In short. Old switchgear can still carry load and yet be unsafe or unsupportable: no spares, a breaking capacity below the present fault level, electromechanical relays with no records, or no protection against arc flash. Start with a condition and risk assessment. Then choose the smallest scope that removes the real risks: refurbishment, a relay upgrade, breaker retrofits, partial replacement or full replacement. Plan the outage with temporary power, and re-run the protection study before anything is energised again.
Who this page is for: For plant engineers and facility managers with ageing switchboards: decide what to refurbish, retrofit or replace, and plan the work without losing critical loads.
Key facts
- Start with a condition and risk assessment, then choose the smallest scope that removes the real risks.
- Options, in rising scope: refurbishment, relay upgrade, breaker retrofit, partial replacement, full replacement.
- Check both breaker breaking capacity and busbar short-time rating against the present fault level.
- New numerical relays need settings from a new study, not copies of old dial positions.
- Plan the outage with temporary power for critical loads, such as a rental generator.
Signs it is time to act
- Spare parts and maker support are no longer available for the breakers or relays.
- The fault level has grown, through a larger transformer, added generators or more motors, beyond the switchgear’s rated breaking or short-time capacity.
- Breakers fail to trip, trip slowly or need repeated mechanical attention.
- Relays are electromechanical, with unknown settings, no test records and no event recording.
- There is no arc-flash containment, no shutters and no safe racking.
- New needs the old panel cannot meet: generator paralleling, synchronising, remote monitoring or hybrid integration.
Condition assessment
| Check | Method | What it reveals |
|---|---|---|
| Ratings against duty | Compare nameplate breaking and short-time ratings with a fresh fault study | Whether the gear can safely interrupt today’s faults |
| Thermal condition | Thermography under load | Loose joints, overloaded busbars, failing contacts |
| Breaker contacts | Contact resistance test (micro-ohm) | Worn or pitted main contacts |
| Breaker mechanism | Timing and travel tests, trip and close coil checks | Slow or sticking operation |
| Insulation | Insulation resistance; partial discharge on HT gear | Moisture, tracking and ageing insulation |
| Protection | Secondary injection of relays; CT checks | Whether the relays and CTs still work as set |
| Oil-filled breakers (HT) | Oil sample and dielectric test | Carbonised or wet oil |
| Documentation | Drawings, settings, maintenance history | What is actually installed versus what is drawn |
Rank each finding by consequence and likelihood. A slightly warm joint is a maintenance job. A breaker that cannot break the present fault level is a safety problem that limits the options.
The options
| Option | Scope | Outage | Relative cost | Best when |
|---|---|---|---|---|
| Refurbishment | Clean, re-torque, replace worn parts and insulation | Short | Low | Structure and ratings are sound and spares exist |
| Relay upgrade | Numerical relays replace electromechanical ones; CTs checked | Short per panel | Low to medium | Breakers are good but protection is old |
| Breaker retrofit | Modern breaker in the existing cubicle using an engineered adapter | Short per cubicle | Medium | Busbars and enclosure are sound but breakers are obsolete |
| Partial replacement | New panels for critical sections, old sections kept | Staged | Medium to high | Only part of the board is at risk |
| Full replacement | New switchboard | Longest | High | Ratings are inadequate or the structure is unsafe |
A breaker retrofit is not a simple swap. Changing the breaker can affect the fault ratings that were proven for the original assembly. Use retrofit kits with the switchboard or breaker maker’s support and documented ratings, and check the busbar’s short-time rating separately.
Relay upgrades: what to check
- CTs. Old CTs were often sized for the burden of electromechanical relays. Numerical relays draw far less, which helps, but check the CT ratio, class and knee-point voltage against the new settings, especially instantaneous elements on high fault levels.
- Auxiliary supply. Numerical relays need a reliable DC or UPS-backed auxiliary supply; electromechanical relays did not need one to operate.
- Functions. Use the upgrade to add what the old scheme lacked: earth-fault, breaker-failure, event and disturbance recording, and for generator panels, reverse power, under- and over-voltage, under- and over-frequency, and sync-check.
- Settings. New relays need new settings from an updated study, not a copy of the old dial positions.
Retrofit work often takes place next to live sections. Isolate, lock off and prove dead under a written permit before any panel is opened.
Planning the outage
- List the loads on each section and how long each can be without power.
