Existing Electrical System and Brownfield Study Guide

How to study an existing electrical system before changing it: survey, drawing checks, measurement, condition, rating checks, risk register and a staged plan with minimal downtime.

In short. On an existing site, the drawings are usually wrong somewhere. A brownfield study starts by finding out what is really installed, how it behaves and what condition it is in. Only then can new generators, transfer switches or loads be added without surprises. Most failed upgrades trace back to an assumption about the existing system that nobody checked.

Who this page is for: For facility managers, consultants and contractors planning upgrades, generator replacements or extensions on running sites.

Key facts

  • Collect records first: drawings, load lists, settings, test reports, maintenance and incident logs.
  • Survey the site against the drawings; mark every difference.
  • Measure real loads for at least a week.
  • Assess condition: thermography, insulation, breaker timing, battery tests.
  • Update the single-line diagram before any study.
  • Plan temporary power for the works.

Study stages

  1. Collect records. Drawings, load lists, settings, test reports, maintenance and incident logs.
  2. Site survey. Compare installed equipment, ratings and cables with drawings.
  3. Measure. Load profiles, power quality, generator performance.
  4. Condition assessment. Thermography, insulation, breaker timing, DC systems.
  5. Update drawings. As-found single-line diagram.
  6. Studies and options. Upgrade, replace or retrofit.

Worked example: survey findings before a generator replacement (illustrative)

Drawing saidSite survey foundEffect on the project
Generator feeds the essential board onlyTwo non-essential boards added to the essential board over the yearsReal generator load 30% higher than the load list
Changeover 4-pole3-pole, neutral solidEarth-fault protection review needed
Main cable 300 mm²240 mm² on part of the runCable limits the new generator’s rating
Relay settings as per 2015 sheetSettings changed, no recordFull settings review

The replacement generator size was revised upward, and the cable section was replaced in the same shutdown. See load study and upgrade planning.

Do not size a replacement generator or plan a cutover from old drawings and load lists alone. Survey and measure first; the cost is small compared with discovering the difference on the day of the changeover.

Works planning

Survey difference register

The register from the survey that preceded the whole study programme on one installation: a 2000 kVA transformer with two 1250 kVA generators. The example above lists four differences found before a generator replacement; this register has seven, and it is worth reading as the origin of this section rather than as a list — five of the findings elsewhere in these guides exist because of a line on this sheet.

ItemDrawing saysSite foundImpact
Main board incomer2500 A3200 A, replaced in 2019 with no drawing updateFault study re-run. The making capacity check then found 112 kA against a 105 kA rating
Transformers on the 11 kV boardTwoThree. T3, 630 kVA, added for the services blockEnergisation plan rewritten. Combined inrush 2220 A against a 600 A instantaneous element
Q1 instantaneous elementOffOn, at 20 kACoordination review. The main would trip with any feeder fault above that figure
Q31 sub-board 2 instantaneous2 × In = 1260 A4 × In = 2520 A, no record of the changeGrading restored and the settings schedule reissued
M-02 motor feeder route90 m120 m, re-routed around a new tank bundStarting drop recomputed at 4.0% rather than 3.0%, so 10.4% at the terminals. Cable upsized to 120 mm²
Sub-board 2 phase allocationBalanced across the three phases355, 245 and 225 A at afternoon peakPhase balance survey commissioned. Circuits moved; neutral fell from 121 A to 9
Generator day tanksCommon day tankSeparate tanks, changed in 2021Availability model corrected in the site’s favour. The shared element is the bulk system, not the day tanks
    
    

Seven differences, and the pattern across them is the argument for surveying before studying rather than after. Not one of these was a mistake on the original drawing: every item was correct when it was drawn, and then the incomer was replaced, a transformer was added, a cable was re-routed around a bund, settings were changed and the day tanks were separated. The drawing did not become wrong, it became old — which is a different problem and the reason a study built on it fails in ways nobody can trace back.

Follow two rows forward and the value of the survey is easy to price. The incomer in row one is why the fault study was re-run, and the re-run is what found the making capacity 7 kA short — a finding that only exists because somebody read a rating plate instead of a drawing.

The cable route in row five is 30 m longer than drawn, which took the motor’s starting drop from 3.0% to 4.0% and the total at its terminals to 10.4%, outside the plant’s limit; sizing that cable from the drawing would have put 95 mm² in the ground and left a motor that struggles to start on one generator for the life of the installation.

Row seven is the one worth keeping on the sheet for its own sake, because it moved the answer the other way. The drawings showed a common day tank, which would have made the two generators far less redundant than they are; the site has had separate tanks since 2021 and nobody updated the record. A register that only collected bad news would have quietly left the availability model pessimistic, and a pessimistic model is not a safe one — it would have argued for spending money on fuel separation that had already been spent.

One practical note on how the register was built. Every line has a drawing reference and a photograph behind it, and the four settings rows were read off the devices rather than from a previous report. That is the difference between a survey and a walk round: a walk round finds the extra transformer, because it is a large object in a room. Only a settings download finds Q31 at four times rating instead of two, and only a measurement over a working day finds 355 A on one phase of a board the drawing calls balanced.

