Generator Commissioning Checklist

Follow a complete generator commissioning checklist covering pre-energisation checks, load and AMF transfer tests, acceptance criteria and handover records.

In short. Generator commissioning is the structured proof that an installed set, its panel and its connections work as the design intended, under load and in automatic mode, before anyone relies on them. A set that starts is not commissioned. The checklist runs from pre-energisation inspection through no-load, load and transfer tests to a signed handover record, and each result is recorded against the scenario that was actually tested rather than implied for scenarios that were not.

Why a start-up is not a commissioning

Many sets in Telangana are handed over after a technician starts the engine, reads 415 V on the panel and leaves. The failures that follow are predictable: the AMF never sends a start signal because a sensing wire was left off, the set trips on the first motor start because the voltage dip was never tested, or the neutral is earthed at both the transformer and the alternator and the earth-fault relay trips on load.

Commissioning exists to find those faults while the installer is still on site and before an outage finds them for you. It has a defined scope, a sequence, acceptance criteria and a record. The service itself is described under generator commissioning; what follows is the engineering content of the checklist.

Pre-energisation checks

Nothing is started until the installation has been inspected cold against the drawings. The items below apply to a typical diesel set with an AMF panel; a synchronising installation adds more.

Running tests in sequence

StageWhat is checkedAccept when
First start, manualCranking time, oil pressure rise, leaks, unusual noise, exhaust colourStable idle and rated speed, no leaks, pressures within manufacturer limits
No-load runVoltage, frequency, phase balance, AVR stability, coolant temperature trend415 V and 50 Hz held within setpoint tolerance for 30 minutes
Protection functional testLow oil pressure, high temperature, overspeed, emergency stop, overcurrent, earth faultEach shutdown and alarm operates by simulation and is logged
Load testSteps to 25, 50, 75 and 100%, voltage and frequency dip and recovery, temperatures, fuel rateTransient response within ISO 8528 class agreed, no overheating at full load for the specified duration
Automatic mode testMains fail, start delay, transfer, retransfer on mains return, cool-down and stopSequence completes unattended with timings recorded
Site load testLargest motor start, UPS input, actual facility loadLoads start and run without nuisance trips

Where the facility load is not available or cannot be interrupted, a resistive or reactive load bank substitutes for it, and load bank testing is the only way to prove full-load thermal performance in a new building that is still empty. A no-load voltage reading proves nothing about behaviour under load.

Testing the transfer system, not just the set

The AMF or ATS panel is where most commissioning failures are found, because it is where the generator, the DISCOM supply, the controller and the site wiring meet. The test must include a real mains failure simulated by opening the incoming breaker, not a button on the controller.

Record the time from mains failure to generator breaker close, confirm the mechanical and electrical interlock prevents both sources closing together, test the retransfer delay so the site does not bounce back to an unstable supply, and check that the set runs its cool-down before stopping. On installations with a UPS, confirm the UPS rides through the transfer and that its battery charger does not pull the generator into an unstable condition when it reconnects. Panel logic is explained under AMF panels.

Recording the scenario, not just the result

A commissioning record that says “load test passed” is close to worthless a year later. The record should state the scenario: which load, for how long, at what ambient temperature, with which protection settings and which firmware version in the controller. If the set was tested to 75% because the load bank available was too small, the record says so and the 100% test is listed as outstanding.

If a protection function was bypassed to complete a test, that is recorded and the bypass removed before handover, never left in place. The final pack should contain the as-built single-line diagram, the settings list, the insulation and earth resistance readings, the load test log, the AMF sequence timings, the outstanding items with owners and dates, and the signatures of installer and client. The start-up and handover service closes this pack, and the readings in it become the baseline for maintenance planning.

Related photographs and videos

Commissioning and acceptance.

What each test has to leave behind

A commissioning test that produced the right result and no usable record has to be done again, and it usually is — two years later, by somebody who cannot tell whether the figure in front of them was ever good. The sequence above says what to run. This says what each run must leave behind for it to count.