- Arrange temporary supply for the critical loads: a rental generator connected to a temporary feeder, or a temporary bus. See rental power.
- Stage the work so that critical loads always have a supply.
- Prepare isolation and permit procedures for work next to live sections.
- Pre-wire and pre-test as much as possible off site.
- Keep a rollback plan if a section cannot be energised on time.
Worked example (illustrative)
A 30-year-old 415 V main switchboard in a factory near Hyderabad has a 1600 A ACB incomer of a model that is no longer supported, electromechanical relays and a 500 kVA standby generator changeover added years later. A transformer upgrade has raised the prospective fault level at the board from about 25 kA to about 35 kA. The incomer’s breaking capacity and short-time rating are both 35 kA (for one second); three feeder MCCBs are rated 25 kA.
| Finding | Decision |
|---|---|
| Busbars and enclosure in good condition; thermography clean; busbar short-time rating confirmed at or above 35 kA for 1 s | Keep (otherwise brace or replace the busbars) |
| Incomer ACB obsolete, rated at exactly the new fault level | Retrofit a supported ACB rated 50 kA in the existing cubicle, with maker documentation |
| Three feeder MCCBs rated below the fault level | Replace with 50 kA units |
| Electromechanical relays, no records | Numerical relay on the incomer; settings from a new study, including a generator-mode group |
| Changeover with only an electrical interlock | Add a mechanical interlock; test each layer. See interlocking and permissives |
The work is done over one weekend. A rental set feeds the critical process load through a temporary panel, and the board is re-energised only after the injection tests and the interlock tests have passed.
Condition scoring sheet
| Item | Score 1 (good) to 5 (unsafe) | Notes |
|---|---|---|
| Breaking and short-time rating versus fault level | ||
| Spares and maker support | ||
| Breaker mechanism and contacts | ||
| Busbars, joints and insulation | ||
| Protection relays and CTs | ||
| Operator safety: shutters, interlocks, arc containment | ||
| Fitness for new functions (generator, monitoring) |
Any score of 5 on rating or safety decides the scope on its own. Otherwise the total guides whether refurbishment and upgrades are enough.
After the work
Re-run the short-circuit and coordination study with the new equipment, commission as for a new board, and update drawings, labels, settings records and operating procedures. See switchgear testing and commissioning and upgrade and replacement planning.
Worked example: is the old busbar strong enough? (illustrative)
A breaker can be retrofitted in an afternoon; the busbar behind it is usually the part that decides whether the board can stay. Two ratings matter. The short-time rating says how long the bars and supports can carry a fault current without overheating; the peak rating says whether they can survive the first-cycle mechanical force.
| Check | Working | Result |
|---|---|---|
| Nameplate short-time rating | 25 kA for 1 s | Heating capability 25² × 1 = 625 kA²s |
| New prospective fault | After the transformer upgrade | 35 kA |
| Time the bars can carry 35 kA | (25 ÷ 35)² × 1 | about 0.51 s |
| Clearing time of the backup for a bus fault | Incomer short-time delay 0.3 s plus breaker opening 0.05 s | 0.35 s: within 0.51 s |
| Peak withstand needed at 35 kA | Factor 2.1 for 20 to 50 kA at low voltage: 2.1 × 35 | 73.5 kA peak |
| Peak withstand of the old bars | 2.1 × 25 | 52.5 kA peak: not enough |
The thermal check passes and the mechanical one fails, which is the common pattern: heating can be bought back with faster clearing, but the first-cycle force cannot. Bracing the bars to a documented rating, limiting the fault current, or replacing the section are then the choices. A busbar with no nameplate rating at all is treated as unproven until the maker or a type-tested equivalent confirms one.
Worked example: why old relay settings do not carry over (illustrative)
An electromechanical inverse-time relay on a 400/5 A CT is found at plug setting 100% and time multiplier 0.3, that is a 400 A setting. On the standard inverse curve the time at ten times setting is 0.14 × 0.3 ÷ (100.02 − 1) = 0.042 ÷ 0.0471 ≈ 0.89 s. Injection testing finds the old disc actually operating in about 1.05 s at that current, because bearings and springs have drifted over the years.
The downstream devices were set, informally, against the slower real relay. Copy the dial settings into a numerical relay and the incomer becomes 0.16 s faster, which can remove the margin the feeders were relying on. The only safe basis is a new study, followed by injection of the new relay at the new settings.
