DG Synchronising Panels Guide

What a DG synchronising panel contains and how it works: synchroniser, sync-check, breaker control, metering, load sharing, protection and the commissioning tests that prove a safe paralleling.

In short. A synchronising panel is the control and protection cubicle that brings a generator onto a live bus safely. It matches speed, voltage and phase angle, and closes the breaker only when an independent check confirms the conditions are safe. It then manages load sharing and protects the set. Its quality shows in three places: the independence of the check-sync relay, the reliability of its control power, and how thoroughly it was tested.

Who this page is for: For engineers, contractors and owners specifying, buying or commissioning DG synchronising panels.

Key facts

  • The generator controller synchronises, shares load and provides basic protection.
  • An independent check-sync relay must also permit every close.
  • Breaker control covers open, close, trip, spring charge and status.
  • Generator protection includes reverse power, loss of excitation and overcurrent.
  • Control power comes from a monitored DC supply.
  • Commissioning proves sequence, synchronising, sharing and protection on load.

Panel contents

ItemPurpose
Generator controllerSynchronising, load sharing, basic protection
Check-sync relayIndependent permission to close
Breaker controlOpen, close, trip, spring charge, status
Protection relayReverse power, loss of excitation, overcurrent, earth fault
MeteringkW, kVAr, voltage, current, frequency
DC supplyControl power with monitoring. See DC control power

Worked example: panel acceptance checks (illustrative)

CheckExpectedFound
Check-sync wired in series with controller close outputClose blocked outside windowPass
Close attempted at 40 degrees with synchroniser forcedCheck-sync blocksPass
Reverse power test by reducing fuel on one setTrip at set value after delayPass at about 8%, 5 s
Loss of DC to the panelAlarm; breaker stays as it is; operator alerted, as protection cannot trip until DC returnsAlarm missing; added
Load sharing at 25, 50, 75%Within a few percent between setsPass after droop matched

See switchgear commissioning and commissioning.

Do not accept a synchronising panel where the check-sync function is only inside the same controller that issues the close. An independent relay in series is what stops one fault from closing a breaker out of phase.

Specifying

  • Number of sets now and in future.
  • Fault level of the bus and breaker ratings.
  • Load sharing method. See multi-set load sharing.
  • Protection functions and settings.
  • Interfaces: utility, SCADA, load shedding.

See paralleling switchgear.

Panel specification sheet

ItemValue
Generator rating and breaker 
Check-sync relay (independent?) 
Protection functions 
Load sharing method 
DC supply and monitoring 

Worked example: choosing the panel’s CTs

A synchronising panel usually carries three sets of current transformers: one for metering, one for protection and one for the generator controller’s load sharing. They are not interchangeable, because each is specified for a different part of the current range. Take a 1000 kVA, 415 V set with a full-load current of about 1391 A.

UseTypical specification (illustrative)Why
Metering1500/1, class 0.5 or 1Accurate around normal load; may saturate on faults, which protects the meter
Protection1500/1, class 5P10 or 5P20Within 5% error up to 10 or 20 times rated current, for fault measurement
Controller load sharingAs the controller maker specifies, often 1500/1 or 1500/5Matched to the controller’s input; accuracy at normal load matters most

The protection CT’s accuracy limit has to cover the fault current: a 5P10 CT on a 1500 A primary stays within 5% up to 15,000 A, which covers the set’s subtransient fault current of about 9300 A. The burden matters as much as the class.

With 10 m of 2.5 mm² copper lead each way, at about 0.0074 Ω per metre, the lead loop is about 0.15 Ω. On a 5 A secondary that loop alone absorbs about 25 × 0.15 ≈ 3.7 VA; on a 1 A secondary only about 0.15 VA. Where the CTs sit in the generator terminal box and the panel is some distance away, 1 A secondaries keep the burden within the CT’s rating. See protection CTs and VTs.

