In short. A protection coordination study chooses settings so that for any fault the nearest device trips first and the others wait, while every cable, transformer, motor and generator stays inside its damage limit. The workflow runs from verified site data, through fault levels and time-current curves, to a settings schedule that is applied, tested and recorded. Most failed studies fail at the first step: settings copied from drawings that no longer match the panel.
Who this page is for: For consultants, protection engineers and plant owners commissioning, reviewing or updating a coordination study.
Key facts
- Set devices from the load end towards the source.
- Grading margins commonly fall between about 0.2 and 0.4 s, depending on device type; use makers’ data.
- Every setting is checked against the downstream device, the damage curve and the minimum fault current.
- Repeat the study for each source mode: grid, generator and parallel.
- Data collection and site verification usually take longer than the calculations.
- Deliverables are curves, a settings schedule, a list of accepted compromises and as-left test records.
The workflow
- Scope and criteria: boundary, grading margins, objectives. See setting philosophy.
- Collect data: single-line diagram, device models and curves, existing settings, CT ratios, cable, transformer and motor data.
- Verify on site: compare nameplates and downloaded settings with the drawings. See inputs and validation.
- Fault levels: maximum and minimum for each mode. See maximum and minimum fault current.
- Load and inrush: full-load, motor starting, transformer inrush and cold-load pickup.
- Damage curves: cables, transformers, motors and the generator.
- Plot and set: curves from load to source, each with its margin. See TCC engineering.
- Resolve conflicts: change devices, add zone interlocking or differential, or accept partial selectivity with a recorded reason.
- Review every mode: grid, generator and parallel.
- Implement and verify: apply settings, test by injection, record as-left values.
Data you must have
| Data | Why |
|---|---|
| Device make, model and curve family | Curves differ between makers and models |
| Existing settings, downloaded or read from the trip unit | Drawings are often out of date |
| CT ratios | Convert primary settings to relay settings |
| Transformer inrush | Avoid trips on energisation |
| Generator decrement curve | Check pickup on the decaying fault current |
| Cable sizes and lengths | Damage curves and minimum fault levels |
Worked example: the main that tripped for every feeder fault (illustrative)
A site with a 1600 A main ACB and eight feeders loses the whole board whenever any feeder faults. Site verification finds the main set differently from the drawings.
| Item | As found | As left |
|---|---|---|
| Main short-time pickup | 2 × In = 3200 A | 6 × In = 9600 A |
| Main short-time delay | 0 s | 0.2 s |
| Main instantaneous | On | Off, or set above the maximum feeder fault |
| Largest feeder (630 A MCCB) instantaneous | 10 × In = 6300 A | Unchanged |
| Feeder fault on grid (about 20 kA) | Main and feeder trip together | Feeder clears; main waits |
The study then checks that 0.2 s still protects the busbar and the transformer’s LV cable, and that on generator supply, where sustained fault current may be only about 3 kA, the feeder, whose 6300 A instantaneous cannot see 3 kA, still clears on its long-time element inside the generator’s capability and the cable’s withstand. See coordination and selectivity.
Never copy settings from a similar site or from old drawings. Download or read the actual settings, verify CT ratios on site, and update the study whenever a device, source or setting changes.
Typical findings on generator sites
- Instantaneous settings above the generator’s fault current, so they never operate on generator supply.
- Earth-fault elements set for grid fault levels.
- Cable protection not met at the minimum fault.
- Overlapping curves between main and feeders.
- Trips on transformer inrush after a restart.
Deliverables
- Time-current curve sets per path and per mode.
- A settings schedule by device and tag, with relay files.
- A list of coordination compromises and the reasons.
- Data for an arc-flash study. See arc-flash study.
- As-left test records.
Settings schedule template
The as-found and as-left settings for one installation — a 2000 kVA transformer with two 1250 kVA generators, a 3200 A main board and feeders at 250 and 400 A — which is the deliverable the workflow exists to produce. The example above is one main breaker that tripped for every feeder fault and the five lines that fixed it; this schedule covers seven devices on a larger site with a generator setting group and a maintenance setting, and three of the seven were found different from the drawings.
| Device tag | Model | As found | New setting | Tested (date) |
|---|---|---|---|---|
| Q1 main incomer | 3200 A air circuit breaker, electronic trip | Long-time 3200 A. Short-time 2 × In = 6400 A at 0 s. Instantaneous on, at 20 kA | Short-time 6400 A at 0.3 s. Instantaneous off, since no downstream device needs it and it defeats grading | Primary injection at commissioning, and again after the change |
| Q1, generator setting group 2 | Same device, second group selected by source state | Not configured | Short-time 4000 A at 0.3 s, so the element still picks up when the sustained single-generator fault is 5.2 kA | Primary injection at 4.5 kA, with the group forced |
| Q1 maintenance setting | Same device, key-switched | Not fitted | Instantaneous 6400 A at 0.05 s while enabled. Alarmed and logged when left on | Primary injection, and recorded against the arc-flash study |
| Q21 sub-board 1 incomer | 1250 A moulded case, electronic trip | Long-time 1250 A. Short-time 8 × In = 10 kA at 0 s | Short-time 10 kA at 0.1 s, giving a 0.2 s margin to Q1 | Primary injection |
| Q31 sub-board 2 incomer | 630 A moulded case | Instantaneous 2 × In = 1260 A. Found at 4 × In = 2520 A, not as drawn | 1260 A restored, no intentional delay, so it is always faster than Q21’s 0.1 s | Primary injection |
| F1 feeder | 250 A moulded case | Instantaneous 10 × In = 2500 A | Unchanged. The minimum fault at its far end on one generator is 5811 A, more than twice the setting | Primary injection, no change made |
| F2 feeder | 400 A moulded case | Instantaneous 10 × In = 4000 A | 6 × In = 2400 A. The phase-to-phase minimum at its far end is 3644 A, which the old setting could not see | Primary injection at 3.6 kA, confirmed tripping |
Read the grading down the fourth column and it comes out as 0 s at the feeders, no intentional delay at sub-board 2, 0.1 s at sub-board 1 and 0.3 s at the main — a 0.2-second margin at the one step where two electronic short-time elements have to be told apart, and simple speed difference everywhere else.
