Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

Manufacturing Power Projects

How factory generator projects are scoped around the production sequence, motor starting and step loads, and how downtime and output claims should be evidenced.

In short. A manufacturing generator project succeeds when it keeps the process safe and restartable, not when it matches the plant’s connected kVA. The scope must say whether the generator supports full production, selected lines or only a safe shutdown, and the design must handle motor starts, step loads and non-linear drives. Claims about reduced downtime or higher output need a measured baseline; an energised generator alone proves neither.

Three different scopes that all get called backup power

Factories in the Patancheru, Pashamylaram, Jeedimetla and Medchal industrial areas ask for generators for three quite different purposes, and confusing them is the root of most poor projects. The first is full production continuity, where the generator carries every line through a DISCOM outage. The second is selected-load continuity, where the generator keeps critical utilities running, such as process cooling, compressed air for instruments, furnace holding power or cold rooms, while production lines stop.

The third is safe shutdown and restart, where the generator only needs to bring the process to a safe state and restart it in order. A 2000 kVA plant may need 2000 kVA of generation for the first, 600 kVA for the second and 250 kVA for the third. The production manager, not the electrical contractor, should decide which applies. Manufacturing power describes typical load classes by sector.

ScopeGenerator sized forMain design riskEvidence of success
Full productionRunning load plus largest motor start plus growthCost, low load factor during partial productionLoad test at production load, transfer test
Selected loadsCritical utilities and their starting sequenceWrong loads on the generator busTransfer test with selected loads, segregation check
Safe shutdown and restartShutdown loads, then sequenced restartRestart attempted all at onceRecorded shutdown and restart sequence

Motor starting and step loads

Industrial loads reach the generator as steps: a motor starting, a chiller loading, a press or a mixer engaging. The alternator must hold voltage well enough that contactors stay closed, and the engine must recover frequency before the next step. Turbocharged diesel engines accept load in increments rather than as a single block, so the project must confirm the manufacturer’s load acceptance capability against the plant’s actual starting sequence.

kVA_required ≈ (P_running / PF) + (S_start,largest − S_run,largest)

P_running is the running load in kW that is already connected, PF its power factor, S_start,largest the starting kVA of the largest motor and S_run,largest that motor’s running kVA. Worked example (illustrative): a plant segment running 280 kW at 0.85 power factor has about 330 kVA of running load. If its largest motor is a 75 kW screw-type machine on star-delta, with starting demand around 210 kVA against 90 kVA running, the starting margin is about 120 kVA, giving a requirement near 450 kVA before growth and derating. The result should be confirmed against the alternator’s voltage dip curve before the rating is fixed. See generator sizing.

Drives, harmonics and sensitive equipment

VFDs, induction furnaces, rectifiers and UPS systems draw non-linear currents that distort generator voltage more than they distort the stiffer DISCOM supply. CNC machines and PLCs may react to the resulting voltage distortion or to frequency excursions during step loads. Where non-linear loads form a large share of the generator load, the alternator may need to be oversized or fitted with a permanent magnet excitation system for better voltage stability, and harmonic filters may be justified. A UPS on the controls protects them from the transfer gap; it does not extend generator runtime and does not cover the drives themselves.

Synchronised sets for variable production

Plants whose load swings widely between shifts often benefit from two or more synchronised generators rather than one large set. At night, one set runs at a healthy load factor; during full production, a second set synchronises and shares load. That also allows one set to be serviced while the other covers the critical utilities. The trade-off is a synchronising panel, load sharing controls and protection that must be engineered and tested. Synchronising panels describes the equipment involved.

What a manufacturing project record should prove

A credible record states which production functions were in scope, what the generator was tested to carry, and in what sequence. Claims about downtime need a defined baseline: outage hours before and after, measured on the same basis. A repaired or newly energised generator does not by itself prove an improvement in output; process outcomes outside the power scope stay outside the claim. No approved manufacturing case is presented in this category at present; when one is added, it will follow these rules. Cases from other sectors are listed under verified projects and healthcare power projects.

Worked example: an injection moulding plant (illustrative)

A plastics plant runs eight injection moulding machines, each with heater bands of about 15 kW and a hydraulic pump motor of about 22 kW, plus chillers, a granulator and lighting. Heater bands hold the barrels at temperature and draw steady power; pump motors start when cycles begin. After a power cut, the heaters must recover temperature before production can resume, so a generator that keeps heaters on saves the long warm-up and the scrap that comes with it. A practical plan restores heaters first, then pump motors one machine at a time, then chillers, so the starting steps stay within what the sets can accept.

