Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

Generators Under 15 kVA

How to select a diesel generator below 15 kVA for a home, clinic, shop, farm pump or telecom site, covering phase, motor starting, runtime and CPCB IV+.

In short. A generator under 15 kVA is chosen by the hardest load it must start, not by the total wattage of everything connected. In this class a single borewell pump, refrigeration unit or air-conditioner can demand more at start-up than the whole running load, and single-phase 230 V versus three-phase 415 V decides the whole installation. Define the load, the phase, the runtime and whether automatic start is needed, and the right set follows from a short list of candidates.

Where small generators are used

Below 15 kVA the typical buyers in and around Hyderabad are households wanting lights, fans and a lift, clinics and diagnostic centres, shops and small offices, petrol pumps, ATMs, telecom shelters, poultry sheds, dairy chilling points and farms with a borewell. The loads look modest but are rarely resistive, and the set has no spare capacity to absorb a bad assumption.

These sets are usually water-cooled single-, two- or three-cylinder diesel engines at 1500 rpm with a brushless alternator, supplied in a canopy that meets the CPCB noise limit. All new diesel sets up to 800 kW, including this class, must meet CPCB IV+ emission norms, so a new set carries the certification mark and the price reflects the electronic fuel system it needs.

Define the load before looking at catalogues

The load inventory page gives a simple format for listing loads, and it is worth doing even for a 7.5 kVA set.

Why total wattage misleads

A 6 kW resistive load and a 6 kW motor-driven load do not create the same generator requirement. A direct-on-line induction motor draws roughly six to seven times its full-load current for the first second, and a small generator must supply that from an alternator with limited transient capability. Single-phase capacitor-start motors can be worse. A motor that restarts against pressure after a short outage starts under load and takes longer to accelerate.

Load typeStarting behaviourPlanning allowance (illustrative)
Lighting, fans, heatersNo inrush of consequenceRunning kW only
Computers, UPS, LED driversLow start, but nonlinear currentRunning kVA plus margin for waveform distortion
Single-phase borewell pump, 1 to 2 HPCapacitor start, 5 to 7 times running currentStarting kVA of 9 to 12 times motor kW
1.5 ton split air-conditioner, fixed speedMotor starts under pressureStarting kVA of 5 to 7 times running kW
Three-phase pump, 3 to 7.5 HP, DOL6 to 7 times full-load currentStarting kVA of 8 to 10 times motor kW

A set in this class can typically accept a single step of 70 to 100% of its rating if the step is mostly resistive, but a motor start that momentarily demands twice the set’s kVA pulls voltage down far enough to trip electronic loads or stall the motor. The method for checking this is on the motor starting page.

Current, phase and the arithmetic

I = (kVA × 1000) / V for single phase, and I = (kVA × 1000) / (√3 × V) for three phase

Here I is the rated current in amperes, kVA is the generator rating and V is the line voltage, 230 V single-phase or 415 V three-phase in India. A 7.5 kVA single-phase set delivers about 32.6 A, and a 10 kVA three-phase set delivers about 13.9 A per phase (illustrative). The three-phase figure explains a common disappointment: a 10 kVA three-phase set cannot run a 7 kVA single-phase load, because each phase is rated for one third of the total.

If most loads are single-phase, buy a single-phase set, or a three-phase set with a manufacturer-rated single-phase output, and balance the rest. The single-phase generator page explains the trade-offs. Converting kW to kVA uses the power factor, and 0.8 is the usual assumption for a mixed small load, so a clinic with 6 kW of measured demand needs 7.5 kVA of running capacity before any starting allowance.

Runtime, fuel and duty

Small sets consume roughly 0.3 to 0.4 litres of diesel per kWh delivered at useful loads, which is higher per unit than larger engines. A 10 kVA set carrying 6 kW uses around 2 to 2.5 litres per hour (illustrative), so a base tank of 25 to 40 litres gives a working day.

Running a diesel set for long periods below about 30% load causes incomplete combustion, carbon build-up and oil dilution, so a set bought for one 5 HP pump should not idle all day feeding two tube lights. For telecom sites that run many hours a day, ask for the prime rating rather than the standby rating and plan service by hours run, as set out on maintenance planning.

Automatic start and installation

An AMF panel senses loss of DISCOM supply, starts the set, transfers the load after warm-up and transfers back when supply returns. For lifts, clinics and shelters it is worth the cost; for a shop it may not be. The changeover must be interlocked so the set can never feed back into the DISCOM network.

