Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

AMF Control Logic

Understand the automatic mains failure sequence step by step, the timers and proving limits that matter, the abnormal cases, and how to commission it.

In short. Automatic mains failure logic watches the utility on all three phases, waits a confirmation delay so that momentary dips do not start the engine, cranks the generator, proves voltage and frequency, transfers the load, and reverses the process once the utility has been stable for a longer return delay before cooling and stopping the engine. Each step depends on a confirmed state rather than a command sent, and each abnormal branch needs a tested response.

The normal sequence step by step

An AMF controller is a state machine, and it is the first layer described in the generator controls centre. It moves from one state to the next only when a condition is confirmed, and every transition has a timer. The table below shows the normal sequence for a single diesel generator with a contactor or breaker changeover on a 415 V supply, with timer ranges typical in Indian installations. Actual values are set for the site.

StepCondition confirmedTypical timerPurpose
Mains failure detectionVoltage or frequency outside limits on any phase2 to 10 s confirmationIgnore momentary dips and DISCOM auto-reclose attempts
StartCrank command issued, engine fires, crank disconnect on speed or oil pressureUp to 3 attempts of 5 to 10 s, rest 5 to 10 sProtect starter motor, detect failed start
Warm-up and provingVoltage and frequency within window, usually 0.9 to 1.1 pu and 47.5 to 52 Hz3 to 10 sDo not connect an unstable source to the load
Transfer to generatorMains contactor open confirmed, then generator contactor closed confirmedInterlock delay 0.5 to 2 sBreak before make, avoid paralleling two sources
Mains return detectionAll phases healthy and stable30 s to several minutesAvoid repeated transfers on a flickering supply
RetransferGenerator contactor open confirmed, then mains contactor closedInterlock delay 0.5 to 2 sReturn load to utility
Cooldown and stopEngine runs unloaded2 to 5 minLet turbocharger and coolant temperatures settle before shutdown

Why the delays exist

The confirmation delay on failure is not hesitancy. Telangana feeders see frequent short interruptions as the DISCOM’s auto-reclosers operate, and a controller that cranked for every one would wear the starter, exhaust the battery and transfer the load needlessly. Two to five seconds covers most reclose cycles. The return delay is longer again, because a returning supply is often unstable for a minute or more.

The voltage and frequency proving window matters more than most installers appreciate. If the generator contactor is allowed to close while the engine is still recovering from cold cranking, the load sees low frequency, the AVR under-excites to protect the alternator, and motors may stall. The deeper discussion of how a set responds to being loaded is in generator transient response.

Signals versus confirmed states

The commonest design weakness in AMF schemes is treating a command as proof of an outcome. The controller energises the generator contactor coil and assumes the load has transferred. If the contactor is mechanically jammed or the coil is burnt, the load sits dead while the controller displays a healthy picture. Good practice wires auxiliary contacts from both switching devices back to the controller, confirms each step before moving on, and raises a transfer-failed alarm if confirmation does not arrive. The same applies to engine running. Crank disconnect should use alternator frequency or a speed signal, with oil pressure as a backup, rather than a fixed time.

Abnormal conditions and the response to each

A functional description that only covers the happy path is incomplete. Each case below should have a written response and a commissioning test.

The changeover hardware

AMF logic drives a changeover, and the changeover’s type shapes the logic. Contactor-based changeovers below about 400 A are simple and fast but rely on electrical and mechanical interlocks to prevent both sources closing together. Breaker-based changeovers with motorised ACBs give fault withstand and proper isolation but have closing times of a few hundred milliseconds that the interlock delays must respect. Dedicated transfer switches, described under automatic transfer switches, bring their own controller and need only a start signal and a running feedback from the set. The panel options themselves are described under AMF panels.

Mains sensing done properly

Sense all three phases, and sense them at the point that represents the supply the load depends on, normally the incoming terminals of the mains breaker. Set under-voltage pickup around 80 to 85% and over-voltage around 110 to 115% of nominal, with phase-loss and phase-sequence detection enabled. In our experience single-phase sensing, inherited from an old relay panel, is the most frequent reason a factory’s motors run single-phased for an hour while the generator sits idle.

Commissioning the sequence

An AMF installation is commissioned by causing a mains failure, not by pressing the test button. With the site prepared and the load either disconnected or willing, open the incoming breaker and record the time of each event from the controller log, confirm the transfer and retransfer, and check voltage on each phase at the load during the generator period. Then repeat with a simulated failed start by isolating the fuel solenoid, and again with the controller deliberately left in manual to prove the alarm. Save the controller configuration file, note the timer settings in the handover record. The service side of this work is under ATS service.

Related photographs and videos

AMF control panel
AMF control panel.
AMF panel front
AMF panel front.
AMF automatic switching overview.