Putting a value on lost production

Effect of an outageWhat to estimate
Production stoppedOutput lost per hour of downtime
Restart timeWarm-up, purging and setting time after power returns
Scrap and reworkMaterial in process that is spoiled
Equipment riskDamage from sudden stops, such as material freezing in a barrel

These estimates, in the plant own terms, show which loads deserve generator backup and how much redundancy is worth paying for.

Using planned shutdowns for generator work

Factories plan annual or quarterly shutdowns. These are the best times for major generator work: overhauls, switchgear maintenance, protection testing and full-load tests with a load bank. Aligning the generator maintenance plan with the production calendar avoids taking backup out of service while the plant depends on it.

Sizing two synchronised sets for a variable plant

If a plant runs between about 200 kW on a light shift and 550 kW at peak, two sets of 400 kVA, each giving 320 kW, cover the peak together and allow one set to carry the light shift at a healthy load. When one set is in maintenance, the plant runs a reduced schedule. The control system starts the second set when load rises and stops it when load falls, with delays to stop it cycling.

What to record on a manufacturing project

These records show whether the backup arrangement is protecting production as intended, and where it should change.

Power quality for automated lines

Automated lines use PLCs, drives and sensors that react badly to dips and distortion. On generator supply, large motor starts and drive harmonics can upset them. Keeping control power on a small UPS, giving drives line reactors, and restoring large motors only after control systems are stable lets production resume without nuisance trips and resets.

Bringing cooling back after an outage

Process cooling, such as mould temperature controllers, chillers and cooling towers, often has to run before machines can restart safely. Chillers are large loads with demanding starts, so they are restored in stages, and the cooling plan is written into the restart sequence. This avoids machines starting before cooling is ready and keeps the generator steps within limits.

Planning for plant growth

Factories add machines and lines over the years. Leaving space and switchboard positions for an extra set, and reviewing the backup plan whenever a new line is installed, keeps the generators matched to the plant instead of discovering a shortfall during the first outage after an expansion.

A simple annual review of the backup plan against the current machine list keeps that match accurate.

Common mistakes

What to send us

Send the load list with motor ratings and starting methods, the list of drives and other non-linear loads, the production sequence, details of the existing DISCOM connection and transformer, and records of outage frequency and duration over the last year. State whether you need full production, selected loads or safe shutdown. Send a generator sales enquiry.

Questions engineers ask

Which factory loads should restart first after a power cut?

Usually process heating and control systems first, then cooling, then large motors one at a time. In the illustrative moulding plant, heater bands come back first to avoid long warm-ups and scrap, followed by pump motors machine by machine and then chillers. Each step stays within what the sets can accept.

How is the value of generator backup judged in a factory?

By estimating output lost per hour, restart and warm-up time after power returns, scrap and rework from interrupted processes, and the risk of equipment damage from sudden stops. These figures show which loads deserve backup and how much redundancy is worthwhile. Estimates are made in the plant own production terms.

When should major generator work be done in a factory?

During planned shutdowns, when overhauls, switchgear maintenance, protection testing and full-load load-bank tests can be done without leaving the plant unprotected during production. Aligning the maintenance plan with the production calendar avoids taking backup away when it is needed. Temporary rental cover can protect the plant if work must happen outside a shutdown.

How are two synchronised sets sized for a variable factory load?

In the illustrative plant running 200 to 550 kW, two 400 kVA sets of 320 kW each cover the peak together, one carries the light shift at a healthy load, and the controller starts and stops the second set with delays to prevent cycling. Maintenance means a reduced schedule.

How much larger than the running load should a factory generator be?

There is no fixed margin; it depends on the largest motor start, the step-load sequence, the non-linear share and growth. A common starting point is 20 to 25% above running kVA, then checked against the motor starting study and the alternator’s voltage dip curve before the rating is fixed.

Can one generator support two plants on the same premises?

Yes, if the combined load and starting sequence is within its capability and the changeover arrangement keeps the supplies separate from the DISCOM. Separate metering and a clear load priority are needed so one plant cannot overload the set at the expense of the other.

Is a CPCB IV+ generator suitable for heavy industrial loads?

Yes. CPCB IV+ sets use electronically controlled engines and aftertreatment, and their load acceptance is specified by the manufacturer like any other set. Low-load operation needs more attention, because aftertreatment works best at moderate to high load. Plan test runs on real load, and keep the aftertreatment service on schedule.

Should we use one large generator or two synchronised sets?

Two synchronised sets suit plants with variable load and a need for maintenance without losing backup. A single set is simpler and cheaper when the load is steady and a short loss of backup during maintenance is acceptable. Logged load over a normal production week decides which, along with the largest motor start.

Generators by rating

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.

CallWhatsAppEnquire