In short. A transformer’s percentage impedance sets the largest current it can pass into a short circuit on its secondary: the lower the impedance, the higher the fault current. A quick rule gives a slightly high, and so safe, answer for an LV board: fault current ≈ rated current ÷ per-unit impedance. Three details then decide whether switchgear is rated correctly: the impedance tolerance, transformers running in parallel, and the X/R ratio that sets the peak current.
Who this page is for: For consultants, panel builders and plant engineers checking LV fault levels and switchgear ratings below a distribution transformer.
Key facts
- Secondary fault current ≈ rated current ÷ (Z% ÷ 100), assuming a strong source.
- Rated LV current at 415 V ≈ 1.391 A per kVA: about 1391 A per 1000 kVA.
- Impedance has a manufacturing tolerance, often around ±10%; use the low end for maximum fault current.
- Two transformers in parallel roughly double the fault level on a shared bus.
- In a Dyn11 transformer, LV earth-fault zero-sequence current circulates in the delta and does not reach the HV lines, so HV earth-fault relays do not see LV earth faults.
- Higher impedance means lower fault current but more voltage drop and harder motor starting.
Reading the nameplate
| Item | Meaning |
|---|---|
| Rating (kVA) and voltage ratio | Sets rated currents on each side |
| Impedance (Z%) | Primary voltage needed to drive rated current into a shorted secondary, as a percentage of rated voltage |
| Vector group (for example Dyn11) | Phase shift and zero-sequence behaviour |
| Tap range and position | Changes the ratio and slightly the impedance |
Typical impedance and fault multiple
| Z% | Fault current as a multiple of rated current | Typical ratings (indicative) |
|---|---|---|
| 4 | 25 | Smaller distribution transformers |
| 5 | 20 | Around 500 to 1250 kVA |
| 6 | 16.7 | Around 1250 to 2500 kVA |
| 8 | 12.5 | Larger units |
Always use the nameplate or test report; the table is a sense check.
Worked example: one transformer, then two in parallel (illustrative)
A plant has a 1600 kVA, 6% transformer and plans a second identical unit on the same bus with a normally closed coupler. The LV board is rated 50 kA.
| Case | Working | LV fault current |
|---|---|---|
| Rated current | 1600 × 1.391 | About 2226 A |
| One unit, nominal impedance | 2226 ÷ 0.06 | About 37.1 kA |
| One unit, impedance 10% low (5.4%) | 2226 ÷ 0.054 | About 41.2 kA |
| Two units in parallel, low tolerance | 2 × 41.2 | About 82 kA, before source impedance and motors |
One transformer sits inside the 50 kA rating; two in parallel are far beyond it. The choices are to run the coupler normally open with an interlock that prevents both incomers and the coupler being closed together, to use higher-impedance transformers, or to buy switchgear rated for the parallel case. See utility fault level for adding the source impedance.
A board that is safe with one transformer can be dangerously under-rated when a second is paralleled, even briefly during a changeover. Check the parallel case, or prevent it with interlocks.
Tolerance and X/R
Use the lower bound of impedance for maximum fault current and the upper bound for minimum. Larger transformers have higher X/R, which raises the DC offset and the peak current that breakers must make and busbars must withstand. Use the transformer maker’s X/R data where available.
Vector group and earth faults
In a delta-star transformer with an earthed star, zero-sequence current from an LV earth fault circulates in the delta and does not appear as zero-sequence current on the HV side. HV earth-fault protection therefore does not see LV earth faults directly, which is why LV earth-fault protection and restricted earth-fault schemes matter. See transformer protection.
Generator-fed transformers
When a generator feeds the transformer, the generator’s reactance adds to the transformer’s and the fault current is far lower than from the grid. Run both cases, because the lower one decides whether protection trips in time. See generator short-circuit contribution.
Using the rule as a sense check
If software reports 60 kA on the LV board of a single 1600 kVA, 6% transformer, something is wrong: the rule says about 37 kA (about 41 kA at low tolerance); the source and cables only lower it, and motor contribution adds a few kA at most. Check the model for a wrong impedance base or a duplicated source.
Transformer fault-level worksheet
| Item | Value |
|---|---|
| kVA, voltage ratio and vector group | |
| Z% (nameplate or test) and tolerance | |
| Rated LV current (A) | |
| Fault current, one unit, low tolerance (kA) | |
| Fault current with parallel units (kA) | |
| Switchgear rating and interlocks |
From percentage impedance to ohms (illustrative)
Percentage impedance is easy to compare between transformers, but a study needs ohms on one voltage side, or per-unit values on one common base. The base impedance on a side is the line voltage squared divided by the rating.
| 1000 kVA, 6%, 11 kV / 415 V | Working | Result |
|---|---|---|
| Base impedance, LV side | 0.415² ÷ 1.0 | About 0.172 Ω |
| Transformer impedance, LV side | 0.06 × 0.172 | About 10.3 mΩ |
| Base impedance, HV side | 11² ÷ 1.0 | 121 Ω |
| Transformer impedance, HV side | 0.06 × 121 | About 7.26 Ω |
| Check by the ratio squared | 10.3 mΩ × (11 ÷ 0.415)² | About 7.26 Ω: the same impedance seen from the other side |
Most errors in hand calculations come from mixing sides or bases: an impedance in ohms on the 11 kV side added to cable ohms on the 415 V side gives nonsense. Convert everything to one side, or to per unit on one base, before adding.