The 0.3 s at Q1 is not a free choice: it has to be long enough to let Q21 clear and short enough that the busbar and the transformer’s LV cable survive 42.3 kA for that long, which is the withstand check the cable study carries at 164.5 mm². Those two constraints meet at about 0.3, and the arc-flash study then has to live with it.
The second row is the setting that only exists because the site has generators. Q1’s short-time element at 6400 A is correct on mains, where the fault level is 42.3 kA — and useless on one generator, where the sustained fault at the main board is 5.2 kA and never reaches the pickup. A second group at 4000 A, selected automatically by source state, restores the element in the mode that needs it most. Without it the main board has no short-time protection at all in single-generator mode, which is both a protection gap and the direct cause of the 14 kA·s arc-flash case.
Two of the as-found entries are the reason site verification cannot be skipped. Q1’s instantaneous element was on, at 20 kA, which on mains means every feeder fault above that figure trips the main at the same instant as the feeder — grading that works perfectly on paper and not at all in the switch room. And Q31 was found at four times rating rather than the two on the drawing, which would have let it sit above sub-board 2’s own minimum fault case. Neither was discoverable from a drawing, a model or a previous report. Both took a laptop and an afternoon at the board.
The last column is the part of the schedule that makes it a record rather than an intention, and the word in it matters. “Primary injection” means current was put through the device and its operation timed; a settings check that reads the display and ticks the row proves that somebody typed the number, not that the breaker trips.
Row seven is the clearest case: the whole point of lowering F2 to 2400 A is that it should now see 3644 A, so the test is an injection at 3.6 kA with a stopwatch on the result. Row six is equally important and reads “no change made” — a device that was already correct still gets tested, because the schedule’s value is that every line on it has been proved, not that every line has been altered.
Common conflicts and how they are resolved
| Conflict | Usual resolution |
|---|---|
| Upstream delay for selectivity exceeds the cable or switchgear withstand | Zone selective interlocking, a larger cable, or a device with a higher short-time rating |
| Generator minimum fault current is below the short-time pick-up | A generator setting group, or a lower pick-up selected when the set supplies the board |
| Motor starting or transformer inrush overlaps the instantaneous setting | Raise the instantaneous above the inrush peak, or add a short delay, checked against damage curves |
| Two devices overlap in the instantaneous region | Maker selectivity tables, a different device pair, or accepted partial selectivity |
| Arc flash energy too high at a board | Maintenance setting, arc detection or busbar differential |
Every compromise that remains is written into the report with its reason and its risk, so the owner accepts it knowingly. See time-current coordination engineering.
Common mistakes
- Copying settings from similar sites.
- No site verification of existing settings.
- Checking the grid case only.
- No record after implementation.
What to send us
Send the single-line diagram, relay and breaker data with present settings, CT ratios and generator data. WhatsApp 98852 01608 or use the enquiry form.
Evidence note. Settings in the example are illustrative; final settings follow the device makers’ curves and the study.
Questions engineers ask
What happens when the generator fault current is below the short time pick-up?
The short time element never operates and the fault is left to the slow long time curve, which can take seconds and raise arc flash energy sharply. The usual cure is a generator setting group, or a lower pick-up selected automatically whenever the set supplies the board, checked against the grid case so selectivity there is not lost.
Should every protection compromise be written into the study report?
Yes. Where full selectivity, damage protection and arc flash limits cannot all be met, the remaining compromise is recorded with its reason, its risk and the operating modes it affects, so the owner accepts it knowingly and the next engineer understands why the settings are as they are.
How long does a coordination study take?
It depends mostly on data collection and site verification, which usually take longer than the calculations. A single board with good data may take days; a large site with several sources, modes and unknown settings can take weeks, including downloading settings, checking device models and testing the final settings.
Can I coordinate without software?
For a few devices in one radial path, yes, by overlaying maker curves on log-log paper and checking margins by hand. For larger systems with several sources and modes, software is far quicker and more reliable, but its results still need checking against maker selectivity tables and hand calculations.
Is full selectivity required?
For critical and life safety circuits, full selectivity is usually required or strongly preferred, so that one fault never drops healthy critical loads. Elsewhere, partial selectivity up to a stated fault current may be acceptable. The study states the level achieved on each path and the reason where it is partial.
When should the study be updated?
Whenever devices, settings, sources, transformers or large loads change, whenever the utility fault level changes, after any unexplained trip, and otherwise at a regular interval, commonly every few years. Each update checks that the installed settings still match the schedule and that the curves still grade in every source mode.
This guide gives general principles. Settings must be verified on site.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.