In short. Commissioning proves that switchgear is installed correctly, safe to energise and works as designed. It runs in stages: inspection, mechanical checks, de-energised electrical tests, protection and control tests, energisation and on-load checks. Every result is recorded for handover. Skipping a stage usually shows up later as a trip, a hot joint or a protection that never operates.
Who this page is for: For commissioning engineers, contractors, consultants and owners receiving new or modified switchgear.
Key facts
- Inspect against drawings, nameplates, torque marks, clearances, labels and earthing.
- Check breaker racking, interlocks, spring charging and shutters mechanically.
- De-energised tests: insulation resistance, contact and joint resistance, CT polarity and ratio.
- Protection: secondary injection of each element and a trip-path test to the breaker.
- Energise in a controlled sequence, then check phase sequence, voltages and currents on load.
- Hand over test sheets, settings, drawings and as-built changes.
Stages
| Stage | Checks |
|---|---|
| Documentation and inspection | Drawings, certificates, nameplates, torque marks, clearances, labels, earthing, terminations |
| Mechanical | Racking, interlocks, spring charging, shutters, doors |
| Electrical, de-energised | Insulation resistance, contact resistance, CT polarity and ratio, wiring checks |
| Protection and control | Secondary injection, trip paths, interlocks, AMF and synchronising logic. See injection testing |
| Energisation | Controlled sequence, phase sequence, voltage checks |
| On load | Currents, differential and directional stability checks, thermography, metering accuracy, load bank where needed. See load bank testing |
Worked example: faults found at commissioning (illustrative)
| Test | Finding | Consequence avoided |
|---|---|---|
| CT polarity check | One phase CT reversed on the generator relay | False differential or reverse power trip on first load |
| Joint resistance | One busbar joint about 3 times the others | Hot joint and failure under load |
| Trip-path test | Relay operated but breaker did not trip: trip wire on wrong terminal | A fault that would never have been cleared |
| Interlock check | Mains and generator breakers could close together | Backfeed or out-of-phase closing |
Each of these passed visual inspection. Only the tests found them. See synchronising panels.
Do not energise switchgear before the trip paths and interlocks have been proven. A relay that operates on the bench but cannot trip its breaker gives no protection at all.
Handover package
- Signed test sheets for every stage.
- Final relay settings and firmware versions.
- As-built drawings.
- Outstanding items with owners and dates.
See commissioning services and the commissioning checklist.
Commissioning record
One incomer panel taken through all six stages, in the order they have to happen. Roles rather than names in the last column, because what matters at handover is that each stage was signed by someone competent for it and that the mechanical work was signed off before anything was energised.
| Panel | Stage | Result | Signed |
|---|---|---|---|
| Main board, incomer | Inspection against drawings: nameplates, torque marks, clearances, labels, earthing | Pass; two labels corrected and one earth bond re-made | Commissioning engineer, 11 March |
| Main board, incomer | Mechanical: racking, interlocks, shutters, spring charging | Pass; one interlock adjusted | Commissioning engineer, 11 March |
| Main board, incomer | Insulation resistance at 1000 V, phase to earth | 2.1, 1.9 and 2.4 GΩ — all far above the minimum | Commissioning engineer, 11 March |
| Main board, incomer | Contact and joint resistance | Main contacts 18, 21 and 19 µΩ; busbar joints 6 to 9 µΩ | Commissioning engineer, 12 March |
| Main board, incomer | CT ratio and polarity by primary injection | 1.24 A at the relay for 400 A primary on a 1600/5 CT; polarity correct | Protection engineer, 12 March |
| Main board, incomer | Protection: secondary injection of every element, then the trip path | All elements within tolerance; breaker opened at 2.08 s at twice pickup | Protection engineer, 14 March |
| Main board, incomer | Energise in sequence, then phase rotation and on-load check | Rotation confirmed; 412, 414 and 413 V; 980 A at 0.86 power factor | Protection engineer, 16 March |
The third column is the one that makes this a record rather than a tick sheet. “Pass” tells a future engineer nothing; 18, 21 and 19 µΩ across the main contacts gives him a baseline, and when the same test reads 34 µΩ in three years he knows the contacts have degraded rather than wondering whether they were always like that. Every number on a commissioning sheet is the first point of a trend, and a sheet of ticks throws that away.
Note also what the first two rows found: two wrong labels, an earth bond that had to be re-made and an interlock out of adjustment — all before a single test instrument came out of its case. That is the normal yield of a careful inspection stage, and it is the stage most often compressed when a programme is running late.
Worked example: what a contact resistance test reveals
A contact resistance test, sometimes called a ductor test, passes a large DC current, typically 100 A or more, through each closed breaker pole and measures the voltage drop to find the resistance in microohms. The heat in a contact is the square of the current times its resistance. A 2500 A breaker pole that measures 40 µΩ dissipates about 2000² × 0.00004 = 160 W at 2000 A of load.
The same pole at 120 µΩ, perhaps from a worn or poorly seated contact, dissipates about 480 W, three times as much, concentrated in a small area. Compare each pole with the others and with the maker’s limit; one pole well above its partners is a finding even if all three are within the published maximum.
Breaker timing and pole spread
A breaker timing test records the closing and opening times of each pole and the spread between the poles. Opening time matters to protection, because it is part of every clearing time and every grading margin. Closing time matters to synchronising, because the synchroniser relies on it. Pole spread, the difference between the first and last pole to make or break, should be a few milliseconds at most; a large spread on closing puts the system briefly on two phases and can upset sensitive protection. Record the values at commissioning; they become the baseline against which slowing mechanisms are detected years later.
