential rise (GPR) = earth-fault current into the grid × grid resistance.
- Tolerable touch voltage for a 50 kg person: (1000 + 1.5 × Cs × ρs) × 0.116 ÷ √t.
- A crushed-rock surface layer raises the tolerable touch and step voltages several times.
- Earthing conductor size: S = I × √t ÷ k.
- Low electrode resistance alone does not prove safety; touch voltages and fault-loop impedance do.
The study workflow
| Step | Input | Output |
|---|---|---|
| 1. Scope | Site layout, voltage levels, sources, applicable standards | What must be designed and checked |
| 2. Soil survey | Resistivity measurements at several spacings and locations, ideally in the dry season | A soil model, often two layers |
| 3. Fault data | Earth-fault current and clearing time for grid and generator supply | The current that flows into the earth grid and for how long |
| 4. Neutral earthing | Source types and protection philosophy | Solid, resistance or high-impedance earthing for each source |
| 5. Preliminary design | Area, conductor and rod layout | Grid geometry and conductor sizes |
| 6. Calculation | Soil model, geometry, fault current | Grid resistance, GPR, touch and step voltages |
| 7. Refinement | Areas that fail the limits | Closer mesh, more rods, surface layer, gradient control |
| 8. Verification | Built installation | Measured resistance, continuity and loop impedance |
Measuring soil resistivity
The Wenner four-pin method places four electrodes in a line at equal spacing a. Current is passed between the outer pins, voltage is measured between the inner pins, and the apparent resistivity is:
For example, a reading of 1.6 Ω at a 3 m spacing gives ρ = 2π × 3 × 1.6 ≈ 30 Ω·m. Measuring at several spacings, such as 1, 2, 4, 8 and 16 m, shows how resistivity changes with depth. In Telangana and Andhra Pradesh, rocky ground and the dry season can raise resistivity many times over the monsoon value, so design on dry-season readings. See earth electrodes and soil resistivity.
Tolerable touch and step voltage
For substations and HT installations, the widely used method limits touch and step voltage according to fault duration and the resistivity of the surface layer a person stands on. For a 50 kg body:
Here ρs is the surface-layer resistivity, Cs a correction for a thin surface layer, and t the fault duration in seconds. For a 70 kg body, 0.157 replaces 0.116.
| Case, fault cleared in 0.5 s | Tolerable touch voltage | Tolerable step voltage |
|---|---|---|
| Natural soil, ρs = 100 Ω·m, Cs = 1 | (1000 + 150) × 0.164 ≈ 189 V | (1000 + 600) × 0.164 ≈ 262 V |
| 10 cm of crushed rock, ρs = 3000 Ω·m, Cs ≈ 0.7 | (1000 + 3150) × 0.164 ≈ 681 V | (1000 + 12,600) × 0.164 ≈ 2230 V |
A thin layer of clean crushed rock raises the tolerable touch voltage more than three times, which is why switchyards and generator plant yards are gravelled.
Grid resistance and ground potential rise
A simple first estimate of the resistance of a grid with area A and total buried conductor length L is:
A 20 m × 20 m grid (400 m²) with 200 m of buried conductor in 100 Ω·m soil gives r ≈ 11.3 m and R ≈ 100 ÷ 45.1 + 100 ÷ 200 ≈ 2.2 + 0.5 ≈ 2.7 Ω. If 500 A of earth-fault current flows into this grid, the ground potential rise is 500 × 2.7 ≈ 1350 V. That is well above the 189 V tolerable touch voltage on natural soil, so the design needs a closer mesh, which keeps the actual touch voltage to a fraction of the GPR, plus a crushed-rock surface layer and a check of the touch voltage at the corners of the grid, where it is highest. Detailed calculation methods then refine these first estimates.
A low earth-pit resistance reading is not proof that an installation is safe. Touch and step voltages during a fault, and whether the protection clears it in time, are what protect people. Ask for both to be shown in the study.
Sizing earthing conductors
For example, a 10 kA earth fault cleared in 1 s with k ≈ 143 (an insulated copper conductor) needs S ≈ 10,000 × 1 ÷ 143 ≈ 70 mm² of copper. The k value depends on the conductor material, the insulation and the final temperature allowed, so take it from the applicable standard’s table. Choose the next standard size and add a corrosion allowance for buried steel.
Decisions specific to generators
| Question | What the study must settle |
|---|---|
| Where is each neutral earthed? | At the generator, at the transformer, or at a common point, for each source arrangement |
| Three-pole or four-pole changeover? | Four-pole keeps one neutral-earth link per source and prevents stray neutral current in the earth system |
| Parallel generators | Third-harmonic current can circulate between sets through multiple neutral earths; neutral switching or reactors may be needed |
| Generator earth-fault current | Often lower than on grid supply; protection must still clear it in time |
| Rental and temporary sets | Local electrodes, bonding and testing on every deployment. See temporary site earthing |
For the DG set’s own earth pits and connections, see DG set earthing installation and the earthing design calculation guide.
