In short. Secondary injection feeds test currents and voltages into a relay’s terminals to prove its settings, timing and logic. Primary injection drives real current through the primary conductors to prove the whole chain: CT ratio and polarity, wiring, relay and trip circuit together. A relay can pass every secondary test and still fail in service because a CT is reversed or a trip wire is missing, which is why new installations, differential schemes and any CT work need primary injection as well.
Who this page is for: For commissioning and maintenance engineers, testing contractors and plant owners planning protection tests on generators, transformers and switchboards.
Key facts
- Secondary injection proves the relay; primary injection proves CT, wiring, relay and trip path together.
- Test timing at several multiples of pickup, for example 2, 5 and 10 times, against the setting curve.
- Standard inverse curve: t = TMS × 0.14 ÷ ((I ÷ Is)0.02 − 1).
- Expected CT secondary current = primary current × secondary rating ÷ primary rating.
- Never open-circuit a CT secondary while primary current flows.
- Record as-found and as-left settings on every test.
Secondary or primary?
| Aspect | Secondary injection | Primary injection |
|---|---|---|
| Where applied | Relay terminals | Through the primary conductor or busbar |
| Proves | Pickup, timing, logic, outputs | CT ratio and polarity, wiring, relay response, trip path |
| Equipment | Relay test set | High-current injection set |
| Typical use | Every relay at commissioning and maintenance | New installations, differential schemes, after CT work |
Worked example: timing test on an overcurrent relay (illustrative)
A feeder relay is set to a standard inverse curve with pickup Is = 400 A primary (CT 800/1, so 0.5 A secondary) and TMS 0.1.
| Test current (× Is) | Injected secondary current | Expected time | Example measured | Result |
|---|---|---|---|---|
| 2 | 1.0 A | About 1.00 s | 1.02 s | Pass |
| 5 | 2.5 A | About 0.43 s | 0.44 s | Pass |
| 10 | 5.0 A | About 0.30 s | 0.38 s | Investigate: outside a typical tolerance |
The 10 times result is slow by about 80 ms, more than the relay’s declared tolerance. The cause was a minimum operating time of 0.38 s entered by mistake in the setting file. It has no effect at low multiples, where the curve time is already longer, but it holds up the trip at high fault currents. Without the multi-point test it would have stayed hidden until a fault.
Primary injection: proving a CT
Injecting 400 A through the primary of an 800/1 CT should give 0.5 A at the relay. A reading of 0.25 A means the CT is on a 1600/1 tap or is the wrong CT; if the secondary current is right but the relay displays 200 A instead of 400 A, the ratio setting in the relay is wrong; a reading of zero means an open circuit or shorting link left in.
For a differential scheme, inject through both CTs: the differential current should be close to zero for through current. If it reads about twice the through current instead, one CT is reversed, and the relay would have tripped on the first load.
Never leave a CT secondary open with current flowing. Dangerous voltages appear, and the CT can be damaged. Check shorting links before and after every test, and remove every temporary link before returning the circuit to service.
Secondary injection plan
- Record as-found settings and compare them with the approved sheet.
- Test pickup and dropout for each element.
- Test operating times at several multiples of pickup.
- Test directional and sequence elements with correct phase angles.
- Test logic: blocking, interlocks, setting groups, outputs and indications.
- Prove the trip contact operates the breaker, where the outage allows.
- Restore settings and record as-left values.
Primary injection plan
- Isolate and secure the circuit; apply temporary shorts where required.
- Inject a safe current and read each CT secondary for ratio and polarity.
- For differential schemes, check through-current balance and internal-fault response.
- Confirm the correct relay and breaker operate.
- Remove all temporary links and record the results.
Typical findings
| Finding | Consequence if missed |
|---|---|
| Wrong CT ratio or tap | All current-based protection wrong by the same factor |
| Reversed CT polarity | Differential or directional protection trips on load, or never trips |
| Trip contact not wired | Relay operates, breaker stays closed |
| Setting group not switching | Wrong settings on generator supply |
| Settings differ from the approved sheet | Coordination lost |
Safety
- Work under a permit with lock-out and verified isolation.
- Isolate trip outputs on live equipment unless breaker operation is intended.
- Use a written procedure and a restoration checklist.
- Only qualified testers work on live panels.
See switchgear testing and commissioning.
Relay test record
A commissioning test on the 1010 kVA set’s overcurrent relay, 1600/5 A CTs, pickup set at 5 A secondary and a time multiplier of 0.2. Expected times come from the standard inverse curve above: at twice pickup, 0.2 × 0.14 ÷ (20.02 − 1) = 2.01 s.
| Element | Setting | Test current | Expected time | Measured time | Pass or fail |
|---|---|---|---|---|---|
| Overcurrent, inverse | Is 5 A, TMS 0.2 | 10 A, twice pickup | 2.01 s | 2.04 s | Pass, 1.5% high |
| Overcurrent, inverse | Is 5 A, TMS 0.2 | 25 A, five times | 0.86 s | 0.88 s | Pass |
| Overcurrent, inverse | Is 5 A, TMS 0.2 | 50 A, ten times | 0.59 s | 0.61 s | Pass |
| Earth fault, inverse | Is 1 A, TMS 0.1 | 5 A, five times | 0.43 s | 0.44 s | Pass |
| Instantaneous overcurrent | Is 40 A | 60 A | Under 0.05 s | 0.032 s | Pass |
| CT ratio and polarity, primary injection | 1600/5 A | 400 A through phase A | 1.25 A at the relay | 1.24 A, correct polarity | Pass |
| Whole trip path, primary injection | Is 5 A, TMS 0.2 | 3200 A primary, twice pickup | 2.01 s relay plus breaker | Breaker open at 2.08 s | Pass, 70 ms of breaker time |
The last two rows are the ones that justify the day’s work. Everything above them was proved by secondary injection, which tests the relay and nothing else: a relay can pass all five of those tests perfectly while its CT is wired with reversed polarity, or while the trip wire to the breaker is landed on the wrong terminal. The 1.24 A measured against 1.25 A expected proves the CT ratio, and the fact that the breaker actually opened proves the path. A record that stops at row five has tested a relay, not a protection scheme.
