In short. A cable is correctly sized only when it passes every test, not just the ampacity table. It must carry the design current after derating, keep voltage within limits both running and during motor starting, survive the fault until protection clears, and carry enough earth-fault current to make the protection operate in time. On generator supply the last two get harder, because fault current is lower, and long runs from rental sets make the voltage-drop and earth-fault checks the ones that usually decide the size.
Who this page is for: For consultants, contractors and plant engineers running cable-sizing studies across a site, especially where feeders are long or fed from generators.
Key facts
- Design current: I = P ÷ (√3 × V × PF × efficiency).
- Voltage drop: ΔV ≈ √3 × I × L × (R cos φ + X sin φ), with L in km.
- Motor starting draws about 6 times running current at a power factor around 0.3; check the drop separately.
- Short-circuit withstand: S ≥ I × √t ÷ k.
- Earth-fault loop: the protective device must see enough current to disconnect in the required time, especially on generator supply.
- Parallel cables must match in length, size and type, and their currents should be measured at commissioning.
The study sequence
- Design current for each circuit.
- Installation method: tray, conduit, buried, duct, grouped.
- Ampacity after correction for ambient, grouping and soil. See ambient derating.
- Voltage drop at running and starting current.
- Short-circuit withstand at the maximum fault and clearing time.
- Earth-fault loop at the minimum fault, including generator supply.
- Mechanical and environmental checks: bend radius, fire performance, UV and oil.
- Terminations and a growth allowance.
Worked example: a 90 kW pump 180 m from a generator-backed board (illustrative)
A 90 kW pump at 415 V, power factor 0.88 and efficiency 0.94 draws about 151 A. Copper cable data at operating temperature: 70 mm² R about 0.32, X about 0.075 Ω/km; 120 mm² R about 0.196, X about 0.072 Ω/km.
| Check | 70 mm² | 120 mm² |
|---|---|---|
| Ampacity after derating | Passes | Passes |
| Running drop (151 A, PF 0.88) | About 14.9 V, 3.6% | About 9.8 V, 2.4% |
| Direct-on-line starting drop (about 905 A, PF 0.3) | About 47 V, 11.4%, plus the generator’s own dip | About 36 V, 8.7%, plus the generator’s dip |
| Soft-start drop (about 3 times running, PF 0.3) | About 5.7% | About 4.3% |
Ampacity alone would pick 70 mm². The starting check rules out a direct-on-line start on either size when the generator’s own dip is added. The study chooses a soft starter with 120 mm² cable (95 mm² only if it also passes the running and starting checks), and then checks the earth-fault loop on generator supply, where the lower fault current must still trip the feeder breaker in time. See motor starting studies.
Do not stop at the ampacity table. On long runs and generator supplies, the starting voltage drop and the earth-fault loop decide the cable size far more often than the current rating.
Short-circuit withstand
S is the conductor area in mm², I the fault current in amps, t the clearing time in seconds, and k a constant for the conductor and insulation (about 143 for copper with XLPE, about 115 for copper with PVC). Check with the maximum fault current for energy, and confirm the clearing time at the minimum fault current. See cable protection and coordination.
Generator-fed and temporary circuits
Rental sets are often placed far from the board. Include the generator’s impedance in the drop calculation, and check that its lower fault current still trips the remote breaker quickly. Temporary cables are handled, weathered and reconnected many times: inspect and test them on every deployment. See rental power.
Parallel conductors
Parallel runs must be the same length, size, type and termination, and laid so they share current. A mismatch can overload one conductor while the total looks fine. Measure each conductor’s current at commissioning.
Harmonics and neutrals
Non-linear loads add heating and third-harmonic current in the neutral, which can exceed phase current. A full-size, or larger, neutral may be needed. See harmonics.
Keeping a cable register
For larger sites, a register of every circuit (size, length, route, protective device, test results and date) makes later studies and fault-finding far quicker.
Cable study sheet
Four circuits on one installation — a 2000 kVA transformer with two 1250 kVA generators in N+1, carrying 885 kW in generator mode — each taken through the same five checks. The example above compares two sizes for one 90 kW pump 180 m from its board; this sheet puts four different circuits side by side on a larger site, and the comparison across them is the finding — only one of the four is decided by its running drop, and none of the four is decided by ampacity.
| Circuit | Design current (A) | Size and length | Running drop (%) | Starting drop (%) | Fault and earth-fault loop checks |
|---|---|---|---|---|---|
| M-02 motor, 110 kW, PF 0.88, efficiency 0.94 | 185 | 95 mm², 120 m | 2.3 | 4.0 soft started, plus the set’s own 6% dip gives 10.4 at the terminals | Withstand at 42.3 kA for 0.05 s needs at least 83 mm²: passes. Loop checked on one generator |
| M-02 motor, the size chosen | 185 | 120 mm², 120 m | 1.9 | 3.5 soft started, so 9.9 at the terminals — inside the 10% limit | Withstand needs at least 83 mm²: passes with margin |
| M-01 chilled water pump, 45 kW, PF 0.86, efficiency 0.93 | 78 | 35 mm², 60 m | 1.1 | 1.0 star-delta | Withstand at 14 kA for 0.05 s needs at least 28 mm²: passes |
| AHU-01 board feeder, 180 kW at PF 0.85 | 295 | 185 mm², 45 m | 0.8 | Largest single fan start adds about 0.3 | Withstand at 31 kA for 0.1 s needs at least 86 mm²: passes |
| U-01 UPS input, 365 kW at PF 0.99 | 513 | 2 × 185 mm², 30 m | 0.4 | No motor start on this circuit | Withstand at 42.3 kA for 0.1 s, each conductor carrying half, needs at least 59 mm²: passes. Parallel runs matched in length and type, currents to be measured at commissioning |
The first two rows are the whole study. The motor draws 110,000 divided by 1.732 times 415 times 0.88 times 0.94, which is 185 A, and 95 mm² carries that comfortably after derating. Its running drop is 1.732 times 185 times 0.120 km times the quantity R cos φ plus X sin φ — with 95 mm² at 0.247 and 0.074 Ω/km and a power factor of 0.88, that bracket is 0.253, and the drop is 9.7 V or 2.3%. Perfectly acceptable.
