Time-Current Coordination (TCC) Engineering Guide

How to read and build time-current curves: device characteristics, inverse and definite-time regions, damage curves, inrush points, grading margins and a method to check selectivity.

In short. A time-current characteristic (TCC) shows how long a protective device takes to operate at each value of current. When the curves of every device in a supply path are drawn on one log-log chart, you can see at a glance three things: whether the device nearest a fault trips first, whether each device protects the cable or equipment it serves, and whether normal starting and inrush currents pass without tripping. On sites with generators the chart must be checked twice, at grid fault levels and at the much lower, decaying generator fault level.

Who this page is for: For electrical engineers, consultants and maintenance teams who must read, check or approve a protection coordination study, including the generator-supply case that most studies miss.

Key facts

  • Both axes are logarithmic: current across, operating time up.
  • Downstream devices must lie to the left of and below upstream devices, up to the downstream fault level.
  • Check the gap between tolerance bands, not between the central lines of the curves.
  • Device curves must lie below and to the left of the damage curve of the cable, transformer or motor they protect.
  • A PMG or auxiliary-winding generator holds about 3 × rated current for around 10 s on a fault; a shunt-excited set may not.
  • Plot every source case: grid only, one generator, all generators.

Reading a TCC chart

Current runs along the horizontal axis and time up the vertical axis, both on logarithmic scales, so that 10 A and 10,000 A, or 10 milliseconds and 1000 seconds, fit on one sheet. The lower left of the chart is fast and sensitive. The upper right is slow and tolerant. A well-coordinated system looks like a set of curves nested inside each other without crossing, with the device nearest the load furthest to the left and lowest.

Conductor heating ∝ I² × t · on log-log axes an I² × t limit is a straight line with a slope of −2

That is why cable damage lines and the long-time part of breaker curves look like sloping straight lines: they both follow heat, and the breaker curve must stay below and to the left of the cable line.

The regions of a device curve

RegionBehaviourPurpose
Long-time (overload)Inverse time, seconds to minutesProtects cables and equipment against heating
Short-timeFixed delay or an I²t ramp, tens to hundreds of millisecondsClears faults while giving downstream devices time to act first
InstantaneousNo intentional delay, a few tens of millisecondsClears severe faults as fast as possible
Fuse melting and clearing curvesTwo curves forming a bandThe band between them is what must be coordinated

Every curve is really a band. Manufacturers publish minimum and maximum operating times for electronic releases, and melting and total clearing curves for fuses. Coordination is checked between the edges of the bands, not between their centres.

What goes on the chart

ItemShown asWhy it is there
Protective devicesCurves with pickup, delay and instantaneous regionsThe thing being coordinated
Full-load currentVertical linePickups must sit to the right of it
Motor startingStarting current for the starting timeCurves must pass to the right of and above it
Transformer inrushPoint, typically 8 to 12 × rated at about 0.1 sInstantaneous settings must sit above it so that energising does not trip
Transformer, cable and motor damageCurves or straight I²t linesProtection must operate before damage
Generator decrementDecaying fault current against timeShows what the generator really delivers in a fault
Maximum and minimum fault currentVertical lines for each source caseLimits of the range the devices must cover

Why the generator case changes the chart

A grid fault level is a single vertical line. A generator’s fault current is a curve that falls with time: about rated current ÷ X″d for the first cycles, then towards rated ÷ X′d, then a sustained value set by the excitation. Alternators with PMG or auxiliary-winding excitation are commonly rated to hold about 300% of rated current for around 10 seconds.

A shunt-excited alternator may fall to rated current or below within a second. Draw the generator decrement curve on the chart. Any device whose operating point lies to the right of the decrement curve at its delay time will not trip on generator supply. See generator short-circuit current.

Worked example: one feeder, two sources (illustrative)

A 1600 A incomer ACB feeds a board with a 630 A feeder MCCB. The board is supplied either from the grid (12 kA at the board) or from a 500 kVA generator with PMG excitation (about 4.6 kA initially, about 2.1 kA sustained).

CheckGrid supplyGenerator supply
Feeder MCCB on a fault at its outgoing terminalsInstantaneous region, about 20 msBelow its instantaneous setting; short-time element at 1500 A pickup clears in about 0.2 s
Incomer ACB on the same faultShort-time band starts at about 0.3 s: clear gapGenerator breaker and incomer short-time delays set at 0.4 s or more: both wait while the feeder clears
Feeder cable damage lineFeeder clears long beforeFeeder clears at 0.2 s, still left of the cable line
Generator decrement at 0.2 sNot applicableAbout 2.5 kA, above the 1500 A pickup: trip assured
Busbar short-time withstandIncomer curve stays below itFar below

If the same feeder had kept a grid-style short-time pickup of 5000 A, the generator fault current, about 4.6 kA at first and falling towards 2.1 kA, would never reach it, and the fault would be cleared only by the long-time element many seconds later. This is one of the most common problems on generator-backed boards.

A TCC study done only for grid supply does not prove a generator-backed installation is protected. Ask for the generator case to be plotted before accepting the settings.

How to check a TCC study, step by step

  1. Draw the maximum and minimum fault-current lines for each board and each source case.
  2. Add full-load, starting and inrush points for the largest loads.
  3. Add damage curves for cables, transformers and motors.
  4. Check that each device curve is right of its load and starting points and left of its damage curve.
  5. Check selectivity between each pair of devices up to the downstream fault level, using tolerance bands. Typical gaps are 0.2 to 0.3 s between numerical relays and electronic releases and 0.3 to 0.4 s with electromechanical relays.
  6. Repeat with the generator decrement curve instead of the grid fault line.
  7. Record where full selectivity is not possible and accept it knowingly.

