Lightning and Surge Risk Engineering Guide

How to assess lightning and surge risk for a generator site: risk assessment, air terminals, down conductors, bonding, surge protective devices in zones, controller protection and inspection.

In short. Lightning damage rarely comes from a direct strike alone. Surges travel along power, signal, data and earth conductors into buildings and equipment. A good scheme starts with a risk assessment. It gives lightning a safe path to earth, bonds every service to one earth reference, and protects each point where a conductor enters the building with surge devices matched to that zone.

Who this page is for: For consultants, facility managers and engineers protecting buildings, generator rooms, telecom and control systems from lightning and surges.

Key facts

  • Assess risk from location, structure, contents and consequences of loss.
  • External lightning protection gives direct strikes a safe path to earth.
  • Equipotential bonding stops dangerous voltage differences between services.
  • Surge devices protect every entry: power, data, signal and antenna lines.
  • Separate earth systems connected by long leads create large voltage differences during a strike.
  • Inspect after storms and on a schedule.

Layers of protection

  1. Risk assessment using a recognised method, to decide what level of protection is justified.
  2. External protection: air terminals, down conductors and earth electrodes.
  3. Bonding: all metal services and earth systems connected to one reference.
  4. Surge protection at each entry and zone boundary. See surge protection and lightning and surge device coordination.
  5. Inspection and maintenance.

Worked example: a telecom site with a generator (illustrative)

FindingRiskAction
Tower earth and generator room earth separate, joined only through a long cable armourLarge voltage difference during a strike damages controllersEarths bonded with a dedicated conductor
Surge device on power onlySurges enter through data and alarm cablesSurge devices added on data, alarm and antenna lines
Generator controller damaged twice in two monsoonsExposed through long control cable to the towerSurge protection on control cable at both ends; cable rerouted

No further controller damage was recorded in the following monsoon. Bonding was the most important change. See earthing studies.

Do not fit surge devices on the power supply only. Surges also enter through data, alarm, control and antenna cables, and through separate earth systems that are not bonded together.

Lightning and surge checklist

ItemStatus
Risk assessment done 
External protection and down conductors 
All earths bonded to one reference 
Surge devices on power, data, signal and antenna 
Inspection after storms 

Worked example: how often strikes arrive (illustrative)

A risk assessment estimates how many dangerous events a structure and its incoming services can expect each year. The number of direct strikes is roughly the local ground flash density, in flashes per square kilometre per year, times the collection area of the structure. For an isolated rectangular building of length L, width W and height H, the collection area is about L × W + 6H × (L + W) + π × (3H)².

ItemWorking, ground flash density taken as 5Result
Building 30 × 20 m, 10 m high600 + 60 × 50 + 3.14 × 900 ≈ 6430 m²About 0.0064 km²
Direct strikes to the building5 × 0.0064About 0.032 a year, once in about 31 years
Overhead power line, 1 km longCollection area about 40 × 1000 = 40,000 m²About 0.04 km²
Strikes to the line5 × 0.04About 0.2 a year, once in about 5 years

Strikes near the building, which induce surges in its wiring, are more frequent still. That is why surge damage to controllers and electronics is common on sites that have never had a direct strike. The real assessment uses the local flash density and the full method of the applicable standard, with factors for location, line type and transformers; these figures only show the proportions.

Protection zones and surge device types

The building is divided into zones, each with less surge energy than the one outside it. Every conductor that crosses a zone boundary passes through a surge device or is bonded at the boundary.

Zone boundaryThreatDeviceTested with
Outside to building, at the service entrancePart of a direct lightning currentType 1, lightning current arrester10/350 µs impulse current
Main board to sub-boardsInduced and residual surgesType 28/20 µs current
Sub-board to sensitive equipmentSmall residual surgesType 3, near the equipmentCombination wave
Data, signal and control linesSurges on low-voltage circuitsLine-specific protectorsAs the maker states

Where a building has external lightning protection, or an overhead supply that can carry part of a strike into it, a Type 1 device is needed at the origin. Where neither applies, a Type 2 device at the origin may be enough. The risk assessment decides.

Choosing a surge device

  • Maximum continuous operating voltage: high enough not to conduct during normal voltage swings. On a 230 V phase-to-earth system it is commonly at least 1.1 × 230 ≈ 253 V, and 275 V devices are usual; earthing arrangements where a fault can raise the phase-to-earth voltage need higher values.
  • Voltage protection level: lower than the impulse withstand of the equipment being protected, with margin. Equipment at the origin withstands more than distribution equipment, which withstands more than appliances and electronics.
  • Discharge capacity: chosen from the risk assessment and the zone; higher at the service entrance than inside.
  • Short-circuit rating and back-up protection: the device and its fuse or breaker must withstand the prospective fault current at that point.
  • Earthing arrangement: the connection mode, phase to earth, phase to neutral or neutral to earth, must suit the earthing system.

Why lead length matters

A surge current rises in microseconds, and every metre of connecting lead adds roughly 1 µH of inductance. At a rate of rise of about 1 kA per microsecond, each metre adds roughly 1 kV across the lead. A device with a protection level of 1.5 kV, connected with a total of 1 m of lead, therefore lets about 2.5 kV reach the equipment, more than many electronics withstand. Keep the leads to the device, and from the device to the earth bar, as short and straight as possible, ideally under about half a metre in total, or use a connection that passes the conductor through the device terminals.