Then the starting check: soft started at three times running, 555 A at a power factor near 0.3, the bracket becomes 0.145 and the drop is 16.7 V or 4.0%. Add the generator’s own 6% dip and the motor sees 10.4% at its terminals, which is outside the plant’s 10% limit. Going to 120 mm² takes the cable’s share from 4.0% to 3.5% and the total to 9.9%, and that 0.5% is the entire reason the site has 120 mm² in the ground.
That sequence is why ampacity is never the answer on a generator-backed circuit. All four circuits here pass ampacity at a size smaller than the one installed. What decides each of them is a different check: M-02 by the combined starting case, M-01 by nothing at all — it is comfortable on every check and 35 mm² is the minimum that passes withstand — the AHU feeder by its withstand duty, and the UPS feeder by the physical practicality of two parallel runs rather than any electrical limit.
The last column is the one most often left as a tick, and it carries two separate checks. Short-circuit withstand is the current at that point times the square root of the clearing time, divided by k — so the motor cable, exposed to 42.3 kA for the 0.05 s its instantaneous element takes, needs at least 83 mm², and the 185 mm² AHU feeder is sized by its 31 kA for 0.1 s rather than by its 295 A of load.
Note what changes between rows three and one: the pump cable sits behind a sub-board at 14 kA and needs only 28 mm², so the same clearing time against a fifth of the current allows a cable a third of the size. The earth-fault loop check is the second half, and on this site it has to be done on one generator rather than on mains, because that is the condition in which the loop impedance is highest and the available current lowest.
The UPS row carries the check that is easiest to forget on parallel conductors: each of the two 185 mm² runs carries about half the fault current, so the withstand calculation uses 21 kA rather than 42.3 and comes out at 59 mm², again rounded up. That is only true if the two runs genuinely share, which is why the row ends with a commissioning action rather than a calculation. Parallel cables that differ in length or route do not share, and the one carrying more does so permanently and invisibly.
One habit makes a sheet like this reusable: the design current is written with the power factor and efficiency that produced it. 185 A is not a property of a 110 kW motor; it is the consequence of 110 kW at 0.88 and 0.94, and a different motor of the same rating will give a different figure. A cable register that records only “110 kW, 120 mm²” cannot be rechecked when the motor is replaced, which is the moment it most needs rechecking.
Voltage drop limits commonly used
| Installation supplied from | Lighting circuits | Other circuits |
|---|---|---|
| Public low-voltage network | About 3% | About 5% |
| Own transformer or generator | About 6% | About 8% |
These are common reference values for the total drop from the origin of the installation to the load, under normal running. Project specifications are often tighter, and motor starting is checked separately against the dip the motor and the other loads can accept. On generator supply the generator holds its own terminal voltage, so the drop is counted from the generator terminals.
Common mistakes
- Stopping at ampacity.
- Ignoring the starting case.
- No derating for grouping and summer ambient.
- Earth-fault loop checked on grid supply only.
What to send us
Send the cable schedule with lengths, the load list and the source data. WhatsApp 98852 01608 or use the enquiry form. For a single circuit, use the cable screening calculator.
Evidence note. Cable data are typical values for illustration; use the cable maker’s data and the applicable standard’s tables.
Questions engineers ask
What voltage drop limits are commonly used for cables?
Common reference values for the total drop from the origin to the load are about 3% for lighting and 5% for other circuits on a public low voltage supply, and about 6 and 8% where the installation has its own transformer or generator. Project specifications are often tighter, and motor starting is checked separately.
Where is voltage drop counted from on generator supply?
From the generator terminals, because the regulator holds the terminal voltage at its setting. The drop through the generator cable, main board and feeders to the load is then added. Long runs from rental sets or remote generator rooms often make voltage drop, not current rating, the check that decides the cable size.
What voltage drop is acceptable?
Common reference values for the total drop are about 3% for lighting and 5% for other circuits on a public supply, and about 6 and 8% with a private transformer or generator. Project specifications and sensitive loads often require less, and motor starting dips are checked separately.
Is aluminium acceptable?
Yes for many feeders, with a larger cross section than copper for the same current, typically about one size or more larger. Terminations need lugs and procedures suited to aluminium, correct torque and periodic checks, because poor aluminium joints are a common cause of overheating.
Why does the earth-fault loop matter?
Because the protective device must see enough earth fault current to disconnect within the required time, or exposed metalwork can stay at a dangerous voltage. Long cables and generator supply raise the loop impedance and lower the current, so the loop check often decides the cable or protective conductor size.
Do I need a cable register?
Yes on any site with more than a few feeders. A register lists each cable with its size, length, route, installation method, protection and checks, so that a later change, such as a larger load or a new source, can be checked quickly without surveying the whole installation again.
Values are illustrative. Follow the applicable standards for ratings and factors.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.