Verification after construction
- Earth electrode and grid resistance by the fall-of-potential method. See earth resistance testing.
- Continuity of every bonding and earthing conductor.
- Earth fault loop impedance at the remote ends of circuits, on each source.
- Touch voltage measurement at critical locations on large installations.
- Re-measurement in the dry season and after civil works.
Earthing study input worksheet
| Input | Value | Source or test reference |
|---|---|---|
| Soil resistivity at several spacings (Ω·m) | ||
| Earth-fault current, grid supply (A) and clearing time (s) | ||
| Earth-fault current, generator supply (A) and clearing time (s) | ||
| Neutral earthing of each source | ||
| Grid area and buried conductor length | ||
| Surface layer type and thickness |
The order a study has to be done in
An earthing study is usually commissioned as a single deliverable and then found, late, to have answered its questions in the wrong sequence. Each step below depends on the one above it, and a step taken before its input exists produces a number that looks like a result and is not one. The column that matters most is the last.
| Step | The question it settles | What it needs settled first | What a site gets wrong by skipping it |
|---|---|---|---|
| 1. System earthing | Where the source neutral is earthed in every operating mode, and what is bonded to what | The single-line diagram and the transfer arrangement | Everything downstream is designed for a fault path that does not exist in one of the modes |
| 2. Fault level and duration | How much earth-fault current can flow, from each source, and for how long before a device clears it | Step 1, plus source impedances and protection grading | Conductors sized on load current rather than on what a fault asks them to survive |
| 3. Soil model | What the ground will actually do, as measured rather than assumed | Nothing, which is why it is so often left until last | An electrode design built on a textbook resistivity, then redesigned after the first test |
| 4. Electrode arrangement | Geometry, depth, material and layout to suit the soil and the fault duty | Steps 2 and 3 together | A pit count copied from another site, sized for neither the soil nor the current |
| 5. Conductor sizing | Cross-section of protective and bonding conductors for the fault they must carry | Step 2, and the material and installation conditions | A conductor that passes a continuity test and fails the one fault it was installed for |
| 6. Touch and step safety | Whether a person standing at the wrong place during a fault is within safe limits | Steps 2, 3 and 4 | A low resistance figure reported as a safe installation, which it does not by itself prove |
| 7. Test and acceptance | What will be measured, by what method, and what result closes the item | All of the above, so the criteria are known before anyone is on site | Tests chosen on the day, with no stated pass criterion and nothing to compare later readings against |
Step 3 is the one that moves in the programme, and it is the one that should not. Soil measurement needs no design information and can be done the week the site is handed over, yet it is routinely deferred until the electrodes are being installed — at which point the design has already been drawn against an assumed figure. Of the seven steps it is the cheapest to do early and the most expensive to discover late, because it is the only one that can make steps 4, 5 and 6 all wrong together.
The dependency chain also explains why two studies of the same installation can disagree without either being careless. If one assumes the neutral is earthed at the transformer in all modes and the other traces an arrangement where the generator neutral earths the system while the mains is off, every figure after step 1 diverges — not because the arithmetic differs but because they are studying two different electrical systems. Settling step 1 against the real transfer scheme, in writing, before anything is calculated, removes the commonest cause of a study that has to be redone.
One practical note on step 7. Acceptance criteria written after the readings are taken are not criteria, and they are visible as such to anybody reviewing the file later. State the method, the instrument, the conditions and the pass figure before the test, and record the season and the weather with the result. An installation whose history consists of a single number per year, with no method and no conditions beside it, cannot be trended — and a trend is the only thing that tells a site its earthing is degrading before a fault does.
Worked example: designing an earth grid (illustrative)
An 11 kV substation and generator plant occupies a 40 m by 30 m yard on soil measured at about 100 Ω·m. Of a 4000 A earth fault on the 11 kV side, about half returns through cable sheaths and the source neutral, so about 2000 A flows into the grid, and the protection clears it in 0.5 s. The method below follows the widely used IEEE 80 approach in simplified form.