What the panel exchanges with everything else

Connected toSignals out of the panelSignals into the panel
EngineStart, stop, speed raise and lower or a speed bias signalRunning, speed, oil pressure, coolant temperature, engine alarms
Alternator and AVRVoltage raise and lower or a voltage bias signalVoltage, excitation alarms
Generator breakerClose, open, spring chargeOpen, closed, tripped, spring charged, racked in
Other synchronising panelsLoad-sharing data, dead-bus permissionLoad-sharing data, dead-bus permission
Plant or master controllerStatus, alarms, available capacityStart and stop requests, set points, mode
Building management or SCADAStatus, alarms, measurementsUsually read-only; remote commands only if agreed

Every interface needs a stated behaviour on loss of the signal. If the speed bias from the plant controller is lost, the set should hold its present load or fall back to droop, not run away; if load-sharing data from another panel is lost, the set should fall back to droop sharing. Write these behaviours into the panel specification and test them at the factory.

A settings sheet for one set’s panel

FunctionTypical starting value (illustrative)Checked against
Synchronising windowVoltage within 5%, slip up to 0.2 Hz, angle within 10 degreesMeasured breaker closing time
Check-synchronising relaySlightly wider than the synchroniser window, angle within about 20 degreesMust never be narrower than the synchroniser’s own window
Reverse powerAbout 8% of rated kW, 5 sEngine motoring power
Loss of excitationPer the alternator maker’s capability curveAlternator data
OvercurrentVoltage-restrained where the sustained fault current is lowFault study on generator supply
Dead-bus closingBus below about 10% voltage, with permission granted to one set onlyArbitration between panels

Keep a printed copy of the settings sheet in the panel and an electronic copy with the plant records, and update both whenever a value changes. The next engineer to investigate a trip will compare the relay’s actual settings with this sheet before anything else.

Load sharing inside the panel, and its fallback

Modern controllers share kW and kVAr by exchanging data over a dedicated link between panels, holding frequency and voltage constant. If that link fails, each controller must fall back to droop sharing on its own, so that the sets keep sharing in proportion to rating with a small, predictable change in frequency and voltage. Set the droop values to match across all sets before commissioning, test sharing with the link disconnected, and make the link failure a clear alarm on the plant controller. See multi-DG load sharing and power management.

Construction details that decide reliability

  • CT circuits: shorting-type terminal blocks so that a CT can be isolated without opening its secondary, which would otherwise develop a dangerous voltage.
  • Voltage sensing: fused, with fuse-failure supervision, and taken from points that cannot be isolated while the breaker is closed without the controller knowing.
  • Test blocks: in every protection current and voltage circuit, so relays can be injected without disturbing wiring.
  • Segregation: power and control wiring separated, and internal separation of the busbar and cable compartments to the form the specification demands.
  • Identification: ferrules at both ends of every wire matching the schematic, and as-built drawings in the panel pocket.
  • Heat: controllers and relays mounted away from resistors and power devices, with ventilation sized for the panel’s losses in a hot room.

One panel per set, or a common panel?

Each generator normally has its own synchronising panel, so that work on one set’s controls does not take the others out and a fault in one panel affects one set only. A common panel serving several sets saves space and cost on small plants, but every set then depends on the same cubicle, DC supply and wiring, and any maintenance inside it is a plant outage. Where a common panel is used, give each set its own controller, check-synchronising relay and protected DC circuit within it, and segregate the sections so that one can be worked on while the others run.

Earthing inside the panel

Each CT and VT secondary circuit should be earthed at one point only, normally in the panel where it is used, and that point should be shown on the drawings. The panel’s protective earth bar must be bonded to the generator and switchboard earthing with a conductor sized for the fault current, and screened communication cables should be earthed as the controller maker specifies, usually at one end, to avoid circulating currents that corrupt the load-sharing data. Many intermittent controller faults on site turn out to be earthing faults in the control wiring.

