In short. A short-circuit study works out the fault current at each important bus, in every permitted operating mode, so that switchgear and cables can be checked against it. Fault current depends on the sources and the impedance between them and the fault. A study therefore needs the utility fault level, the transformer impedance, generator and motor data and the cables. It must also cover the weakest mode, so that protection is known to operate.
Who this page is for: For consultants and electrical engineers checking switchgear ratings and protection after adding transformers, generators or large motors.
Key facts
- Fault current is set by source strength and impedance, not by load.
- Transformer impedance usually dominates low-voltage fault level.
- Generators give much lower fault current than mains, and it falls with time.
- Running motors add to the first cycles of a fault.
- Maximum fault checks equipment; minimum fault checks protection.
- Adding a source or a larger transformer means repeating the study.
Worked example: main board of a 1000 kVA, 415 V site (illustrative)
| Step | Value |
|---|---|
| Transformer full-load current = 1,000,000 ÷ (1.732 × 415) | about 1391 A |
| Transformer impedance 6% = 0.06 per unit; utility 250 MVA = 0.004 per unit on a 1 MVA base | 0.064 per unit total |
| Mains fault at main board = 1391 ÷ 0.064 | about 21.7 kA (23.2 kA if the utility is ignored) |
| Running motors (from motor data) | about 2 kA extra in the first cycles |
| 500 kVA generator alone: 696 A ÷ 0.12 (subtransient reactance) | about 5.8 kA initially, then falling |
The 36 kA board passes on mains. The generator case is the one to check for protection: 5.8 kA at the board, less at the end of each feeder. See maximum and minimum fault studies and generator fault contribution.
Do not reuse an old fault study after changing a transformer, adding a generator or paralleling sources. Higher fault current can leave switchgear underrated, and lower fault current can stop breakers tripping quickly.
Inputs
- Utility fault level at the supply point, for maximum and minimum conditions.
- Transformer rating, impedance and vector group. See transformer impedance.
- Generator reactances and decrement data.
- Large motors and cable sizes and lengths.
- Breaker states in each operating mode.
Fault level sheet
Every bus on one installation, in every mode it can run in: a 2000 kVA transformer at 6% impedance on a 350 MVA utility, with two 1250 kVA generators. It is a stiffer and larger site than the 1000 kVA case worked through in the example above, which is what makes the second column earn its place — on this board the mode changes the answer by a factor of nine.
| Bus | Mode | Fault kA | Equipment rating kA | Pass? |
|---|---|---|---|---|
| Main board, 3200 A | Mains, no motors | 42.3 | 50 breaking | Yes |
| Main board, 3200 A | Mains, with running motors | 45.3 | 50 breaking | Yes, with 4.7 kA of margin. See the making-capacity check |
| Main board, 3200 A | Both generators | 29.0 initially, decaying | 50 breaking | Yes |
| Main board, 3200 A | One generator | 14.5 initially, about 5.2 sustained | 50 breaking | Yes for equipment. This is the case to check for protection, not for rating |
| Sub-board 1, 1250 A | Mains, with motors | 31 | 36 breaking | Yes |
| Sub-board 1, 1250 A | Both generators | 20 | 36 breaking | Yes |
| Sub-board 2, 630 A | Mains, with motors | 14 | 25 breaking | Yes |
| Sub-board 2, 630 A | Both generators | 8 | 25 breaking | Yes |
| Sub-board 2, 630 A | One generator, sustained | 2.3 | 25 breaking | Yes for equipment, and the lowest figure on the sheet. Arc-flash and coordination both turn on this row |
The main board figure is worth following all the way through, because each step changes it. The transformer’s full load current is 2,000,000 divided by 1.732 times 415, which is 2782 A. Its 6% impedance is 0.06 per unit on its own 2 MVA base, and a 350 MVA utility adds 2 divided by 350, so 0.0057 per unit on the same base — giving 0.0657 in total.
Dividing 2782 by 0.0657 gives 42.3 kA. Leave the utility out and the answer is 2782 divided by 0.06, which is 46.4 kA: ignoring the supply impedance makes the fault level look about 4 kA worse than it is, which is safe for an equipment check and wrong for a protection study.
Running motors then add about 3 kA to the first cycles, taking the initial figure to 45.3 kA against a 50 kA board. That is a pass with 4.7 kA of margin, and it is also the entire reason this site needed the separate equipment check on the next page: a board that passes on breaking current can still fail on making capacity, because the peak that arrives in the first half cycle is more than twice the r.m.s. figure. The fault level sheet is not the place that question gets answered, but it is the place it gets raised.
The generator rows are the opposite problem. Two 1250 kVA sets have a full load current of 1739 A each, and at a subtransient reactance of 0.12 per unit each one contributes 1739 divided by 0.12, about 14.5 kA — so 29 kA for the pair, falling from the first cycles onwards. On one set the board sees 14.5 kA initially and settles to around 5.2 kA, roughly three times full load current.
No equipment on this site is troubled by any of those numbers. What they do instead is decide whether the protection will operate at all, and how long an arc would last, which is why the last row carries a 2.3 kA figure and a note rather than a tick.
One discipline makes the sheet reusable: every row names a mode, and the modes are the ones the site can actually be in. There is no row for one generator paralleled with the mains, because this installation transfers on an open transition and that combination cannot occur. Adding a row for a configuration the switchgear forbids inflates the maximum for no reason; leaving out a configuration the switchgear allows is how a board ends up under-rated. The single line diagram, not the imagination, settles which rows exist.