Even a small canopied set needs a level base, clearance for cooling air and service, an exhaust that does not discharge toward a window, an earth electrode connected to the alternator frame and neutral as the supply authority requires, and correctly sized cables with an MCB or MCCB at the set. For a one-off event, see small rental generators.

Single-phase loads on a small three-phase set (illustrative)

SetRated currentCapacity per phase
10 kVA three-phase, 415 VAbout 13.9 A per phaseAbout 3.3 kVA on each phase
10 kVA single-phase, 230 VAbout 43.5 AThe whole 10 kVA on one phase

A house with 4 kW of single-phase load all on one phase overloads that phase of a 10 kVA three-phase set while the other two phases sit nearly idle, even though the total is well under the rating. Either the loads are spread across the three phases at the distribution board, or a single-phase set is chosen. See single-phase generators.

Fuel at the small end

A modern 20 kVA set uses roughly 3.9 to 4.1 litres an hour at three-quarters load and about 5.1 to 5.3 at full load, according to makers’ data. Small sets often run lightly loaded, where consumption per kWh is higher, so a set sized close to the real load, with its largest motor start checked, costs less to run than a larger one bought for safety. A tank of about 50 to 100 litres covers most household and small office outages; longer outages need a refuelling plan.

Generator, inverter or both

NeedBest fit
Lights, fans and computers for short outagesInverter and batteries
Pumps, air conditioners and long outagesGenerator
Sensitive electronics with no break, plus long outagesUPS or inverter backed by a generator

See generator vs inverter vs UPS.

Installing a small set properly

Small sets are often placed wherever there is room: a terrace corner, a parking bay or a balcony. A good position keeps the exhaust away from windows and neighbours, gives the radiator free air, keeps rain off the controls and allows the set to be reached for service. The set needs an earth connection, a changeover that prevents it ever feeding back into the grid, and a cable sized for its current and the run length. For homes and clinics, an AMF panel that starts the set and switches the load automatically removes the need for anyone to be on hand during an outage. See outdoor installation.

Before buying, list every load the set must run together, note which ones start with a motor, and check the largest start against the set rather than adding up nameplates. That short list prevents the two classic mistakes of this class: a set that stalls on the pump, and a set three times too large that runs almost unloaded for years.

Common mistakes

What to send us

Send a list of the loads you want to run together, the rating and starting type of the largest motor, whether the premises have a single-phase or three-phase connection, the hours per day the set will run and a photograph of the proposed location. If you have an existing set, a nameplate photograph tells us the make, rating and phase. Submit it through the generator sales enquiry form and we will recommend a size and a changeover arrangement.

Questions engineers ask

Can a three-phase generator supply single-phase loads?

Yes, if the loads are spread across the three phases. A 10 kVA three phase set offers only about 3.3 kVA on each phase, so 4 kW of single phase load on one phase overloads that phase while the others sit idle. Spread the loads at the distribution board, or choose a single-phase set.

How long does a small generator run on a tank of diesel?

A modern 20 kVA set uses roughly 3.9 to 4.1 litres an hour at three quarters load and about 5.1 to 5.3 at full load, so a 50 to 100 litre tank covers many hours of typical household or small office outages. Longer outages need a refuelling plan and clean fuel.

What size generator do I need for a house with a 1.5 ton AC, a 1 HP pump, lights and fans?

Running load is around 3 kW, but the fixed-speed air-conditioner and the pump both start hard. A 7.5 kVA single-phase set is the usual choice, and 5 kVA is marginal unless the air-conditioner is an inverter type and the pump is not started while it runs (illustrative).

Can a small generator run a computer and a UPS safely?

Yes, if the set is sized for the UPS input, including battery recharge, and has a stable regulator. A UPS draws distorted current that a small set turns into voltage distortion, and some UPS units reject a supply whose frequency wanders. Size with margin, test the UPS on the set, and keep large motor loads off the same set.

Is a 15 kVA diesel generator covered by CPCB IV+?

Yes. New diesel generator sets up to 800 kW, which includes 15 kVA, must meet the CPCB IV plus emission norms, so a new set carries the certification on its nameplate and an electronic fuel system. Check the certificate and the nameplate before buying a set described as new, and keep both with the set records.

Should I choose an air-cooled or a water-cooled engine?

Water cooled engines run quieter, hold temperature better in hot weather and suit long running hours, which is why most stationary sets in this class use them. Air cooled engines are simpler and lighter and suit occasional portable use. For daily outages in a hot climate, water cooled is usually the better choice.

Generators by rating

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.

CallWhatsAppEnquire