In short. A load list records every significant load with its rating, power factor, duty, starting method and priority. A load schedule then works out what runs together in each mode. Done properly, it separates connected load from real demand. It shows what the generator must carry and start, and which loads can be shed. Every other study builds on it.
Who this page is for: For consultants, plant engineers and owners preparing load data for transformer, generator, UPS and cable sizing.
Key facts
- Record kW, power factor, duty, starting method and priority for each load.
- Motor nameplate kW is shaft output; electrical input is higher.
- Duty and standby units do not both count in normal demand.
- Make a separate schedule for generator mode.
- Show the largest motor and its starting method separately.
- Include UPS losses and battery recharge after an outage.
What each line should hold
| Field | Why it matters |
|---|---|
| Tag and description | Traces the load through drawings, cables and protection |
| Rating, power factor, efficiency | Gives real current and kVA, not just kW |
| Duty: continuous, intermittent, standby | Decides whether it counts in demand |
| Starting method | Decides voltage dip on generator |
| Priority and shed status | Decides what the generator must carry |
Worked example: generator-mode schedule (illustrative)
| Load | Installed | Counted in generator mode |
|---|---|---|
| Water pumps, 3 × 30 kW input (2 duty, 1 standby) | 90 kW | 60 kW |
| Compressed-air plant, 55 kW input, star-delta | 55 kW | 55 kW |
| Lighting | 20 kW | 20 kW |
| UPS input: 42 kW load and losses + 6 kW recharge | 48 kW | 48 kW |
| Air conditioning, 80 kW at 0.8 diversity | 80 kW | 64 kW |
| Workshop (shed on generator) | 45 kW | 0 kW |
| Total | 338 kW | 247 kW |
Running demand is 247 kW, not 338 kW. The 55 kW motor start is checked separately. See maximum demand and motor starting on generators.
Do not size a generator from the sum of nameplate kW. Count only what runs together, add UPS recharge, and check the largest motor start on its own.
Load list sheet
The schedule for one installation — a 2000 kVA transformer with two 1250 kVA generators in N+1 and a 400 kVA UPS. The example above works a six-line schedule down from 338 kW to 247; this is a nine-line schedule on a site four times the size, and the gap it opens is wider for a reason the last column makes plain.
| Tag | kW | Power factor | Duty | Starting | Priority | Generator mode kW |
|---|---|---|---|---|---|---|
| M-01 Chilled water pumps, 3 × 45 kW input | 135 | 0.86 | 2 duty, 1 standby | Star-delta | Essential | 90 |
| M-02 Process compressed-air plant, 110 kW input | 110 | 0.88 | Continuous | Soft start | Essential | 110 |
| M-03 Cooling tower fans, 4 × 22 kW | 88 | 0.85 | All four together | Direct on line | Essential | 88 |
| M-04 Effluent transfer pump, 75 kW input | 75 | 0.87 | Intermittent | Soft start | Non-essential | 0 |
| AHU-01 Air handling, 6 × 30 kW | 180 | 0.85 | 0.9 diversity | Direct on line, one at a time | Essential | 162 |
| L-01 Process and plant lighting | 70 | 0.95 | Continuous | — | Essential | 70 |
| U-01 UPS input: 320 kW load and losses, plus 45 kW recharge | 365 | 0.99 | Continuous | — | Critical | 365 |
| H-01 Hot water and services | 120 | 1.00 | 0.7 diversity | — | Non-essential | 0 |
| W-01 Workshop and stores | 60 | 0.90 | Shed on generator | — | Non-essential | 0 |
| Installed total | 1203 | — | Mains mode with diversity: 1104 kW | — | — | 885 |
Three totals, and they are not interchangeable. 1203 kW is what is installed and is the figure nobody should size anything from. 1104 kW is the mains-mode demand once the standby pump is left out and diversity is applied to the air handling and the hot water. 885 kW is the generator-mode demand, which drops a further 219 kW because the effluent pump, the hot water and the workshop are shed. At the measured power factors that 885 kW is 949 kVA, so one 1250 kVA set carries it at 76% — which is why this site is N+1 on two sets rather than N on three.
The UPS line is the one that most schedules get wrong, and here it is the largest load on the sheet. 365 kW is not the UPS rating and not the critical load either: it is 320 kW of load plus conversion losses, and 45 kW of battery recharge.
That recharge figure exists only after an outage — which is precisely when the generator is running — so leaving it out would understate generator-mode demand by 45 kW at the exact moment it matters. It also carries a power factor of 0.99, which is what pulls the whole site’s power factor up to 0.93 and, as the reactive power study found, removes the case for any correction at all.
The fifth column is on this sheet rather than in the motor study because it changes the answer to a different question. M-02 is the largest motor at 110 kW, and its starting method is the single entry that decides whether one generator can run this plant: direct on line it draws about 798 kVA and dips the set 11%, past the plant’s 10% limit, and soft started it draws about 399 kVA for a 6% dip. Writing “soft start” in a load list is therefore not a note about the motor; it is a constraint on the generator that has already been accepted.
One entry is deliberately zero rather than absent. The 75 kW effluent pump is shed on generator, so its generator-mode figure is 0 — but it stays on the sheet, with its rating and its starting method, because the day somebody decides the effluent pump is essential after all, the 885 kW becomes 960 and the 76% becomes 82%, and the person making that decision needs to see the number they are moving. A load removed from the schedule is a load nobody will reconsider.