Use the retrofit to reduce arc-flash risk
- Arc detection: light sensors with a current check can usually be added to an existing board, cutting clearing for an internal arc to well under a tenth of a second.
- Maintenance switch: a selector that lowers the incomer’s short-time delay while people work on the board, so an arc clears in about 0.05 s instead of 0.3 s, roughly a sixth of the energy.
- Remote racking and operation: moves the operator outside the arc boundary for the riskiest task, racking a breaker in or out.
- Shutters and insulated barriers: close off live spouts when a breaker is withdrawn, which many old boards lack entirely.
Rerun the arc-flash study after the work and relabel the board. See arc-flash risk and mitigation.
Retrofit or replace: what to compare
| Factor | Retrofit in the existing board | New switchboard |
|---|---|---|
| Outage | Short, one cubicle at a time | Long, unless built alongside and cut over |
| Proven ratings | Only as good as the retrofit kit’s documentation and the old busbar | Verified as a complete assembly by the maker |
| Internal arc containment | Rarely improves | Can be specified from the start |
| Remaining life | Limited by the oldest part kept | Full life |
| Space and lead time | Uses the existing footprint, short lead time | Needs space or a phased swap, longer lead time |
Old materials need planned handling
Older switchgear can contain materials that need care during strip-out: oil in bulk-oil and minimum-oil breakers, arc chutes and boards made with asbestos-based materials in some older designs, SF6 gas in some high-voltage units, and lead-acid batteries in the tripping supply. Identify them in the assessment, before any panel is dismantled, and arrange removal and disposal through authorised handlers. Finding them during the outage stops the work and lengthens the shutdown.
Common mistakes
- Retrofitting breakers without checking the busbar’s short-time rating.
- Copying old relay settings into new relays.
- Underestimating the outage, with no temporary supply ready.
- Mixing new and old devices without a fresh selectivity check.
- Leaving drawings and labels as they were.
What to send us
Send photographs of the switchboard and nameplates, the single-line diagram, the present fault level or transformer details, relay settings if known, and the loads that cannot be interrupted. WhatsApp 98852 01608 or use the enquiry form.
Evidence note. The example is illustrative. Retrofit decisions need inspection and testing of the actual switchgear and the makers’ documentation.
Questions engineers ask
How do I check the short-time rating of an old busbar?
Compare its nameplate rating with the present fault level in two ways. Heating scales with current squared times time, so bars rated 25 kA for 1 s carry 35 kA for only about 0.51 s, which backup clearing of 0.35 s can meet. The peak force cannot be bought back: at 35 kA the bars need about 73.5 kA peak withstand, against 52.5 kA for a 25 kA rating.
Can old relay settings be copied into a numerical relay?
No. An old disc relay set at time multiplier 0.3 should operate in about 0.89 s at ten times setting, but drifted relays are often found at 1.05 s or more, and downstream devices were graded against the slower real relay. Copying the dial settings makes the incomer faster and can remove the margin. Use a new study and test the new relay by injection.
Is retrofit cheaper than replacement?
Usually at the start, because the busbars, enclosure and cabling are reused and the outage is shorter. Over the whole life it depends on the busbar ratings against the present fault level, how long the oldest retained parts will last, and whether a new board would add internal arc containment. Compare outage, proven ratings, remaining life and risk, not just the first cost.
Can new breakers fit old cubicles?
Often, using engineered retrofit kits that adapt a modern breaker to the old cubicle, racking and busbar connections. Use kits backed by the breaker or switchboard maker with documented ratings for the combination, check the busbar short-time and peak ratings separately, and confirm interlocks, shutters and auxiliary wiring work with the new breaker before it is energised.
Do I need a new study after retrofit?
Yes. New breakers and relays have different curves and ratings, and the fault level may have changed since the board was built. Rerun the short-circuit study, the coordination study on every source including the generator, and the arc-flash study, then issue settings from those results and test them by injection before re-energising.
How can I keep power on during the work?
Work one section or cubicle at a time and feed critical loads from a temporary supply, such as a rental generator connected through a temporary panel or feeder. Pre-wire and test new parts off site, prepare isolation and permits for work next to live sections, and keep a rollback plan in case a section cannot be re-energised on time.
This guide gives general principles. Decisions need inspection and testing of your switchgear.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.