Condition tests and what each reveals

TestRevealsNotes
Infrared thermographyLoose or corroded joints, overloaded conductors, unbalanceDone with the board under substantial load, ideally at least about 40%
Insulation resistanceDeteriorated cable or winding insulationTrend over years matters more than one reading
Contact resistanceWorn breaker and switch contacts, poor busbar jointsCompared between phases and with the maker’s values
Breaker trip test by primary or secondary injectionWhether protection trips at its setting and in timeOld breakers often trip late, or not at all, after years without operation
Battery capacity testReal capacity of tripping and starting batteriesA battery that shows full voltage may still fail under load
Earth electrode and continuity testsEarth resistance and bonding integrityDone in the dry season for the worst case
Transformer oil testsMoisture, breakdown strength and dissolved gasesGas analysis shows internal overheating or arcing early

Where to measure, and for how long

Place power quality analysers at the main incomer, at each board that will be affected by the project, and at the generator output during a test run at realistic load. Record for at least a full week covering all shifts, and through any known peak such as month-end production or summer cooling. Record voltage, current, kW, kVAr, power factor, harmonics and events. A week of data shows the real maximum demand, the unbalance between phases, the harmonic content and the dips the site already experiences, all of which change the design.

Retain, retrofit or replace

FindingUsual decision
Equipment in good condition, ratings adequate, spares availableRetain, with updated settings and labels
Busbars and enclosure sound, breakers obsolete or wornRetrofit new breakers or protection relays into the existing board
Fault rating below the new fault levelReplace, or limit fault current by design
Poor condition, no spares, no maker supportReplace within the project

Retrofitting keeps the busbars and cabling, shortens the shutdown and costs less, but only if the board’s fault and temperature ratings still suit the new duty. See brownfield power control modernisation and integration.

Working safely during the survey

Surveys of old installations often happen without current arc flash labels, with unknown settings and with boards that cannot easily be isolated. Treat every board as hazardous until the study shows otherwise. Limit live work to what is essential, such as voltage and current measurements with suitable instruments and personal protective equipment, under a permit. Opening covers, removing shrouds and tracing cables are done with the circuit isolated wherever the site can allow it. See arc flash study architecture.

Planning the cutover

  • A step-by-step switching sequence, reviewed by the site and the contractor together.
  • Temporary supply for loads that cannot stop, sized from the measured demand, not the old load list.
  • Hold points where tests must pass before the next step starts.
  • A rollback plan that returns the site to its original state if a step fails.
  • Named people for each switching operation, with communication agreed in advance.

Most brownfield incidents happen during the cutover, not in the design. A written sequence with hold points and a rollback turns a risky day into a controlled one.

What the site should have at the end

An as-built single-line diagram, an updated load list, a settings schedule with old and new values, test records, arc flash labels for every board, and a register of the survey differences and how each was resolved. These documents become the starting point for the next project, so that it does not need to survey the whole site again.

Common mistakes

  • Trusting old drawings.
  • No load measurement.
  • Condition of switchgear assumed.
  • No temporary power plan.

What to send us

Send whatever records exist and what you plan to change. WhatsApp 98852 01608 or use the application engineering enquiry.

Evidence note. Findings are illustrative.

Questions engineers ask

Which condition tests matter most before upgrading an existing installation?

Thermography under substantial load to find hot joints, breaker trip tests by injection to prove protection still works, contact and insulation resistance, battery capacity tests for tripping and starting supplies, earth electrode tests, and oil tests on transformers. Old breakers that have not operated for years often trip late or not at all, which only a trip test reveals.

When should old switchgear be retrofitted rather than replaced?

When the busbars and enclosure are sound and their fault and temperature ratings suit the new duty, but the breakers or relays are worn or obsolete. Retrofitting new breakers or relays keeps the cabling, shortens the shutdown and costs less. Where the fault rating is too low or the board is in poor condition with no support, replacement is the right decision.

Why survey if we have drawings?

Because drawings record the installation as it was when drawn, and running sites change: breakers replaced, loads added, cables rerouted and settings altered without the drawing being updated. A study built on old drawings gives confident but wrong answers. The survey finds the differences before they cause a failed upgrade or an unsafe isolation.

How long should measurement run?

At least a full week covering every shift and operating pattern, and longer if the site has monthly or seasonal peaks. Measurement should also include the generator during a test run at realistic load. Short measurements on one day usually miss the true peak, the worst unbalance and the dips the site already experiences.

Can we upgrade without a shutdown?

Often partly. Temporary generators, phased cutovers, bypass arrangements and work during low-load periods can keep critical loads supplied. Some steps, such as replacing a main busbar, still need a shutdown, so the plan schedules them, provides temporary supply where needed and keeps the outage as short as possible.

What if equipment is obsolete?

Check whether spares and support are still available and whether its ratings still suit the new duty. Where the enclosure and busbars are sound, retrofitting modern breakers or relays is often the best value. Where ratings are inadequate or the condition is poor, replace it within the project rather than in a separate shutdown later.

This guide gives general principles. Work must follow site safety rules and regulation.