Fault types and their relative size
| Fault | Relative to the three-phase fault | Main use in the study |
|---|---|---|
| Three-phase | Reference | Usually the highest current; equipment ratings |
| Phase to phase | About 0.87 times, from √3 ÷ 2 | Protection sensitivity where earth faults are limited |
| Phase to earth | Close to or slightly above it at a solidly earthed LV transformer; much lower with earthing impedance or long cables | Earth fault protection and touch voltage |
| Two phases to earth | Between the two | Checks on some earthing arrangements |
Which current is checked against which rating
| Quantity | Meaning | Checked against |
|---|---|---|
| Initial symmetrical current | The rms fault current in the first cycles | Breaker breaking capacity on LV breakers |
| Peak current | The highest instantaneous value, including DC offset | Making capacity and busbar peak withstand |
| Breaking current | The current when the contacts part | Breaking capacity on breakers with a time delay |
| Short-time current | The current flowing during a deliberate delay | Short-time withstand rating for the delay time |
| Steady-state current | The current after the transients have decayed | Protection operation, especially on generators |
Maximum fault calculations raise the source voltage slightly, commonly by a voltage factor of 1.05 or 1.10 at low voltage depending on the voltage tolerance, while minimum calculations lower it, commonly to 0.95. These factors, and the method, follow the applicable short-circuit standard. See IEC short-circuit calculation engineering.
How generator fault current changes with time
| Period | Reactance that governs it | Typical range, per unit | Fault current, multiple of rated |
|---|---|---|---|
| First cycles | Subtransient | About 0.10 to 0.20 | About 5 to 10 |
| Next few tenths of a second | Transient | About 0.15 to 0.35 | About 3 to 6 |
| After about a second | Synchronous, with excitation support | About 1.5 to 3.0 unsupported | About 3 with a permanent magnet or auxiliary excitation system; below rated without one |
Ranges vary with make and frame, so the study uses the alternator’s own data sheet and decrement curve. Without excitation support, a generator’s sustained fault current can fall below its rated current, and overcurrent protection may never operate. See generator short-circuit contribution.
Worked example: can the cable survive the fault? (illustrative)
A cable must carry the fault current until the protection clears it without overheating its insulation. The adiabatic check is I² × t ≤ k² × S², where k depends on the conductor and insulation and S is the cross-section in mm².
| Cable | Working | Result |
|---|---|---|
| 70 mm² copper, PVC insulated, k about 115 | 115² × 70² | About 64.8 million A²s |
| Fault current 20 kA | 64.8 million ÷ 20,000² | Must be cleared within about 0.16 s |
An instantaneous breaker clears in well under that time; a breaker with a 0.3 s short-time delay for selectivity does not, and the cable would be damaged before it trips. Selectivity settings and cable sizes must be checked together, which is why this check sits in the short-circuit study.
UPS, battery and solar inverters
Inverter-based sources do not behave like rotating machines in a fault. Their electronics limit the current, often to about 1.5 to 2 times rated, for a short time set by the maker, and some disconnect. A UPS on inverter supply may therefore be unable to clear a fault on a downstream circuit by tripping its breaker, unless the circuit protection is chosen for that low current or the UPS transfers to bypass to clear it. The study models each inverter from the maker’s fault data and checks downstream protection in that mode. See inverter, UPS and BESS fault current behaviour.
When the study must be repeated
- A transformer replaced, added or put in parallel.
- A generator added, replaced or allowed to parallel with the grid or with another set.
- Large motors or inverter sources added.
- A new utility fault level notified.
- A bus coupler or interlock arrangement changed.
- Main cables rerouted or resized.
Each of these changes the fault current somewhere, and the study, the protection settings and the arc flash labels must follow it.
Common mistakes
- Studying the main board only.
- Ignoring generator mode.
- Assuming a typical transformer impedance.
- Adding sources that cannot be connected together.
What to send us
Send the single-line diagram, transformer and generator data and the utility fault level. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. Values are illustrative; project studies govern.
Questions engineers ask
How long can a cable carry a fault current before it is damaged?
The adiabatic check limits I squared t to k squared S squared. A 70 mm² copper PVC cable with k about 115 can withstand about 64.8 million A2s, so at 20 kA it must be cleared within about 0.16 s. A breaker with a 0.3 s short-time delay for selectivity would let it overheat, so cable sizes and settings are checked together.
Why can a generator fault current fall below its rated current?
After the first cycles the fault current is limited by the synchronous reactance, often 1.5 to 3 per unit, which alone would give less than rated current. With a permanent magnet or auxiliary excitation system the regulator can hold about three times rated current for a few seconds; without one, overcurrent protection may never operate.
Why do I need a minimum case?
Because protection must operate on the lowest fault current that can occur, such as on generator supply, with the utility at its weakest or with fewer sources connected. A breaker that trips instantly at the maximum fault level may trip slowly, or not at all, at the minimum, leaving a fault in place.
Should I include motors?
Yes for the maximum case. Running induction motors feed current into a nearby fault for the first few cycles, raising the initial and peak currents that breakers must make and break. Motors are usually grouped by board rather than modelled one by one, and they are left out of the minimum case.
What if equipment rating is exceeded?
The options are to replace or uprate the equipment, to reduce the fault current with higher impedance transformers, reactors or operating interlocks that prevent sources being paralleled, or to use current limiting devices tested in combination with the equipment. Leaving it in service unchanged is not an option.
How often should it be repeated?
Whenever the system changes in a way that alters fault current, such as a new transformer, generator, large motor, inverter source or a new utility fault level, and otherwise at a regular interval, commonly every few years, to capture changes that were made without a study.
This guide gives general principles. Studies must use verified data.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.