Impedance is a trade-off, not just a fault number
A low impedance keeps the secondary voltage stiff, so voltage drop under load and dips during motor starts are small, but the fault current rises and so does the cost of switchgear. A high impedance limits fault current but makes voltage drop and motor starting worse.
At full load and a power factor of 0.85, a 6% transformer whose impedance is mostly reactance drops roughly 1 × 0.85 + 5.9 × 0.53 ≈ 4.0% from no load to full load, before the tap is used to correct it. Choosing a transformer therefore balances the switchboard fault rating against the voltage performance the loads need, and the choice is made with both studies in view.
Worked example: X/R and the peak current (illustrative)
The peak current in the first half cycle is about κ × √2 times the initial symmetrical current, where κ is about 1.02 + 0.98 × e−3 ÷ (X/R). Larger transformers have higher X/R ratios, so their peak is a larger multiple of the rms value.
| X/R | κ | Peak as a multiple of rms | Peak for a 37.1 kA board |
|---|---|---|---|
| 4 | About 1.48 | About 2.10 | About 78 kA |
| 8 | About 1.69 | About 2.40 | About 89 kA |
The breaker’s making capacity and the busbar’s peak withstand must cover the peak, not the rms value. An X/R value assumed too low understates the peak by about 11 kA in this example, which can be the difference between a pass and a fail.
Load sharing between parallel transformers
Transformers in parallel share load in inverse proportion to their impedances. Two 1600 kVA units, one at 6% and one at 5.4%, carrying 2400 kVA together, share it as 1600 ÷ 6 ≈ 267 against 1600 ÷ 5.4 ≈ 296. The lower-impedance unit takes about 1263 kVA, 79% of its rating, and the other about 1137 kVA, 71%. The pair cannot be loaded to 3200 kVA without overloading the lower-impedance unit first.
Parallel operation also needs the same voltage ratio, the same vector group and the same tap position. A ratio difference drives a circulating current even at no load: with 0.5% difference between two 6% units, the circulating current is about 0.005 ÷ (0.06 + 0.06) ≈ 4% of rated current, flowing all the time and heating both units. A different vector group gives a phase displacement that acts as a short circuit and must never be paralleled.
Earth fault current on the LV side
For a delta-star transformer with its LV star point solidly earthed, the earth fault current at the LV terminals is close to the three-phase fault current, and can slightly exceed it, because the zero-sequence impedance of the transformer is close to its positive-sequence impedance. Further from the transformer, earth fault current falls faster than three-phase current, because it returns through the protective earth conductor, whose impedance adds to the phase conductor. The earth fault level at the far end of each final circuit is what decides whether its protection disconnects within the required time. See earthing system study architecture.
When a transformer is replaced or added
| Check | Why |
|---|---|
| LV fault current and peak | A larger or lower-impedance unit raises both |
| Busbar and breaker ratings | Breaking, making and short-time withstand |
| Vector group | Parallel operation and earth fault behaviour |
| Tap range and position | Voltage at light and full load |
| Protection settings | HV relay, LV incomer and earth fault settings |
| Arc flash study and labels | Incident energy follows fault current and clearing time |
Ask the maker for the routine test report of the actual unit: measured impedance at the principal tap, load losses, which give the resistance and so the X/R ratio, and the vector group. Values from a catalogue are typical; the test report is the unit. See short-circuit study architecture.
Common mistakes
- Ignoring impedance tolerance.
- Forgetting the parallel case during changeover.
- Using a different tap’s data.
- Trusting a software result that fails the sense check.
What to send us
Send transformer nameplate photographs or test reports, the switchboard rating and the single-line diagram. WhatsApp 98852 01608 or use the enquiry form. See also transformer sizing.
Evidence note. Tolerances and typical values are indicative; nameplate and test-report data govern.
Questions engineers ask
How do two parallel transformers with different impedances share load?
In inverse proportion to their impedances. Two 1600 kVA units at 6 and 5.4% carrying 2400 kVA share it as about 1137 and 1263 kVA, so the lower impedance unit reaches its rating first and the pair cannot carry 3200 kVA. Ratios, vector groups and tap positions must also match, or circulating current flows even at no load.
How much does X/R change the peak fault current of a transformer?
The peak is about kappa times the square root of two times the rms fault current, with kappa rising with X/R. At X/R 4 the peak is about 2.10 times the rms value and at X/R 8 about 2.40 times, so a 37.1 kA board sees about 78 or 89 kA. Making capacity and busbar peak withstand must cover the higher figure.
Why does a higher %Z reduce the fault current?
Because the percentage impedance is the voltage needed to drive rated current through the shorted transformer. With a higher impedance, the full system voltage drives fewer multiples of rated current into a fault. A 6% unit allows about 16.7 times rated current from a strong source; an 8% unit allows about 12.5 times.
Is the quick formula exact?
No. Dividing rated current by per unit impedance assumes an infinitely strong source and ignores cables, motors and voltage factors. It slightly overstates the fault current at the LV terminals, which makes it a safe sense check for ratings, but a study adds the source impedance, motor contribution, tolerance and the applicable calculation method.
How does the vector group matter?
It sets the phase shift between primary and secondary, which must match for parallel operation, and the path for zero sequence current. In a delta star transformer, an LV earth fault current circulates in the delta and is not seen as earth fault current on the HV side, so LV earth faults need their own protection.
Should I use nameplate or test values?
Use the routine test report of the actual unit where it exists, because it gives the measured impedance at the principal tap and the load losses, from which the resistance and X/R ratio follow. The nameplate value is acceptable for screening. Catalogue or typical values are only for early design and must be marked as assumed.
Values are illustrative. Use actual data for studies.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.