Where the seconds actually go

The sequence above describes what happens. This is what it costs in time, stage by stage, so that a site can tell whether its own changeover is slow or simply honest. Every figure is a range, because each depends on the equipment and on settings that are deliberately adjustable.

StageTypicalWhat decides itWorth shortening?
Mains failure confirmed0.5 to 3 sThe start delay, set to ride through brief dips and reclosures rather than start for every flickerRarely. Shortening it buys seconds and costs a start every time the utility blinks
Crank and fire2 to 8 sBattery condition, starter, ambient, whether the engine is pre-heatedYes, and it is the stage that degrades silently as the battery ages
Run up to stable voltage and frequency5 to 12 sEngine and alternator; the controller waits for both to be inside a window before it will transferOnly by tuning, not by narrowing the window, which transfers onto an unsettled supply
Transfer0.1 to 1 sThe changeover mechanism, plus any deliberate dead time between opening one source and closing the otherNo. The dead time is there to keep two sources apart
Total, mains failure to load restored8 to 24 sThe sum of the four above, as configured on that siteThe figure to measure and record, not to assume
On return: mains proved stable1 to 10 minA deliberately long delay, so the site does not transfer back onto a supply that is about to fail againNo. This is the one delay that should be generous
Cool-down and stop3 to 5 minUnloaded running to let turbocharger and engine temperatures settleNo. Stopping a hot turbocharged engine immediately is how bearings are lost

The third row is where the quoted ten-second changeover usually goes wrong in practice, and the mistake is to fix it by widening the acceptance window so the controller transfers sooner. That hands the load a supply that has not settled, and the equipment most likely to object is the equipment the generator was installed for. If the run-up is slow, the answer is in the governor and regulator tuning, or in the engine, and the stage to attack first is the second row: a tired battery adds seconds to every start and gives no other warning that it is failing.

Read the whole column and a useful distinction appears. The first four rows exist to restore supply and are worth measuring and improving; the last two exist to protect something and are worth leaving alone. Sites under pressure to shorten the changeover almost always propose cutting the return delay or the cool-down, because those are the longest numbers on the sheet — and they are the two that cost nothing to the outage and protect the plant from the utility and from itself.

One measurement note. Time these stages with a recording instrument or the controller’s own event log, not with a stopwatch and a pair of eyes, and record them at commissioning so that the figures exist as a baseline. A changeover that has quietly grown from nine seconds to fifteen over four years is a battery and a starter telling the site something, and it is only visible against the original record.

Common mistakes

What to send us

Send a photograph of the controller and the changeover panel with the door open, the generator nameplate, and a description of the fault or the behaviour you want, for example the delay before start, the behaviour during short outages or the retransfer timing. If a UPS is in the circuit, note its autonomy. For a new scheme, a modernisation of an old relay panel or a scheme that has stopped behaving, use the application engineering enquiry.

Questions engineers ask

Why is the delay on returning to mains so much longer than the delay on starting?

Because the two delays protect different things. The start delay rides through brief dips and reclosures, so a few seconds is enough. The return delay has to establish that the utility is genuinely back and not about to fail again, which takes minutes, and transferring back early means a second outage and a second transfer for the load. It is the one delay on the sequence that should be generous.

Our changeover takes longer than it used to. Where has the time gone?

Almost always cranking. A battery losing capacity adds seconds to every start and gives no other warning, because it still reads correctly at rest. Time the stages separately rather than the whole sequence: mains failure confirmed, crank and fire, run up to stable, transfer. If the run-up stage is the slow one it is governor and regulator tuning, and widening the acceptance window to transfer sooner just hands the load an unsettled supply.

How long should the generator take to pick up the load after a power cut?

For a healthy set with a typical configuration, about 10 to 20 seconds from the start of the outage. That is the sum of the mains failure confirmation delay, cranking, the voltage and frequency proving period and the transfer interlock. Loads that cannot accept that gap need a UPS, since no diesel set transfers instantly.

Why does my generator start but the load does not transfer?

Usually the controller has not received confirmation that the generator output is within its voltage and frequency window, or the generator contactor has failed to close and its feedback is missing. Check the proving limits, the alternator sensing wiring, the contactor coil and the auxiliary contacts before suspecting the controller itself.

Should the AMF transfer the neutral?

It depends on the earthing arrangement. Where the generator neutral is separately earthed at the set, a four-pole changeover avoids two parallel neutral-earth paths. Where the generator neutral is bonded only at the main earth bar, a three-pole changeover is common. The choice must follow the earthing design and the protection scheme, not habit.

Can one AMF controller handle two generators?

Not in the single-set sense. Two sets serving one load need either a generator-to-generator transfer scheme, where one is duty and one is standby, or a synchronising and load-sharing scheme where both can run together. The choice depends on whether one set can carry the whole load. Either scheme is tested by failing the running set on load and confirming the other takes over within the design time.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.

CallWhatsAppEnquire