In short. Not every load needs backup, and almost no site needs all of it on the generator. Load classification ranks each load by what happens if it loses power, then decides which loads are carried, how fast they come back, in what order, and which are shed when capacity falls. It is the step that sizes the generator, splits the switchboard into essential and non-essential sections, and drives the load-shedding logic, so it comes before equipment is chosen.
Who this page is for: For facility managers, hospital and building engineers, and consultants deciding what a generator must carry and in what order loads return.
Key facts
- Classify by consequence of loss and tolerable outage time, not by connected load.
- Typical tiers: life safety, critical, essential and deferrable.
- Include each load’s auxiliaries (cooling, pumps, controls, communications) in the same tier.
- Restore in steps the generator can accept, largest motors early, while the set is lightly loaded.
- Define the shed order for when a set trips or capacity falls.
- Operations and safety owners decide the consequence; engineering turns it into design.
The tier model
| Tier | Consequence of loss | Tolerable break | Typical supply |
|---|---|---|---|
| Life safety | Risk to people | Seconds, often set by code | Battery-backed escape lighting, plus dedicated generator circuits, tested |
| Critical | Safety, major damage or large loss | None to seconds | UPS, then generator |
| Essential | Operations degrade but recover | Up to a minute or two | Generator after a short delay |
| Deferrable | Comfort or convenience | Hours | Shed when capacity is short |
Method
- Start from the load list. See load list.
- For each load ask: what happens if it stops for a second, a minute, an hour?
- Set its tolerable outage time and tier.
- Add the auxiliaries it depends on to the same tier.
- Sum demand by tier and size the plant with redundancy. See multi-DG capacity.
- Set the restart sequence and the shed order. See load shedding.
- Record the owner and reason for each decision, and review yearly.
Worked example: a hospital wing (illustrative)
The wing has 1200 kW of connected demand. Classification gives:
| Tier | Loads | kW | Return |
|---|---|---|---|
| Life safety and critical | Escape lighting, fire systems, theatres, ICU, medical gases, IT through UPS | 380 | At transfer |
| Essential | Lifts, water pumps, sterilisation, kitchen, cooling for critical areas | 420 | Two blocks of 210 kW, about 15 and 30 s after transfer |
| Deferrable | General comfort cooling, laundry, non-clinical areas | 400 | Shed during generator operation |
The first two tiers need 800 kW, not 1200 kW. With sets rated 400 kW each at site conditions, N = 2 and three sets give N+1. The first step of 380 kW is about 32% of the three running sets; if one set has failed, it is about 48% of the remaining two, which must be inside the engines’ load-acceptance limit.
With one set out, the two remaining sets run at 100%, so any load growth uses up the spare; a larger set size or a fourth set restores margin. If two sets are lost, the logic sheds the essential tier and keeps life safety and critical loads on the one remaining set, about 95% of its rating, connected in steps it can accept.
Do not leave the restart to chance. If every load returns at once after a transfer, the generator can trip on the combined step and the critical loads go down with the rest. Set the order and delays, and test them.
Dependencies
A critical process often depends on an auxiliary left in a lower tier: the cooling for a server room, the pump for a process, the ventilation for a battery room. Many outages come from an unprotected auxiliary supporting a protected load. Trace each critical load’s dependencies and lift them into the same tier.
Restart logic
- Return power in steps within the engines’ load-step limits. See load-step response.
- Start large motors early, while the generator is lightly loaded.
- Block heavy loads until enough sets are online.
- Decide which loads restart automatically and which need an operator.
How it shapes the design
Classification sets the switchboard split into essential and non-essential sections, the number and placement of ATS units, the UPS boundary and the shedding scheme. Doing it after equipment is bought usually means oversized sets or a rewired board.
Load classification register
The register for one installation — a 2000 kVA transformer with two 1250 kVA generators in N+1 and a 400 kVA UPS. The example above classifies a hospital wing of 1200 kW into three tiers and sizes the plant from the first two; this register covers a process site of similar size whose tiers come out quite differently, and whose constraint turns out not to be the alternator at all.
| Load | kW | Tolerable break | Tier | Restart step | Shed order | Decision owner |
|---|---|---|---|---|---|---|
| Critical load through the UPS | 320 | None | Critical | Already live. The UPS carries it through the transfer | Never shed | Operations |
| L-01 process and plant lighting | 70 | 10 s | Essential | Step 1, at transfer | 5th | Safety |
| M-02 process compressed-air plant | 110 | 60 s | Essential | Step 2, largest motor while the set is lightly loaded | 3rd | Operations |
| M-01 chilled water pumps, 2 duty | 90 | 2 min | Essential | Step 3, the second pump 10 s after the first | 2nd | Operations |
| AHU-01 air handling | 162 | 5 min | Essential | Step 4, one fan at a time, 5 s apart | 1st | Operations |
| M-03 cooling tower fans | 88 | 5 min | Essential | Step 5, all four within 20 s | 1st, with the air handling | Operations |
| UPS battery recharge | 45 | Hours | Essential | Step 6, last, once everything else is stable | 4th | Engineering |
| M-04 effluent transfer pump | 75 | Hours | Deferrable | Not restarted on generator | Shed at transfer | Operations |
| H-01 hot water and services | 84 | Hours | Deferrable | Not restarted | Shed at transfer | Facilities |
| W-01 workshop and stores | 60 | A shift | Deferrable | Not restarted | Shed at transfer | Facilities |
| Tier totals | 1104 | — | Critical 320, essential 565, deferrable 219 | Generator mode carries 885 kW | — | — |
The three tiers add to 1104 kW, and the first two add to 885 — which is the generator-mode figure the load schedule arrives at independently, from duty and diversity rather than from consequence. Two different questions, asked in two different documents, giving the same number: that agreement is the check, and when it fails it is almost always because a load has been classed essential without being counted, or counted without being classed.