Coordinating devices in stages

When a Type 1 and a Type 2 device are installed in stages, the larger device must take most of the energy before the smaller one conducts, or the smaller device is destroyed. Coordination comes from the length of cable between them, often around 10 m, or from a decoupling inductor, or from devices designed by one maker to work together. The device data states how coordination is achieved; the design follows it.

Points that generator sites often miss

  • Surge protection at the generator output and at the changeover, not only at the grid incomer.
  • Protection on the remote start, alarm and communication cables between the generator and the main building.
  • Protection on battery charger supplies, fuel level sensor cables and outdoor enclosure lighting.
  • Bonding of the exhaust stack, fuel tank, fuel pipes and canopy to the earth system.
  • A single bonded earth for the generator, the main building and any tower or mast.

Generator controllers and AMF panels contain electronics with low surge withstand, and they are often connected to the building by long cables. Most lightning damage on generator sites is to these parts, not to the engine or alternator. See earthing system study architecture.

Bonding at the point of entry

Every metal service, water pipes, gas pipes, cable armour, cable trays and data cable screens, is bonded to the main earth bar where it enters the building, with short conductors. Live conductors that cannot be bonded directly are bonded through surge devices at the same point. Bringing all services in at one entry point keeps the bonding conductors short and makes the protection far more effective than bonding at scattered points around the building.

Inspection and records

CheckWhenRecord
Surge device status indicatorsMonthly, and after every stormDevices replaced, with date and location
Back-up fuses or breakers of surge devicesWith the indicator checkAny operation, as evidence of a surge
Down conductors and jointsAnnuallyCondition, corrosion, damage
Earth electrode resistance and bonding continuityAnnually, in the dry seasonMeasured values against the design
Equipment damageAfter every eventWhat failed, where, and which path the surge took

A damage record over several monsoons shows which entries and cables are vulnerable, and is the best guide to where protection must be improved. See GPR, touch and step voltage studies.

One earth reference for everything

During a strike the earth electrode of the struck system rises in voltage, sometimes by tens of kilovolts, for a few microseconds. Any equipment connected between that system and a separate, unbonded earth sees the full difference across its insulation. That is how a strike to a mast destroys a controller in a building fifty metres away.

Bonding every earth system on the site, the building, the generator, the transformer, the mast and any separate instrument earth, into one network with low-inductance conductors removes the difference, so that everything rises together and nothing in between is stressed. A separate “clean earth” for electronics, isolated from the main earth, is an old practice that makes surge damage worse, not better.

After a strike or a damaging surge

Check every surge device indicator and back-up fuse, inspect the down conductors and bonding near the point of strike, test the earth resistance if the electrode was involved, and record each item of damaged equipment with its location and connected cables. The pattern of damage usually shows the path the surge took, and the protection is then improved on that path.

Common mistakes

  • Separate unbonded earth systems.
  • Surge protection on power only.
  • Long, looped surge device leads.
  • No inspection after storms.

What to send us

Send the site layout, earthing details and damage history. WhatsApp 98852 01608 or use the application engineering enquiry.

Evidence note. The example is illustrative.

Questions engineers ask

Are lightning surges more likely through cables than direct strikes?

Usually yes. With an illustrative ground flash density of 5, a 30 by 20 m building 10 m high expects a direct strike about once in 31 years, but a 1 km overhead line feeding it collects strikes about once in 5 years, and nearby strikes induce surges more often still. That is why surge devices on every incoming cable matter so much.

Why must surge device leads be kept short?

Each metre of lead adds about 1 microhenry, and at a surge current rising at about 1 kA per microsecond that adds roughly 1 kV. A device with a 1.5 kV protection level on 1 m of total lead lets about 2.5 kV reach the equipment. Keeping leads under about half a metre, straight and close together, keeps the protection effective.

Does an SPD make the site lightning-proof?

No. A surge protective device limits the surge voltage on the conductors it is connected to, within its rating. Protection depends on the whole system: a risk assessment, external protection where justified, bonding of every service to one earth reference, devices on every entering cable and short connection leads. One device alone protects very little.

Do I need external lightning protection as well?

That depends on the risk assessment, which weighs the strike frequency, the structure, its contents, its occupants and the consequences of loss. Tall or isolated structures, towers, fuel stores and buildings housing critical services often need it. Where external protection is fitted, a Type 1 surge device at the service entrance is also needed.

How often should SPDs be checked?

Check the status indicators monthly and after every storm, and inspect the devices, their back-up fuses or breakers and their connections at least annually. Replace any device whose indicator shows it has failed, and record where and when, because repeated failures at one entry point show where protection or bonding needs improvement.

Why do controllers fail but not the engine?

Controllers, AMF panels and battery chargers contain electronics with low surge withstand, and they are often connected to distant equipment through long control and communication cables that collect surges. The engine and alternator are robust machines. Surge protection on control cables at both ends, and bonding of all earths, protect the electronics.

This guide gives general principles. A lightning protection design must follow applicable standards.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.