Cable Size and Voltage Drop Calculator

How to screen cable size for current rating, voltage drop and short-circuit withstand, with a worked example, correction factors and the point at which a full design is needed.

In short. A cable must pass three checks, and the hardest one sets the size. It must carry the load current without overheating after correction for its installation. It must keep the voltage drop within limits at full load and during motor starting. And it must survive the fault current until the protection clears it. This calculator screens current-carrying capacity and steady-state voltage drop for a three-phase circuit; prospective fault current, protective-device clearing time, cable short-circuit withstand and motor-starting voltage drop are checked separately, and final selection follows the cable maker’s data and the applicable standard.

Who this page is for: For electricians, contractors and engineers who need a quick, defensible first size for a generator, motor or feeder cable before detailed design.

Key facts

  • Three checks: current rating after correction, voltage drop, and short-circuit withstand.
  • Three-phase load current: I = P ÷ (√3 × V × PF × efficiency).
  • Voltage drop ≈ √3 × I × L × (R cos φ + X sin φ), with R and X in ohms per km and L in km.
  • Many designs limit running voltage drop to about 3 to 5%; motor starting is checked separately.
  • Short-circuit withstand: minimum area S = I × √t ÷ k.
  • On generator supply, cable drop adds to the generator’s own voltage dip at motor start.

The three checks

CheckQuestionUsually governs when
Current ratingCan the cable carry the design current after correction for ambient, grouping and installation?Short, heavily loaded runs in hot or crowded trays
Voltage dropIs the drop within limits at full load and during motor starting?Long runs, motor feeders, generator supplies
Short-circuit withstandCan the cable survive the fault until the protection clears it?Short runs close to a strong source with slow clearing

Step 1: design current and current rating

I = P ÷ (√3 × V × PF × η) for a three-phase load

A 75 kW motor at 415 V with a power factor of 0.88 and efficiency of 0.93 draws 75,000 ÷ (1.732 × 415 × 0.88 × 0.93) ≈ 128 A. The cable’s tabulated rating applies to reference conditions. Multiply it by correction factors for the real installation, and the corrected rating must exceed the design current and the protective device setting.

ConditionTypical correction factor (indicative; use the standard’s tables)
Air at 45 °C instead of 30 °C, XLPE cableAbout 0.87
Four circuits touching on one trayAbout 0.65 to 0.75
Buried in dry, high-resistivity soilCan fall well below 0.8; depends on soil thermal resistivity
Cable in conduit or closed trenchLower than open tray; check the installation method

In Hyderabad’s summer, cables in outdoor trays and roof runs routinely see 45 °C or more, so use the hot-weather factor, not the reference rating.

Step 2: voltage drop at full load and at starting

ΔV ≈ √3 × I × L × (R cos φ + X sin φ) · ΔV % = ΔV ÷ V × 100

R and X are the cable’s resistance and reactance per kilometre at operating temperature, from the maker’s table. Steady-state drop is often limited to about 3 to 5% at the load end, depending on code and equipment. Motor starting is checked separately, because current is several times higher at a low power factor.

Worked example: a 75 kW motor 120 m from the panel (illustrative)

QuantityRunningDirect-on-line start
Current128 A at PF 0.88About 6 × 128 ≈ 770 A at PF about 0.3
Cable70 mm² copper, R ≈ 0.32 Ω/km, X ≈ 0.08 Ω/km
R cos φ + X sin φ0.32 × 0.88 + 0.08 × 0.475 ≈ 0.3200.32 × 0.3 + 0.08 × 0.954 ≈ 0.172
Voltage drop1.732 × 128 × 0.12 × 0.320 ≈ 8.5 V (2.0%)1.732 × 770 × 0.12 × 0.172 ≈ 27.5 V (6.6%)

The running drop of 2% passes a 3% limit. During a direct-on-line start the cable alone drops about 6.6%. On a grid supply that is usually acceptable. On a generator, the alternator’s own transient dip adds to it, so the total at the motor can approach 20% or more. If the motor struggles to accelerate, a larger cable, a shorter route or a reduced-voltage starter is needed. See motor starting and voltage-dip studies.

Step 3: short-circuit withstand

S ≥ I × √t ÷ k · k ≈ 115 for copper in a PVC cable, ≈ 143 for copper in an XLPE cable

For the same 70 mm² copper XLPE cable, the maximum fault current it can survive for 0.2 s is 143 × 70 ÷ √0.2 ≈ 22 kA. Close to a large transformer, with a breaker that takes longer to clear, this check can govern even when current rating and voltage drop are comfortable.

Do not size a generator or motor cable on current rating alone. A cable that runs cool can still drop enough voltage at starting to stall the motor, or fail to survive a fault. Check all three before ordering.

What changes on generator supply

  • Weaker source. Generator fault current is lower and decays, so protection clears more slowly. Check that the breaker still operates on the generator’s fault current. See generator short-circuit current.
  • Voltage dip budget. Cable drop at starting adds to the alternator’s transient dip. Keep the generator-to-panel cable short and generously sized.
  • Long rental connections. Temporary cables to a rental set’s position can be long; size them for starting, not just for running current.
  • Parallel runs. Large sets use several cables per phase. Equal lengths and routing are essential so that current shares evenly. See the breaker, changeover and cable size chart.

When screening is not enough

Use a full calculation to the applicable standard for parallel cables, buried or high-ambient routes, harmonic-rich loads, large motors and high fault levels. See cable sizing and voltage-drop studies.

