In short. Construction and infrastructure sites need power that changes with the work: site offices and tower cranes first, then batching plant and hoists, then building commissioning loads. A sound project plans generator capacity and temporary distribution by work stage, earths and protects every feeder, controls fuel and monitors running hours, and records what was delivered and tested so later claims stay within the evidence.
Power follows the programme
A high-rise in Kokapet, a metro extension, a highway flyover and a water pipeline all need temporary power, but their demand profiles differ and each changes as the work advances. Early stages may need only site offices, labour camp lighting, welding sets and a few pumps. Mid-programme brings tower cranes, passenger and material hoists, concrete pumps and batching plant.
Near completion, the building’s own lifts, chillers and fire pumps need power for testing and commissioning, often before the permanent DISCOM connection is energised. Planning one generator for the whole programme usually means either a large set idling for months or a small set that is overloaded at the peak. A staged plan, typically with rental generators added and removed as stages change, matches capacity to need. Construction and infrastructure power and construction rental generators describe the options.
| Work stage | Typical loads | Power planning focus |
|---|---|---|
| Mobilisation | Site offices, camp, lighting, small tools | Single-phase balance, small set or rental |
| Substructure | Dewatering pumps, piling rigs, welding | Continuous pump duty, monsoon peaks |
| Superstructure | Tower cranes, hoists, concrete pumps, batching | Motor starting, step loads, distribution spread |
| Finishing and commissioning | Building lifts, HVAC, fire pumps, testing loads | Stable voltage, documentation, interface with permanent system |
Sizing for cranes and hoists
Tower cranes and hoists combine large motor starts with regenerative energy during lowering. A generator that easily carries the average site load can still dip enough during a hoist start for the crane’s controls to fault. Inverter-driven cranes reduce the starting step but add harmonic load, and regeneration back into a lightly loaded generator can drive frequency or voltage upward unless the crane has braking resistors. The crane supplier’s power data, not its nameplate kW, should set the requirement.
I = (P × 1000) / (√3 × V × PF)
I is feeder current in amperes, P the feeder load in kW, V the line voltage (415 V) and PF the power factor. Worked example (illustrative): a hoist feeder carrying 45 kW at 0.8 power factor draws about 78 A, so a 100 A protective device and cable rated for the load after grouping and ambient derating would be a starting point, then checked for voltage drop over the actual run length. A 150-metre run to the far end of a site can drop enough voltage to cause motor trouble even if the generator is correctly sized. See cable sizing.
Temporary distribution, earthing and protection
Most construction power incidents happen in distribution, not at the generator. One set often feeds several separate load areas through cables laid across a changing site, which is why distribution panels should be arranged by area or by purpose, with protection matched to each outgoing feeder and residual current protection for hand tools and site lighting.
Every temporary system needs a defined fault return path: the generator neutral and frame earthed, earth continuity carried to each distribution board, and the earth electrode tested before energisation. Cable routes must be protected from vehicles, buried or raised where they cross haul roads, and reviewed as the site layout changes, since a route that was safe last month may sit under a new excavation. Distribution panels and earthing and neutral cover the details.
Fuel, maintenance and monitoring
Construction generators run long hours in dust, heat and vibration, so service intervals arrive sooner than on a standby set and air filters and radiators need more frequent attention. Fuel is both a cost and a control problem: telemetry that records fuel level, running hours and load lets the contractor see whether consumption matches work done and spot losses early. Planning refuelling around the programme also avoids the commonest site outage, which is simply a set running dry over a weekend.
Separating delivery from demonstrated performance
Mobilising and connecting a generator are project activities; they do not themselves prove that the site was continuously powered. A useful project record states the work stage, supported loads, distribution arrangement, tests performed before energisation, operating responsibilities and the duration of the deployment. No approved construction case is presented in this category; future cases will keep to what the records show. Related categories include manufacturing power projects and mining power projects.
How power needs change through a building project
| Phase (illustrative) | Main loads | Typical power arrangement |
|---|---|---|
| Enabling works | Site offices, dewatering pumps, lighting | Small set near the offices, pumps on their own feeder |
| Structure | Tower crane, hoists, batching, welding, tools | Larger set for crane and hoists, separate supply for offices |
| Fit-out | Tools, temporary lighting, hoists, testing | Reduced set size as the crane leaves |
| Commissioning | Building services tests before permanent supply | Set sized for the commissioning loads, with metering |
Planning these changes at the start allows sets to be swapped or released as each phase ends, rather than keeping one large set running lightly for the whole project.
Worked example: a high-rise residential project (illustrative)
During the structure phase, a tower crane with a hoist motor of around 55 kW, two passenger and material hoists of about 15 kW each, a small batching plant of about 30 kW and assorted tools and lighting of about 30 kW may run on site. The crane hoist start is the hardest step.
A set of around 250 kVA, giving 200 kW, covers the running load with margin for the crane start, while site offices run on a separate 30 kVA set so their computers and air conditioning are not disturbed by crane and hoist starts. When the crane is dismantled, the large set is released and a smaller one carries fit-out loads.