From motor shaft kW to electrical demand
A motor nameplate states mechanical output at the shaft. The supply sees the input, which is higher by the motor’s losses, and the kVA, which is higher again by the power factor. Efficiencies and power factors below are typical of modern high-efficiency motors at full load; the motor data sheet replaces them.
| Shaft rating | Efficiency, about | Input kW | Power factor, about | Input kVA | Current at 415 V |
|---|---|---|---|---|---|
| 7.5 kW | 90% | 8.3 | 0.82 | 10.2 | About 14 A |
| 30 kW | 93% | 32.3 | 0.85 | 38.0 | About 53 A |
| 55 kW | 93% | 59.1 | 0.86 | 68.8 | About 96 A |
| 110 kW | 95% | 115.8 | 0.87 | 133.1 | About 185 A |
Motors rarely run at full shaft load. A pump selected with margin may run at 70 to 80% of its rating, and its input is lower in proportion, but its power factor is also lower at part load. Where the duty point is known, the load list uses it; where it is not, it uses the rating and says so.
Which data to trust
| Source | Confidence | Use |
|---|---|---|
| Measured load over a full operating cycle | Highest for existing loads | Existing sites and expansions |
| Equipment data sheet for the actual model | High | New equipment once selected |
| Nameplate | Good for rating, poor for actual duty | Survey of existing plant |
| Typical values by equipment type | Low | Early design only, marked as assumed |
Each line in the list records which source its figures came from. When a figure is upgraded from an assumption to a data sheet or a measurement, the list is revised and the studies that depend on it are checked.
Operating scenarios and the simultaneity matrix
The same list gives different demands in different operating states. A simple matrix marks which loads run in each one.
| Load group | Normal day | Peak production | Generator supply | Night and holidays |
|---|---|---|---|---|
| Process motors | Yes | Yes, all | Essential lines only | No |
| Air conditioning | Yes | Yes | Critical rooms only | Partial |
| UPS and IT | Yes | Yes | Yes, plus recharge | Yes |
| Lighting | Yes | Yes | Essential circuits | Security lighting |
| Workshop and non-essential | Yes | Yes | Shed | No |
Each column becomes a schedule with its own total. The peak column sizes the transformer and incomer, the generator column sizes the set, and the night column is the light-load case for voltage rise and capacitor control.
Load categories and how each is treated
| Category | Examples | Treatment on generator supply |
|---|---|---|
| Life safety | Emergency lighting, fire pumps, smoke extraction, evacuation lifts | Restored first, never shed |
| Critical | IT, controls, process safety systems | On UPS; generator carries UPS input and recharge |
| Essential | Key production lines, cold storage, water supply | Restored in stages after transfer |
| Non-essential | Workshops, comfort heating, general power | Shed, or restored only if capacity allows |
The category is set with the owner, not by the engineer alone, because it is a business decision about what must keep running. See critical load classification and load prioritisation.
Single-phase loads and phase balance
Lighting, small power and IT are often single-phase. The load list assigns each to a phase and totals the three phases separately. A board whose phases differ widely loads one phase of the transformer or generator more than the others, raises neutral current and creates voltage unbalance that heats three-phase motors. Rebalancing on paper, before installation, costs nothing; rebalancing afterwards means moving circuits. See voltage unbalance and negative sequence studies.
Keeping the list alive
A load list is a controlled document like the single-line diagram. It carries a revision number, the date, who changed it and why. Every new load, every removal and every change of duty or category is entered before the work is done, and the change is checked against the transformer, generator and UPS margins. Sites that keep the list current can answer “can we add this machine?” in an afternoon; sites that do not must survey the whole installation again.
Writing the UPS line correctly
A UPS line in the load list is not its kVA rating. It is the output load divided by the UPS efficiency, plus battery recharge after an outage. A 200 kW output load on a UPS at about 95% efficiency draws about 211 kW, and recharge adds more until the batteries are full. Enter the output load, the efficiency and the recharge as separate figures, so each can be checked and updated.
Common mistakes
- Counting standby units as running.
- One power factor for every load.
- Forgetting UPS recharge.
- Double counting a transformer and its downstream loads.
What to send us
Send your equipment list or panel schedules and tell us which loads must run on generator. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. Values are illustrative.
Questions engineers ask
How is a motor shaft rating turned into electrical demand?
Divide the shaft kW by the efficiency for input kW, then by the power factor for kVA. A 55 kW motor at about 93% efficiency and 0.86 power factor draws about 59.1 kW and 68.8 kVA, about 96 A at 415 V. Using shaft kW as electrical demand understates the load, and using kW alone understates the kVA.
Why does a load list need several operating scenarios?
Because the same loads run in different combinations in normal running, peak production, generator supply and at night. A simultaneity matrix marks what runs in each state. The peak case sizes the transformer, the generator case sizes the set with UPS recharge included, and the night case is the light load check for voltage rise and capacitor control.
What is the difference between a load list and a load schedule?
A load list records every load with its data: rating, power factor, efficiency, duty, starting method and category. A load schedule uses that list to work out what runs together in a given operating state and totals the demand for it. One list supports several schedules, such as peak, generator supply and light load.
How much growth allowance should I include?
Base it on known plans rather than a flat percentage. Add committed future loads explicitly as lines, reserve space and ratings for probable growth, and state any general allowance separately, with its reason, so that it is not hidden inside the load figures and counted twice when the real loads arrive.
Can I use measured data?
Yes, and for existing loads it is usually the best data, provided the measurement covers a full operating cycle including peak production, and records kW, kVA and power factor by board. Mark which lines are measured and which are from nameplates or data sheets, so the confidence in each figure is visible.
Why record starting method?
Because the starting method decides the current a motor draws when it starts, and therefore the voltage dip on the transformer or generator. A large motor started direct on line can decide the generator size, while the same motor on a soft starter or drive may not. The starting method is a constraint on the source.
This guide gives general principles. Values must come from your equipment.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.