Factory tests and site tests

A synchronising panel should arrive on site having already proven everything that can be proven without the generator. The factory test covers wiring checks against the schematic, insulation tests, secondary injection of every protection function, simulation of the synchronising sequence with a test set, the check-synchronising relay’s blocking outside its window, and the behaviour on loss of DC and loss of each interface signal.

The site test then proves what only the real machine can show: phasing across the breaker, actual synchronising and closing time, load sharing at several loads, reverse power by reducing fuel, and the response to a set tripping at load. Splitting the tests this way finds wiring errors in the factory, where they are quick to correct, instead of on site with the client waiting. See FAT and SAT framework.

What should be handed over with the panel

  • As-built schematics and wiring diagrams, matching the ferrules in the panel.
  • The settings sheet for every controller and relay, with the reason for each value.
  • CT and VT test certificates, including ratio, polarity and magnetising checks.
  • Factory and site test records, signed, with measured closing times and sharing results.
  • Controller configuration files, backed up and stored off the panel.
  • The operating procedure for manual synchronising, posted at the panel.

Upgrading an old synchronising panel

Many older plants still synchronise by hand with a synchroscope and lamps, or with a first-generation controller that is no longer supported. An upgrade usually keeps the breakers and busbars and replaces the controls: a modern generator controller per set, an independent check-synchronising relay in each closing circuit, numerical protection with reverse power and loss of excitation, and monitored DC supply.

Before ordering, confirm that each breaker’s closing mechanism is fast and consistent enough for automatic synchronising, that the engine governor and AVR can accept the new controller’s bias signals, and that the existing CTs are of a suitable class, or budget for new ones. See legacy switchgear modernisation and retrofit.

Common mistakes

  • No independent check-sync.
  • Generator protection left to the controller only.
  • DC supply not monitored.
  • Sharing tested at one load only.

What to send us

Send the generator ratings, number of sets and the single-line diagram. WhatsApp 98852 01608 or use the application engineering enquiry.

Evidence note. Test values are illustrative.

Questions engineers ask

Which CT class does a synchronising panel need?

Usually three sets for different jobs: metering CTs of class 0.5 or 1, protection CTs of class 5P10 or 5P20, and whatever the generator controller specifies for load sharing. For a 1000 kVA set a 1500/1 protection CT of class 5P10 stays accurate up to 15,000 A, above the set subtransient fault current of about 9300 A. Prefer 1 A secondaries where the leads are long, to keep the burden low.

What should happen if the load-sharing link fails?

Each generator controller should fall back to droop sharing on its own, so the sets keep sharing load in proportion to their ratings with a small, predictable change in frequency and voltage. Match the droop settings on every set before commissioning, test sharing with the link disconnected, and make the link failure a clear alarm so it is repaired rather than left running in droop.

What is a synchroscope?

An indicator that shows the phase angle between the incoming generator and the busbar, and whether the generator is running faster or slower. The pointer rotates at the slip frequency and passes the top position when the two voltages are in phase. On automatic panels it is a check on the synchroniser; on manual panels it guides the operator, together with a sync-check relay.

Why is sync-check separate?

So that one failure cannot cause an out-of-phase close. The synchroniser adjusts speed and voltage and issues the close; an independent sync-check relay, with its own measurement, only permits the close inside the voltage, slip and angle window. If the synchroniser misbehaves, the check relay still blocks a bad close that could damage the alternator and coupling.

Can one panel serve several generators?

Usually each generator has its own section with its breaker, controller and protection, connected to a common bus and a communication link for load sharing. A common section then holds the bus, the feeders and any mains incomer. Shared components, such as one synchroniser switched between sets, are possible but create a single point of failure.

How often should it be tested?

At commissioning, after any change to controls, breakers or settings, and on a regular schedule, often monthly as part of on-load testing, so synchronising, load sharing and soft unloading are exercised. Check the close angle and peak current on the event record from time to time, because a slowing breaker gradually worsens synchronising.

This guide gives general principles. Follow the manufacturer’s commissioning procedures.