From temporary to permanent supply
Near completion, permanent transformers and the building generator arrive, but temporary power often still feeds parts of the site. A clear handover plan states which loads move to the permanent supply and when, how the temporary set is disconnected safely, and how commissioning tests on the building generator are carried out without interrupting work that still depends on the temporary supply.
Night work and safety lighting
Concrete pours and urgent work often run into the night. Area lighting becomes part of site safety, so lighting circuits are separate from tool circuits, protected by their own devices and backed by emergency lighting on escape routes. If the set stops, people can still leave the structure safely.
A site power checklist
- Crane and hoist motor data, including starting method.
- Expected phases and their dates, to plan set changes.
- Location for each set, with access for refuelling and lifting.
- Earthing, residual current protection and cable routes.
- Fuel arrangement and daily log.
- Contacts for breakdown and for releasing sets.
Monsoon on a construction site
Construction sites in Telangana and Andhra Pradesh often work through the monsoon. Sets are placed on raised bases, cable joints are kept off the ground and sealed, and excavations near cable routes are watched for collapse. After heavy rain, insulation and earthing are checked before sets are loaded again.
Worked example: fuel during the structure phase (illustrative)
If the main set averages about 120 kW over a 10-hour working day at roughly 0.28 litres per kWh, it uses about 34 litres an hour, close to 340 litres a day and around 8800 litres over 26 working days. Knowing this lets the contractor plan deliveries and check the daily log for losses.
Neighbours, noise and dust
Urban building sites have neighbours close by. Acoustic sets placed away from homes and offices, exhausts pointed away from windows, and working hours that respect local rules reduce complaints. Keeping sets clear of dust from cutting and batching also protects their air filters and radiators.
Records worth keeping on a construction project
A daily log for each set, recording hours, fuel, load, faults and any moves, supports fuel reconciliation and billing, and shows how site power needs changed through each phase. It also helps plan temporary power on the next project.
Common mistakes
- Sizing one generator for the whole programme. It runs lightly loaded for months, then is overloaded when cranes and batching plant arrive.
- Running long feeders without a voltage drop check. Hoists and pumps at the far end of the site stall or trip even though the generator has spare capacity.
- Omitting residual current protection on tool and lighting circuits. A damaged cable in wet conditions becomes a shock hazard to workers.
- Leaving cable routes unchanged as the site evolves. Vehicles and new excavations damage cables that were safely routed at the start.
What to send us
Send the construction programme with expected stages and durations, the load schedule for each stage including crane, hoist and pump data, a site plan showing distances from the generator location to each load area, and access and fuel arrangements. Send a generator rental enquiry.
Questions engineers ask
How do generator needs change through a building project?
Enabling works need small sets for offices and pumps; the structure phase adds the crane, hoists, batching and welding, needing a larger set; fit-out needs less as the crane leaves; and commissioning needs a set sized for building services tests before permanent supply arrives. Sets are swapped as phases end.
Why should site offices have a separate generator from the crane?
Crane and hoist motor starts cause voltage dips that disturb office computers and air conditioning. In the illustrative high-rise project, a 250 kVA set carries crane, hoists and batching, while a separate 30 kVA set keeps the offices on a steady supply. Each set then runs at a sensible load.
How is temporary power handed over to permanent supply?
With a plan stating which loads move to the permanent supply and when, how the temporary set is disconnected safely, and how building generator commissioning tests run without interrupting work still depending on temporary power. The plan prevents gaps and unsafe switching. It is agreed before the final months begin.
How much fuel does a construction site generator use?
In the illustrative structure phase, a set averaging about 120 kW for ten hours a day at roughly 0.28 litres per kWh uses about 340 litres a day, around 8800 litres over 26 working days, which sets delivery planning and daily log checks. Larger sites scale this up accordingly.
Should a construction site buy or rent its generators?
Rental usually suits construction because demand changes by stage and ends at handover. Purchase can make sense for long programmes with a steady base load, or for contractors who move sets between sites. Compare total cost including maintenance, fuel management and the resale value. Hire first.
What size generator does a tower crane need?
It depends on the crane’s hoist motor rating, its drive type and the other loads on the same set. The crane manufacturer’s power requirement and starting data should be used; a generic multiple of crane kW is not reliable. Drives on the crane need a harmonic allowance too.
How is a construction generator earthed?
The generator neutral and frame are connected to a tested earth electrode, and an earth conductor is carried to every distribution board so faults can clear through the protective devices. Residual current protection is added on final circuits for tools and lighting. Test it weekly.
Can the construction generator be used to commission building services?
Yes, if its capacity, voltage stability and connection arrangement suit the commissioning loads. Commissioning lifts, chillers and fire pumps needs a more controlled supply than general site power, with documented connections and protection. A separate, load-bank tested set for commissioning avoids disturbing site power and gives the services contractors a supply whose voltage and frequency they can rely on.
Generators by rating
- Under 15 kVA generators
- 15–50 kVA generators
- 50–125 kVA generators
- 125–250 kVA generators
- 250–500 kVA generators
- 500–1000 kVA generators
- 1000–2000 kVA generators
- 2000 kVA and above generators
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.