Insulation resistance and dielectric tests
Insulation resistance is measured with a DC test voltage appropriate to the circuit, typically 1000 V for 415 V switchgear, between each phase and earth and between phases, with electronic devices disconnected. Installation standards set minimum values, commonly 1 MΩ for low-voltage circuits, but new switchgear and cables normally read hundreds or thousands of megohms, and the comparison between phases and with earlier readings tells more than the absolute figure.
The assembly’s own power-frequency dielectric test is part of the maker’s routine test under IEC 61439; on site, insulation resistance before first energisation is the usual check, with a dielectric test only where the specification calls for it and the equipment can be properly isolated.
A first energisation plan
- Confirm every test record is complete and every test link, shorting link and temporary earth has been removed.
- Confirm protection is in service with commissioning settings, and that the upstream protection will clear a fault on the new board.
- Clear the area, close doors and announce the energisation.
- Energise the incoming supply with all outgoing breakers open, and check voltages, phase rotation and metering.
- Close outgoing breakers one at a time, checking each circuit’s voltage and load.
- Run the board on load and carry out a thermographic survey once it has warmed up.
The first thermal survey
A thermographic survey under load, after the board has run for long enough to reach a steady temperature, finds loose connections that every other test missed, because they only show when current flows. The first survey after commissioning is also the baseline for every later one. Survey at a load of at least about 40% of rating where possible, record the load at the time, and compare similar components with each other: a joint several degrees warmer than its neighbours on the same circuit deserves attention even if its absolute temperature looks acceptable. See switchboard thermal and busbar engineering.
Functional tests: controls and interlocks
Every control function must be exercised as it will be used: local and remote closing and opening, indication on the board and on the monitoring system, spring charging, undervoltage releases, emergency trips and every interlock. Interlocks in particular are tested by attempting every forbidden operation, by every route, and confirming it is blocked. A board that has passed every electrical test but whose generator incomer can be closed onto a live utility bus has not been commissioned. See breaker interlocking and transfer logic.
Who witnesses what
Commissioning is most reliable when the person who builds or installs the equipment is not the only person who tests it. The owner or an independent engineer should witness the tests that matter most, protection injection, interlock checks and first energisation, and sign the records alongside the tester. Disagreements found during witnessed tests are cheap to resolve on the day and expensive to resolve after handover.
Common mistakes
- Relays tested without the trip path.
- CT polarity assumed from drawings.
- No joint resistance measurements.
- Handover without final settings.
What to send us
Send the single-line diagram, panel list and protection settings. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. Findings are illustrative.
What the handover package has to contain
Commissioning is not finished when the board energises. It is finished when the next engineer can work on it, and that depends entirely on what was written down. The package that makes a board maintainable:
- The test sheets, with readings rather than ticks. Insulation resistance, contact and joint resistance, breaker timing, CT ratio and polarity, and every protection element with its measured time against its expected time. These become the baseline for the whole life of the board.
- The settings register, with the rule beside each number. Not a screen dump of the relay — the reason the setting is what it is, so a future change can be judged rather than guessed at.
- Drawings marked up as built. Every change made during installation, on the drawing, not in somebody’s memory. A single-line diagram that does not match the board is worse than none, because it will be trusted.
- The trip and interlock schedule. What each protection trips, what is locked out and what is alarm-only. This is the document that answers “why did the whole bus go off” at two in the morning.
- Torque figures and the maker’s maintenance intervals, with the thermography baseline from the first on-load survey.
Two practical points on the sequence itself. Energise in a controlled order, section by section, with a check at each step rather than closing everything and looking for smoke — a phase rotation error found at the incomer is an inconvenience, and the same error found after the motors have run is a repair bill.
And make the on-load check a real one: voltages, currents and power factor on every phase, compared against what the design predicted. The sheet above reads 980 A at 0.86 power factor, and if the design said 700 A at 0.9 then something in the load schedule was wrong and this is the moment it is cheapest to discover.
Questions engineers ask
What does a contact resistance test show?
Whether each breaker pole closes onto good contacts. A DC current of 100 A or more is passed through the closed pole and the voltage drop gives the resistance in microohms. Heat rises with resistance: a pole at 40 microohms dissipates about 160 W at 2000 A, while one at 120 microohms dissipates about 480 W. Compare the three poles with each other and with the maker limit.
When should the first thermal survey be done?
After commissioning, once the board has run on load long enough to reach a steady temperature, ideally at 40% or more of its rating. It finds loose connections that other tests miss, because they only heat up when current flows, and it becomes the baseline for every later survey. Record the load on each circuit at the time.
Why test protection if it is factory tested?
Because the factory test proves the equipment as built, not as installed. Transport can loosen joints and mechanisms, site wiring can reverse a CT or swap a trip output, and the settings may never have been entered. Site tests prove the whole chain, from primary current through CTs, wiring, relay and trip coil to the breaker opening, with the actual settings.
What is primary injection?
Passing a test current through the primary conductors so that it flows through the CTs exactly as load or fault current would. It proves CT ratio, polarity and the secondary wiring together with the relay, which secondary injection, applied at the relay terminals, cannot. It is the normal test for new installations and for any change to CTs or their wiring.
Who should do commissioning?
Competent, authorised engineers working to a written procedure and test plan, with the protection settings, drawings and maker data in hand. Ideally they are independent of the people who wired the panel, so that wiring errors are not repeated in the tests. The owner or consultant should witness key tests and sign the records.
What documents should be handed over?
As-built drawings and single-line diagram, the protection study and setting sheets, test records with as-left values, relay configuration files, maker manuals and spares lists, interlock and operating procedures, and a punch list of open items with owners and dates. Together they let the next engineer maintain and test the plant without rediscovering it.
This guide gives general principles. Follow manufacturer procedures and site safety rules.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.