The constraint is the engine, not the alternator. 885 kW at the site’s measured power factor of 0.933 is 949 kVA, which is 76% of one 1250 kVA set — comfortable. But a 1250 kVA set is rated at 0.8 power factor, so its engine is 1000 kW, and 885 is 88.5% of that.
The set runs out of kilowatts long before it runs out of kilovolt-amperes, and anybody checking only the kVA figure would conclude there was 24% of headroom when there is 11.5%. The tier totals have to be tested against the kW rating on any site whose power factor is better than 0.8, which, with a large rectifier load, most modern sites are.
The fifth and sixth columns are deliberately not the reverse of each other. Restart order is governed by what the engine can accept — the largest motor goes on early, at step 2, while the set is still lightly loaded, and the battery recharge goes last because it is the only load that can wait hours. Shed order is governed by consequence, so the air handling and the cooling tower fans go first despite being restarted late. Writing one list and reversing it produces a scheme that sheds the motor before the fans, which is exactly wrong on both counts.
The last column is the one that makes the register a decision rather than an opinion. The tolerable break for lighting was set by safety, not engineering; the ten seconds in that row is a judgement about evacuation in a process area, and engineering’s job was to deliver it, not to choose it. Equally, the 60 seconds against the motor came from operations, who know what a minute without instrument air costs. An engineer who fills in the third column alone has written a wish list; the register is only binding when each line has a name against it.
How long typical loads can tolerate a break
| Load | Typical tolerance | Usual answer |
|---|---|---|
| Servers, network and control systems | Milliseconds | UPS, then generator |
| Escape lighting and fire alarm | Set by safety rules, often seconds | Battery-backed, plus generator circuits |
| Lifts | Seconds, but people may be trapped | Generator, with at least one lift on the essential supply |
| Cold rooms and freezers | Often hours, set by thermal mass and door discipline | Generator after a delay, with the refrigeration plant restarted in stages |
| Continuous processes | Seconds, but restart may take hours | Decided by the cost of a restart, not the break itself |
| Comfort cooling and general power | Hours | Shed on generator supply |
The tolerance is set with the people who run each area. A process that stops for two seconds may take six hours to restart and lose a batch, so its real tolerance is the restart cost, not the break.
When everything is called critical
A common first answer from each department is that its loads are critical. Putting a cost on each tier usually settles it: critical loads need UPS capacity, generator capacity and redundancy, so every kilowatt moved into that tier has a visible price. Asking what actually happens after one minute, one hour and one day without power, load by load, separates real critical loads from important ones. The result is recorded with the name of the person who decided it, so that later changes are deliberate.
Making the classification visible
Boards, sockets and circuits on essential and critical supplies are marked distinctly, so that staff plug critical equipment into the right sockets and do not load the essential supply with heaters or kettles. The board schedule shows the tier of every circuit. A classification that exists only in a study report is soon undone by new equipment plugged into whichever socket is nearest.
Proving it in a real transfer
The classification is tested by a full transfer to generator at a planned time: the critical tier must ride through on UPS, the essential tier must return in the planned steps, and the deferrable tier must stay off. Any load that behaves differently, or any department that finds something missing, feeds back into the next review. See ATS and transfer system study engineering.
Common mistakes
- Everything on the generator without ranking.
- Forgetting auxiliaries.
- No restart sequence.
- A classification never updated after changes.
What to send us
Send your load list and how long each area can be without power. WhatsApp 98852 01608 or use the enquiry form.
Evidence note. The example is illustrative; life-safety requirements follow the codes that apply to the building.
Questions engineers ask
How long can typical loads tolerate a power break?
Servers and controls tolerate milliseconds and need a UPS; escape lighting and fire alarms follow safety rules; lifts tolerate seconds but may trap people; cold rooms often tolerate hours depending on thermal mass; continuous processes may tolerate seconds but take hours to restart; comfort cooling tolerates hours and is shed on generator supply.
How do you stop every department classing its loads as critical?
Put a cost on each tier. Critical loads need UPS capacity, generator capacity and redundancy, so every kilowatt moved into that tier has a visible price. Asking what actually happens after a minute, an hour and a day without power, load by load, separates truly critical loads from important ones, and the named owner of each decision is recorded.
Who decides the tier?
The people responsible for operations and safety decide the consequence of losing each load, such as clinical, production or security managers. The engineer turns those decisions into tiers, supply arrangements, restart steps and shed order, and records who decided each one and why, so later changes are deliberate.
Why classify at all?
Because carrying every load on the generator and UPS is rarely necessary and very costly. Classification sizes the generator and UPS for what truly matters, sets the restart sequence the set can accept, and defines what is shed first when capacity falls, so the most important loads keep running.
How often should it be reviewed?
At least once a year, and whenever a department changes its use, new equipment is added or an incident shows a gap. Each review checks that the tiers still match the real consequences of loss, that the board schedules agree and that the restart and shed sequences still work.
Do UPS loads need generators?
Usually yes, unless the outage is always shorter than the battery autonomy. The UPS bridges the gap while the generator starts, but only the generator supplies energy for a long outage. The generator must then carry the UPS input, including battery recharge, as part of the critical tier.
This guide gives general principles. Tiers must be agreed with the site owner.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.