Curves at different voltages

When HT and LV devices appear on one chart, all currents must be referred to a single voltage. An 11 kV relay curve is moved onto a 415 V chart by multiplying its currents by 11,000 ÷ 415 ≈ 26.5. Forgetting this conversion is a common reason for curves that seem to coordinate but do not.

Problems commonly seen on charts

  • Instantaneous regions that overlap, so both devices trip together.
  • An upstream breaker with no short-time delay, so there is no selectivity at all.
  • A fuse and a relay with different curve shapes that cross at high current.
  • Instantaneous setting below transformer inrush.
  • No generator decrement curve, so the generator case was never checked.

From chart to evidence

A chart shows intended behaviour. Evidence comes from injection test results, as-left settings and relay event records after a real trip. If a recorded operating time differs from the chart, investigate before the next fault. See injection testing and protection records.

TCC review worksheet

CheckGrid supplyOne generatorAll generators
Fault-current lines drawn   
Load, starting and inrush clear of curves   
Damage curves protected   
Selectivity gaps (tolerance bands)   
Generator decrement checked   
Accepted exceptions recorded   

Grading margins that are commonly used

Upstream and downstream pairTypical marginNote
Electronic trip breaker over electronic trip breakerAbout 0.1 to 0.15 s in the short-time zoneTight tolerances allow small margins
Numerical relay over numerical relayAbout 0.2 to 0.3 sIncludes breaker opening time and relay overshoot
Older electromechanical relaysAbout 0.4 sWider tolerances and overshoot
Fuse over fuseCurrent ratio of about 1.6 to 2 to 1Confirmed from the maker’s selectivity data
Breaker over fuseUpstream curve clear of the fuse total clearing curveChecked on I²t in the fast region

The margin is checked between the edges of the tolerance bands at the maximum fault current seen by the downstream device, not between the central lines at a convenient current.

When curves are not enough

For faults large enough to operate instantaneous elements or current-limiting breakers, the curves of two devices often overlap, and the chart cannot show whether they are selective. Breaker makers publish selectivity tables, based on tests of specific combinations, that state up to what fault current the downstream device clears alone. Selectivity in that region is proved from those tables, for the actual pair of devices, not from the curves.

Partial selectivity

A pair can be selective only up to a certain current, for example 10 kA, above which both may trip. If the maximum fault current at the downstream device is below that limit, the pair is fully selective in practice; if it is above, the pair is partially selective, and a fault close to the downstream device may trip the upstream one as well. The study states the limit for each pair and whether it is enough for the critical paths.

The settings schedule

The study ends with a schedule listing every adjustable device, its location, current rating, and each setting: long-time pick-up and delay, short-time pick-up and delay, instantaneous pick-up, earth fault pick-up and delay, and any setting groups. Old and new values sit side by side. The schedule is used to apply the settings, to test them by injection, and as the record for the next study. See protection coordination study workflow.

Common mistakes

  • Spacing the central curves instead of the tolerance bands.
  • Leaving damage curves off the chart.
  • Plotting only the grid case.
  • Mixing voltage bases on one chart.
  • Trusting software output without checking its assumptions.

What to send us

Send the single-line diagram, the device models and settings, cable sizes and lengths, and the generator and alternator data sheets. WhatsApp 98852 01608 or use the enquiry form. See also coordination and selectivity and the coordination study workflow.

Evidence note. Excitation support figures are typical of present-day alternator designs; the selected alternator’s data sheet governs. The worked example is illustrative.

Questions engineers ask

What grading margin is needed between protective devices?

Commonly about 0.1 to 0.15 s between electronic trip breakers, about 0.2 to 0.3 s between numerical relays, about 0.4 s for older electromechanical relays, and a current ratio of about 1.6 to 2 to 1 between fuses. The margin is checked between tolerance band edges at the maximum fault current the downstream device sees.

Why are maker selectivity tables needed as well as curves?

For faults large enough to operate instantaneous elements or current limiting breakers, the curves overlap and cannot show whether two devices are selective. Makers test specific combinations and publish the fault current up to which the downstream device clears alone. Selectivity in that region is proved from those tables for the actual pair.

Why log-log scale?

Because protective devices act over a huge range of current and time, from tens of amps to tens of kiloamps and from milliseconds to many minutes. A logarithmic scale fits that range on one sheet, and heating limits that follow current squared times time become straight lines, which makes the chart easy to read.

What is a damage curve?

A curve showing how long a cable, transformer or motor can carry a given current before it is damaged by heat or mechanical force. The protective device curve must lie below and to the left of the damage curve of the equipment it protects, at every current up to the maximum fault level.

How much time gap is enough?

Enough to cover the tolerance of both devices, the opening time of the downstream breaker and any relay overshoot. Commonly about 0.1 to 0.15 s between electronic trip breakers and about 0.2 to 0.3 s between numerical relays, checked at the maximum fault current the downstream device sees, on every source the site can run on.

Can software do this?

Software plots the curves, applies tolerances and checks margins quickly at every current, which is essential for large systems. It still needs correct device data and settings, a check of every source case including generator supply, and maker selectivity tables for the instantaneous region, where curves cannot show selectivity.

This guide gives general principles. Settings must be confirmed with manufacturer curves.