TestThe measurement that proves itWhat the record must carryWhat makes the record worthless
Insulation resistanceResistance at a stated test voltage, with the machine at a stated temperatureVoltage applied, duration, winding temperature, instrument and its calibration dateA single figure with no temperature beside it, which cannot be compared with anything later
Loaded electrical performanceVolts, amps and frequency on each phase at each load step, with the step held long enough to settleThe load at each step in kW and in percent, the power factor, and how long it was heldReadings taken while the load was still changing, which read better than the truth
Thermal stabilityCoolant, oil and air temperatures still rising or flat at the end of the full-load runThe ambient, the room air path as it actually was, and the last three readings so the trend is visibleOne temperature at the end of the run, which cannot show whether it had stopped climbing
Exhaust back pressurePressure at the engine outlet at full load, against the engine maker’s limitThe tapping point, the instrument, and the limit it was judged againstA pass recorded with no limit stated, which is an opinion rather than a result
Transient responseThe voltage and frequency excursion and the time to recover, captured rather than watchedThe step applied, in kW and as a percent of rating, and the recovery time to a stated band“Recovered quickly”, which no later engineer can compare a new reading against
Automatic transferElapsed times for each stage, from mains failure to load restored and backEvery delay setting as found and as left, with the measured times beside themMeasured times with no settings recorded, so a changed delay is invisible
Protection and alarmsEach function made to operate by injection or simulation, and seen to actHow it was made to operate, what the set actually did, and which functions were not provableA tick against a function that was only confirmed to be enabled on a screen

The pattern down the last column is the same failure in seven forms: a result recorded without the conditions that produced it. A figure with its conditions can be compared with a figure taken three years later, and that comparison is the whole value of commissioning records. A figure on its own can only be read as a pass or a fail by the person who took it, on the day, and that person will not be available.

Instruments, and the question nobody asks on the day

Before any of the above means anything, the instruments have to be worth believing. Record the make, model and serial of each one used, and the date its calibration expires — not whether it is calibrated, but when that lapses, because a certificate that ran out two months ago invalidates every reading taken with it. Where a reading comes from the generator controller rather than a test instrument, say so: a controller’s displayed current is derived from its own transformers and is a useful number, but it has not been proved against anything and should not be recorded as a measurement.

One practical ordering point. Take the baseline readings before the first loaded run, not after. Insulation resistance on a cold, dry machine, battery voltage before any cranking, and coolant and oil levels before the set has run are the only chance to capture the machine in a known state. After a full-load run every one of those is a different number, and the set has no baseline for the rest of its life.

Common mistakes

What to send us

Send the single-line diagram, the generator and panel nameplate photographs, the site drawings showing room, exhaust and fuel arrangement, a list of the largest motors and any UPS on the backed-up supply, and the date the site expects to take load. Tell us whether a load bank will be needed because the facility load is not yet available. We will return a commissioning scope and test plan matched to the installation. Request generator commissioning or a pre-handover check.

Questions engineers ask

What should a commissioning record contain for each test?

The conditions, not only the result. A resistance figure needs the test voltage and the winding temperature; a loaded reading needs the load in kilowatts and as a percent, the power factor and how long the step was held; a back-pressure result needs the tapping point and the limit it was judged against. A number recorded without its conditions cannot be compared with a reading taken three years later, and that comparison is the whole value of the record.

Why take the baseline readings before the first run?

Because after a loaded run every one of them is a different number, and the machine never has a baseline again. Insulation resistance on a cold dry winding, battery voltage before any cranking, coolant and oil levels before the set has run: those describe the machine in a known state. Taken afterwards they describe a machine that has just worked, which is useful but is not a reference.

How long should a full-load commissioning test run?

Long enough for coolant and oil temperatures to stabilise at full load, which usually means at least one to two hours at 100% after the step tests, in the hottest ambient conditions practical. Shorter runs prove electrical output but not thermal capacity. Record readings every 15 minutes.

Can we commission without a load bank?

Only if the actual facility load is available, can be interrupted for testing and is large enough to reach the rated output. In a new building that is still empty, a load bank is the only way to prove full-load performance before handover. Plan its connection early.

Who signs off a generator commissioning in India?

The installer and the client’s engineer sign the test record. Depending on capacity and state rules, the installation may also need electrical inspectorate approval under the CEA regulations before it is energised, and the pollution control board consent conditions apply to emissions and noise. Keep copies.

What is the difference between commissioning and a routine load test?

Commissioning proves the whole installed system against its design for the first time, including wiring, protection, earthing and transfer logic. A routine load test later confirms the set still performs; it assumes the system was proven correct at the start. Compare each later test with the commissioning record.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.