| Step | Working | Result |
|---|---|---|
| Grid layout | 5 m mesh: 7 conductors of 40 m and 9 of 30 m, buried at 0.6 m, plus ten 3 m rods at the perimeter | 550 m of conductor, 30 m of rods |
| Grid resistance | R = ρ [1 ÷ L + 1 ÷ √(20A) × (1 + 1 ÷ (1 + h√(20 ÷ A)))] | about 1.42 Ω |
| Ground potential rise | 2000 A × 1.42 Ω | about 2830 V |
| Tolerable touch, 50 kg person, bare soil | (1000 + 1.5 × 100) × 0.116 ÷ √0.5 | about 189 V |
| Tolerable touch, with 100 mm crushed rock of 3000 Ω·m | (1000 + 1.5 × 0.70 × 3000) × 0.116 ÷ √0.5 | about 681 V |
| Calculated mesh (touch) voltage | ρ × Km × Ki × IG ÷ LM | about 419 V |
| Calculated step voltage | ρ × Ks × Ki × IG ÷ LS | about 318 V, against about 2231 V tolerable with the rock layer |
The ground potential rise of about 2830 V is far above the tolerable touch voltage, so the design cannot rely on a low resistance alone. The mesh voltage of about 419 V fails the 189 V limit on bare soil and passes the 681 V limit once the crushed-rock layer is laid, so the surface layer is part of the design, not decoration. The step voltage passes comfortably with the rock in place.
When the calculation fails
- Close the mesh: a 4 m spacing in place of 5 m lowers the mesh voltage where people stand.
- Add rods at the perimeter and corners, where the voltage gradients are steepest.
- Lay or maintain the crushed-rock surface layer, and keep it clean of soil and vegetation that lower its resistivity.
- Reduce the current entering the grid, through cable sheath bonding or resistance earthing of the source neutral where the protection allows it.
- Bury a gradient-control ring outside the fence and bond the fence, or isolate it, so a person outside cannot touch it during a fault.
Each change is recalculated, and the built grid is measured: resistance by the fall-of-potential method and, on large grids, touch voltages by current injection. The calculation and the measurement together are what an acceptance is based on.
The same yard on generator supply
On generator supply the earth-fault current is set by the generator’s reactance and its neutral earthing, and may be far smaller than the grid figure. A smaller current lowers the ground potential rise but can also slow the protection, and the clearing time enters the tolerable-voltage formula through its square root. A study therefore runs both cases, grid and generator, and the design must pass the worse of the two.
Common mistakes
- Designing from one resistivity reading, or from monsoon readings.
- Judging the design by electrode resistance alone.
- Leaving out the generator-supply case.
- Skipping the crushed-rock layer that the calculation relied on.
- No periodic re-testing.
What to send us
Send the site layout, soil test results if available, the single-line diagram, the transformer and generator data, and the protection settings. WhatsApp 98852 01608 or use the enquiry form.
Evidence note. Formulas are the widely used forms for substation earthing; detailed designs need the full method of the applicable standard and measured site data. Examples are illustrative.
Questions engineers ask
How is an earth grid designed?
From measured soil resistivity and the earth-fault current that enters the grid, a mesh layout is chosen and its resistance, ground potential rise, touch and step voltages are calculated. The calculated touch and step voltages must stay below the tolerable limits, adding mesh, rods or a crushed-rock surface layer where they do not.
What is earth potential rise?
The voltage an earth grid rises to, relative to remote earth, while fault current flows into it: the current into the grid multiplied by the grid resistance. In the example on this page, about 2000 A into a 1.42 ohm grid gives about 2830 V.
What has to be settled before an earthing study can start?
Two things, and neither is a calculation. Where the system neutral is earthed in every operating mode, which fixes the fault path the whole study is about; and a measured soil resistivity, which fixes what any electrode can achieve. A study that assumes either of them produces figures that look finished and are rebuilt after the first site test.
Why do two studies of the same installation disagree?
Usually because they assumed different neutral arrangements. If one takes the system as earthed at the transformer in all modes and the other traces an arrangement where the generator neutral earths the system while the mains is off, every figure after that point diverges. The arithmetic is not in dispute; they are studying two different electrical systems, and settling the transfer scheme in writing first prevents it.
What earth resistance is required?
There is no single figure. The required value follows from the earth fault current, the clearing time and the touch and step voltages that are acceptable, together with the needs of protection and lightning. A low resistance alone does not prove safety; the study checks the voltages that people could actually touch.
Why a four-pole switch?
Where each source has its own neutral to earth bond, such as a generator earthed at the set, switching the neutral keeps one bond per source in every position. That makes earth fault current return on the intended path, so earth fault protection measures it correctly and stray currents do not flow in metalwork.
Does the generator need its own earth?
A generator needs a reliable connection to the site earthing system and, depending on the earthing arrangement, a neutral to earth bond at the set. A separate isolated earth is not wanted; the generator earth is bonded into the main earthing network so that all metalwork rises together during a fault or a surge.
How often should earths be tested?
Commonly at least once a year, preferably in the dry season when soil resistance is highest, and after any work that may have disturbed electrodes or bonds. Tests cover electrode resistance, continuity of bonding conductors and the condition of joints, with results compared against the design and earlier records.
This guide gives general principles. Earthing design must follow the applicable standards and be done by qualified engineers.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.