Cable screening worksheet

ItemValue
Load (kW), voltage, power factor, efficiency 
Design current (A) and protective device setting (A) 
Route length (m) and installation method 
Correction factors (ambient, grouping, installation) 
Voltage drop running (%) and at starting (%) 
Fault current (kA), clearing time (s), minimum area (mm²) 
Size chosen and governing check 

Worked example: a generator feeder to the changeover (illustrative)

A 250 kVA set at 415 V has a full-load current of 250000 ÷ (1.732 × 415), or about 348 A. The set stands 40 m from the changeover panel, with the cable on an outdoor tray that reaches 45 °C in summer, grouped with two other circuits.

CheckWorkingResult
Design current250 kVA at 415 Vabout 348 A
Corrections0.87 for 45 °C × about 0.8 for groupingabout 0.70
Required tabulated rating348 ÷ 0.70about 500 A
CandidateTwo runs of 120 mm² copper XLPE per phase, equal length and route, checked against the maker table for this installation
Running voltage drop1.732 × 348 × 0.04 × (0.098 × 0.8 + 0.04 × 0.6) for two runs in parallelabout 2.5 V, well under 1%

In this case the current rating governs, not the voltage drop, because the run is short and heavily loaded in a hot tray. The values in the working, 0.098 and 0.04 ohms per km, are typical figures for one 120 mm² copper cable, halved for two equal runs in parallel; the maker table and the installation method decide the final size.

Aluminium cables and terminations

Aluminium has about 61% of the conductivity of copper, so an aluminium cable needs roughly one size larger, about 1.6 times the cross-section, for the same resistance. It is lighter and lower in cost, and widely used for large feeders. The weak point is the termination: aluminium forms an oxide layer and creeps under pressure, so it needs lugs made for aluminium or bimetallic lugs where it meets copper busbars, the correct crimping tool and die, contact compound where the lug maker specifies it, and terminations retorqued and checked by thermal imaging after the first weeks of load.

Earth fault loop on long runs

A long cable raises the impedance of the earth fault loop, so the current that flows in an earth fault at the far end may be too low to trip the protective device within the required time. This is a separate check from voltage drop and short-circuit withstand. It is most often the governing check for long final circuits and for circuits fed from a generator, whose fault current is lower than the grid. Where the loop impedance is too high, the remedies are a larger protective conductor, a larger cable, a protective device with a lower magnetic setting where coordination allows, or a residual current device.

Harmonics and the neutral

Loads with electronic power supplies, such as computers, LED lighting and drives with single-phase front ends, draw triplen harmonic currents that add in the neutral rather than cancelling. In an office or data room the neutral current can approach or exceed the phase current. A full-size or oversized neutral is then specified, and the phase conductors are derated for the extra heating from harmonic current, using the factors in the cable standard.

Making parallel runs share the current

Current divides between parallel cables in proportion to their impedance, so runs of different length, size or route do not share equally, and one cable can overload while the others run cool. Parallel runs are therefore the same size, material, length and type, terminated in the same way, and laid so that each run carries one conductor of each phase in a group, which keeps the reactance of each run equal. A clamp meter reading on each run at full load at commissioning confirms the sharing.

Common mistakes

  • Choosing the size from current rating alone.
  • Ignoring grouping and summer ambient.
  • Forgetting the motor-start drop, especially on generator supply.
  • Skipping the short-circuit withstand check.
  • Unequal parallel runs that overload one cable.

What to send us

Send the load, voltage, route length and installation method, the largest motor and its starter, and whether the circuit runs on generator supply. WhatsApp 98852 01608 or use the enquiry form.

Evidence note. Cable data and correction factors in the examples are typical values for illustration. Final selection must use the cable maker’s tables and the applicable standard.

Questions engineers ask

Which check usually governs a short generator cable?

Usually the current rating after correction for ambient temperature and grouping. In the 250 kVA example a 40 m run in a hot, grouped tray needs about 500 A of tabulated rating for a 348 A load, while its running voltage drop is well under 1%. Long runs are more often governed by voltage drop.

Why can a long cable stop earth-fault protection from working?

A long cable raises the impedance of the earth fault loop, so a fault at the far end may draw too little current to trip the protective device in the required time. This is checked separately, especially on generator supply, and fixed with a larger protective conductor, a different device setting or an RCD.

What voltage drop is acceptable?

Codes and equipment set the limits; many designs aim for about 3 to 5% at the load end at steady full load, split between the main feeder and the final circuit. Check the applicable code and the voltage tolerance of the equipment, and treat motor starting as a separate, larger allowance that depends on the motor and its supply.

Why does motor starting need a separate check?

Starting current is several times the running current at a low power factor, so the drop is much larger. A drop that is acceptable while running can stall the motor or drop out contactors during the start, and on generator supply the cable drop adds to the alternator dip, so the starting case is checked on its own.

Copper or aluminium?

Both are used. Aluminium needs about 1.6 times the cross-section of copper for the same resistance and needs careful terminations with lugs suited to aluminium, the correct crimping tools and checks after the first weeks of load. Choose by cost, space, weight, termination arrangements and the applicable code.

Is this enough for a final design?

No. It is a screening tool for current rating and steady-state voltage drop. Final design follows the cable standard and checks short-circuit withstand at a verified fault level and clearing time, motor-starting voltage drop, the earth fault loop, harmonics and the installation details, using the cable maker data.

Values are illustrative. Use manufacturer cable data and applicable standards for design.