ATS Service

What automatic transfer switch service involves, how to test the whole mains-failure sequence safely, the faults behind failed transfer and settings to verify.

In short. An automatic transfer switch is only proven by running the complete sequence: mains failure detected, generator started, generator source accepted, load transferred, mains restored, retransfer after the return delay, and generator cooled down and returned to standby. ATS service inspects the switching mechanism, interlocks, contacts and control supply, verifies source sensing against a meter, checks the start signal to the generator and the timers, and records a witnessed functional test agreed with the site.

Why the transfer path deserves its own service

A standby generator that starts perfectly but never receives the load has failed, as far as the facility is concerned. The transfer switch sits between the DISCOM supply and the generator on one side and the essential load on the other, carrying full load current daily on the mains side while its generator side may not operate for months. Mechanisms stiffen, relays stick, sensing transformers drift and the start-signal wire corrodes, all without visible symptoms until the night the supply fails. The guide to automatic transfer switches explains the types; service is about keeping whichever type you have ready.

What an ATS service visit covers

A proper visit splits into inspection with the panel isolated, electrical checks and a live functional test. The isolated inspection covers the switching device, whether a motorised changeover switch, a pair of contactors with mechanical and electrical interlock, or a pair of air circuit breakers with a mechanical interlock. We check contact wear, termination tightness with a torque wrench, signs of heating, free movement of the interlock and mechanism, and the control fuses, relays and controller. Thermal imaging under load before isolation finds loose terminations a visual check misses.

The electrical checks cover insulation resistance of the main circuit, operation of the motor or coils on manual command, and proof that the mechanical interlock prevents both sources closing together under every combination of manual and electrical command. On contactor panels the electrical interlock is checked separately, since a welded auxiliary contact can defeat it. The ATS and switchgear parts page lists what is normally replaced at these visits.

Source sensing is where most faults hide

The controller decides that the mains has failed, or that the generator is acceptable, from voltage and frequency measurements through sensing circuits. Service verifies these against a calibrated meter on all three phases. The table lists the settings that need checking against the site’s requirements rather than being left at default. The ranges are indicative; the right values depend on the load, the quality of the local supply and the engine manufacturer’s recommendations.

SettingWhat it doesTypical range, 415 V 50 Hz siteWhat goes wrong if set incorrectly
Mains under-voltage dropout and pickupDefines when the mains is failed and when restoredDropout 80 to 85%, pickup 90 to 95%, with hysteresisToo tight causes nuisance transfers on DISCOM dips; too loose leaves the load on a brown-out
Phase loss and phase sequenceDetects single phasing and wrong rotationEnabled on all three phasesSingle-phase sensing misses loss of one phase and three-phase motors burn
Mains failure delayRides through short dips before starting the generator2 to 10 secondsZero delay starts the set on every flicker; a long delay extends the outage
Generator warm-up or transfer delayLets voltage and frequency stabilise before transfer5 to 15 secondsTransfer onto an unstable source trips UPS and motor protection
Mains return delayConfirms the mains is stable before retransfer1 to 5 minutesA short delay causes repeated transfers on a flickering supply

The start signal and the generator interface

The link between the ATS and the generator is a pair of wires carrying a volt-free contact or a DC signal, and it fails more often than either device. Service confirms that the contact closes on mains failure, that the generator controller receives it and starts, and that the generator’s ready-to-load signal, where used, returns to the ATS. Where the ATS and generator come from different suppliers, we confirm which device is the master.

Either the ATS commands the start and the generator controller obeys, or the generator’s AMF controller senses the mains itself and the ATS is a slave switching device. Two devices both sensing the mains with different settings produce transfers nobody can explain. The ATS and AMF control logic guide describes the arrangements.

Running the functional test

A visual inspection cannot prove automatic transfer. The functional test is agreed in writing with the site because it interrupts the essential load, so the test window, the loads affected and the abort criteria are recorded first. The sequence we witness and time is as follows.

The record from this test, kept with the panel, is the evidence that the transfer system works and the baseline for the next test.

Faults we see repeatedly

Transfer never happens though the generator runs

Usually the generator-available signal, a failed transfer relay, a generator-side mechanism seized through disuse, or a generator voltage marginally outside the acceptance window. Compare the controller’s acceptance readings with a meter at the generator terminals.

Retransfer fails or cycles

Usually a mains return delay too short for a flickering supply, a drifted mains sensing transformer, or loss of one phase that single-phase sensing cannot detect.

Both sources closed, or a burnt panel

The mechanical interlock has been defeated, often during a previous repair where someone bypassed it to get the site running. This is the most dangerous condition a transfer switch can be in, because it back-feeds the generator into the DISCOM network and endangers line workers. Any bypassed interlock is restored before the panel is left.