Worked example: is the test set big enough?
A secondary injection test set has to drive the test current through the relay’s input and the test leads. A modern numerical relay on a 1 A input has a tiny burden, perhaps 0.1 Ω, so injecting 10 A for a ten-times-pickup timing test needs only 1 V and 10 VA. An older electromechanical relay may present several ohms at its tap setting: 2 Ω at 10 A needs 20 V and 200 VA, and some test sets cannot hold a stable current at that burden.
For primary injection the question is different. A 200 A primary test set pushing current through a 1500/1 CT produces only about 0.13 A on the secondary, enough to prove ratio and polarity on a sensitive numerical relay, but not to test an overcurrent element set at several times rated current. Plan the primary test around what the CT ratio and test set can actually deliver.
As-found and as-left: why both are recorded
Every test should record the relay as it was found before anything was touched, and as it was left. As-found values show whether the protection would have worked correctly on the day before the test: a relay found with the wrong setting, a drifted timer or a disabled output had been unprotected since the last visit, and that is a finding even if it is corrected within minutes. As-left values prove what the next interval starts from. A test record with only as-left values tells the owner nothing about the risk they were carrying.
Testing logic, not just elements
Numerical relays combine their elements through programmable logic and an output matrix. A relay whose overcurrent element times perfectly can still fail to trip if the element is not mapped to the trip output, or if a blocking signal from another relay is permanently present. Test the logic end to end: inject a condition and watch the actual output contacts operate the right breakers and send the right signals, including interlocks and blocking schemes between relays. Compare the relay’s logic configuration with the approved design each time, because a logic change is invisible from the front panel.
End-to-end tests on schemes with two ends
Differential and other schemes that compare quantities at two locations can be tested by injecting at both ends at the same moment, with test sets synchronised to a common time reference. The injection reproduces a through-fault and an internal fault exactly as the relays would see them, including the phase relationship between the two ends. It proves the communication between the relays and the stability of the scheme without driving primary current through the protected equipment, and it should follow any change to the communication path or the CTs at either end.
Typical test intervals
| Item (illustrative) | Commissioning | Routine interval |
|---|---|---|
| Numerical relay, self-supervised | Full secondary injection and logic test | Every 3 to 6 years, with a functional trip test more often |
| Electromechanical relay | Full secondary injection | Every 1 to 2 years, as drift is more likely |
| CT ratio, polarity and magnetising curve | Primary injection and excitation test | After any work on the CT or its wiring |
| Breaker trip from protection | Every breaker | Every 1 to 2 years |
| Differential and REF stability | Primary or end-to-end test | After any change to CTs, wiring or settings |
The intervals depend on the importance of the equipment, the relay technology and its self-supervision, and the owner’s standards. A relay that has tripped correctly on a real fault, with its record downloaded and checked, has also passed a useful test.
Restoring the panel after testing
Most protection failures introduced by testing come from the last ten minutes of the job: a test link left open, a trip output left disabled, a CT shorting link left in, a settings group left on the test values. Use a restoration checklist for every panel, signed by the tester and checked by a second person, and confirm through the relay’s own status that every input and output is back in service before the panel is closed.
Common mistakes
- Testing the relay but not the circuit.
- Testing at one current only.
- Failing to restore settings or remove links.
- No as-found record.
What to send us
Send the relay models, setting sheets, CT ratios and the single-line diagram. WhatsApp 98852 01608 or use the enquiry form.
Evidence note. The example and tolerances are illustrative; each relay maker’s declared accuracy governs acceptance.
Questions engineers ask
What test set capacity does secondary injection need?
Enough voltage to drive the test current through the relay and leads. A numerical relay on a 1 A input with about 0.1 ohm burden needs only 1 V and 10 VA at 10 A, while an electromechanical relay of 2 ohms needs 20 V and 200 VA at the same current. For primary injection, remember the CT ratio: 200 A through a 1500/1 CT gives only about 0.13 A on the secondary.
What is an end-to-end test?
A test of a scheme that compares quantities at two locations, such as line or cable differential, in which test sets at both ends inject at the same moment, synchronised to a common time reference. It reproduces through-faults and internal faults exactly as the relays see them, proving the communication and stability without driving primary current through the equipment.
Is secondary injection enough?
For routine tests of a relay, yes: it proves pickups, timing and logic at the relay terminals. New installations and any change to CTs or their wiring also need primary injection, or an equivalent on-load check, because only current through the primary proves CT ratio, polarity and the secondary wiring.
Why record as-found values?
To show what the protection was actually doing before anything was adjusted. As-found records reveal drift, wrong settings, unauthorised changes and failures that would otherwise be corrected and forgotten, and over several tests they show trends that justify a shorter or longer test interval for each type of device.
Can injection be done live?
Secondary injection can be done with the plant running only with strict isolation: trip outputs isolated at test blocks, CT secondaries shorted before the relay is disconnected, and VT circuits isolated. The risks of an unwanted trip or an open CT are real, so many sites plan tests during outages or use duplicated protection.
How often should relays be tested?
At commissioning, after any change, and periodically, commonly every one to four years. Self-supervising numerical relays can be tested less often than electromechanical ones, which drift; critical or harsh-environment sites test more often. As-found failure rates from past tests are the best guide to the interval.
This guide gives general principles. Follow equipment and test-set instructions.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.