Related photographs and videos

ATS interlocking and transfer safety.

A transfer timing record (illustrative)

The functional test is only useful if each stage is timed and compared with the settings. A record for an AMF-controlled 250 kVA set might read like this.

StageSettingMeasured
Mains failure confirmedStart delay to ignore short dipsAs set
Crank to runningWithin the cranking cycles setFirst crank
Voltage and frequency acceptedWithin the acceptance bandAccepted
Transfer to generatorAfter the warm-up delayLoad on generator; total break recorded
Mains restored and stableRetransfer delay so the mains proves itselfAs set
Retransfer to mainsAfter the delayLoad back on mains
Cool-down and stopCool-down periodStopped, controller back in auto

A stage that takes longer than its setting, or that needed help to complete, is a finding, even if the load was eventually transferred.

Mechanism and contact checks

ItemWhat is checkedWhy it matters
Main contactsErosion, pitting, alignmentWorn contacts overheat on the mains side, which carries load every day
TerminationsTightness, discolouration, temperature under loadLoose joints are the commonest cause of heat damage in transfer panels
Operating mechanismFree movement, lubrication as the maker specifies, end positionsA sticking mechanism transfers slowly or not at all
InterlocksElectrical and mechanical interlocks block a prohibited operationProves the permitted sequence for the installed transfer type: on open-transition equipment the generator and mains are never connected together, and on closed-transition equipment they are paralleled only through the approved synchronising and protection scheme
Control supplySupply to the transfer controls on both sourcesA transfer switch with a dead control supply cannot move

Thermal imaging under load

The mains side of a transfer switch carries load every day, so heat builds where joints loosen or contacts wear. A thermal image of the terminals and contacts taken while the panel is carrying normal load, compared phase with phase and with the previous visit, finds a failing joint long before it fails. Any hot spot is corrected at a planned shutdown rather than discovered as a burnt terminal during an outage.

A safe monthly transfer test

  1. Agree a time with the people who depend on the supply.
  2. Confirm the set is in automatic with no active alarm and adequate fuel.
  3. Simulate a mains failure at the sensing point, not by pressing start on the controller.
  4. Record each stage of the sequence and the readings on generator supply.
  5. Restore the mains, record the retransfer and cool-down, and confirm the controller is back in automatic.

Where the site cannot accept a monthly break, the transfer is tested at the next planned shutdown and the controller start is exercised on its own in the meantime, with the gap noted in the log so the full sequence is not forgotten.

Common mistakes

What to send us

Send photographs of the ATS panel with the door open, the nameplates of the switching device and the controller, the generator nameplate, and a description of what happens during a mains failure now, including whether the generator starts, whether the load transfers and whether retransfer works. Include a single-line diagram or the previous test record if you have one. Submit through the service and AMC enquiry form; transfer switch service can be included in a generator AMC.

Questions engineers ask

What should be timed during an ATS test?

Each stage of the sequence against its setting: the start delay after the mains failure, cranking to running, acceptance of voltage and frequency, the transfer to generator and the length of the break, the retransfer delay after the mains returns, the retransfer itself and the cool-down before stopping. A stage that runs longer than its setting is a finding even if the load was transferred.

Why do transfer switch terminals overheat?

Because the mains side carries the load every day, and a joint that has loosened or a contact that has worn develops resistance and heats. Thermal imaging of the terminals and contacts under normal load, compared phase with phase and with the previous visit, finds the hot spot early, and it is corrected at a planned shutdown before it burns during an outage.

How often should an ATS be tested?

A full mains-failure simulation with load transfer monthly is good practice for critical sites and quarterly for most commercial sites, with an inspection and torque check annually. Many sites run the generator weekly on no load, which exercises the engine but not the transfer switch, so make sure some tests include an actual transfer.

Can the ATS be tested without interrupting the load?

The logic can be tested from the controller’s test mode without transferring, and a bypass-isolation ATS allows the switch to be maintained while the load stays on the mains. An open-transition transfer test interrupts the load briefly, which is why it is scheduled and agreed with the site in advance. An approved closed-transition switch can transfer between two healthy, synchronised sources without a break during a planned test or retransfer, but a genuine loss of mains still causes an interruption until the generator is available.

How long is the supply interrupted during a transfer?

An open-transition transfer breaks one source before making the other, typically for a few hundred milliseconds to a second. Loads that cannot tolerate this need a UPS. Closed-transition transfer avoids the break but needs synchronised sources and is a different class of equipment, with its own protection and, for the utility side, the approval of the DISCOM.

Why does the generator start but the load stays on the mains?

The mains sensing saw a dip the controller treated as a failure, but the mains recovered before the transfer delay expired, or the generator voltage or frequency did not enter the acceptance window. Check the event log, compare the acceptance settings with the generator output, and review the mains failure delay.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.