In short. A UPS protects the instant; a generator protects the duration. The UPS bridges the seconds between a supply failure and the generator taking over, and conditions the supply while it runs. Its design follows from four decisions: how critical the load is, how long the batteries must last, how much redundancy is needed, and how it will work with the generator behind it. A UPS with no generator is a delayed shutdown, not continuity.
Who this page is for: For IT, hospital, laboratory and facility engineers planning or reviewing UPS systems, and for anyone deciding how a UPS and generator should work together.
Key facts
- Check both ratings: UPS kVA ≥ load kW ÷ load power factor, and load kW ≤ UPS kW rating.
- UPS input power = output power ÷ efficiency + battery charging power; the losses become room heat.
- Battery runtime covers generator start, transfer and a margin, not the whole outage.
- Battery voltage is not battery capacity; prove capacity with load tests and trend internal resistance.
- Redundancy needs independent failure paths: N+1 survives one module failure, 2N survives a whole path.
- Size the generator for the UPS input, not its output. See UPS and DG integration.
From milliseconds to hours
| Time after a mains failure | What carries the load | What must be right |
|---|---|---|
| First milliseconds | UPS inverter, from the battery | Online topology for critical loads; healthy battery |
| First ten seconds or so | UPS battery while the generator starts | Generator start readiness; AMF settings |
| Next minutes | Generator through the UPS rectifier, with walk-in | Generator sized for UPS input, harmonics and recharge |
| Hours | Generator | Fuel autonomy and a refill plan |
Decision map
| Decision | Options | See |
|---|---|---|
| Topology | Online double conversion for critical loads; line-interactive for less critical ones | Online UPS |
| Scale | Single-phase, three-phase, industrial | Three-phase UPS |
| Redundancy and growth | Modular, parallel, 2N | Modular UPS |
| Batteries | VRLA or lithium-ion; monitoring | Batteries |
| Bypass | Static and maintenance bypass | Bypass |
Worked example: sizing a server-room UPS (illustrative)
A server room has equipment nameplates totalling 24 kW, a measured typical load of 15 kW at a power factor near 0.9, and expected growth of 30% over three years.
| Step | Working | Result |
|---|---|---|
| Planning load | 15 kW × 1.3 | 19.5 kW |
| Required kVA | 19.5 ÷ 0.9 | About 21.7 kVA: a 30 kVA class unit, checked against its kW rating |
| Battery energy for 10 minutes | 19.5 kW × 10 ÷ 60 ÷ 0.94 inverter efficiency | About 3.5 kWh delivered from the battery |
| With ageing and design margin of about 25% | 3.5 × 1.25 | About 4.3 kWh, confirmed against the maker’s discharge tables |
| Input power at full planning load | 19.5 ÷ 0.94 | About 20.7 kW plus battery charging |
| Heat to remove | 20.7 − 19.5 | About 1.2 kW, plus battery-room heat |
The nameplate total of 24 kW would have pushed the design toward a larger unit than needed. Measured load with an honest growth figure gives a better result. Ten minutes of battery is ample to cover a generator start and transfer with margin; much longer runtimes add cost and space but little continuity, unless the generator start is unreliable or the load needs time for an orderly shutdown.
Battery mindset
A battery bank can show correct float voltage and still collapse under load. Capacity falls with age and heat: a VRLA battery kept well above its rated temperature loses life quickly. Test under load at intervals, trend internal resistance or conductance, keep the battery cool, and replace strings before they reach end of life.
Do not judge a UPS battery by its voltage alone. The first real test of an untested bank is usually the outage it fails in. Load-test it, and keep a record.
Redundancy architecture
| Architecture | Example for a 40 kW load | Survives | Cost and complexity |
|---|---|---|---|
| Single UPS | One 50 kVA unit | Nothing beyond its own bypass | Lowest |
| N+1 modular or parallel | Three 25 kVA modules where two carry the load | One module failure | Moderate |
| 2N | Two independent 50 kVA systems feeding dual-corded loads | A whole path failure, including its distribution | High |
Redundancy is only real if failure paths are independent. Two UPS units sharing one battery bank, one input breaker or one output board share a single point of failure. See N, N+1 and 2N systems.
Room and environment
- A cool, clean, dry room with service clearance.
- Battery temperature controlled, since life falls with heat.
- Fire detection and safe battery handling.
- Floor loading checked for battery cabinets.
- Cable routes planned for bypass and future growth.
Operating practices
- Test transfer to battery periodically, with the load owners informed.
- Record UPS and battery readings, and trend them.
- Keep firmware versions and settings on record.
- Train staff on bypass procedures before they are needed.
- Test the UPS and generator together, on load. See load bank testing.
UPS planning worksheet
| Item | Value |
|---|---|
| Measured load (kW) and power factor | |
| Growth allowance and planning load (kW) | |
| UPS kVA and kW rating chosen | |
| Runtime needed (minutes) and battery energy (kWh) | |
| Redundancy: single, N+1 or 2N | |
| Generator behind the UPS: kVA and start time |
What the three UPS types actually pass to the load
UPS units are classified by what their output depends on, and the classification says more than the marketing names. In the international UPS performance standard the three classes are written by their initials. A VFD unit — voltage and frequency dependent — passes the mains straight through and starts its inverter only when the mains fails; this is the offline or standby type.
A VI unit — voltage independent — corrects the voltage with a tapped transformer or a bidirectional converter but passes the mains frequency through; this is the line-interactive type. A VFI unit — voltage and frequency independent — rebuilds the output from DC all the time, so neither the mains voltage nor its frequency reaches the load; this is double conversion.
| Class | Common name | Mains disturbances passed to the load | On mains failure | Typical use |
|---|---|---|---|---|
| VFD | Offline, standby | Voltage changes, frequency changes, most transients | Transfer in a few milliseconds | Single desktop computers, small domestic loads |
| VI | Line-interactive | Frequency changes; voltage corrected in steps | Short transfer, usually under 10 ms | Small offices, network cabinets, loads on a reasonable supply |
| VFI | Online, double conversion | None while on the inverter | No transfer; the battery is already on the DC bus | Servers, medical, process control, anything on a generator |
The last column of the VFI row is the practical reason double conversion dominates critical power in this region. A line-interactive unit fed from a generator passes the generator’s frequency movements straight to the load and may transfer to battery every time the frequency dips on a load step. A double-conversion unit isolates the load from them completely, at the cost of higher losses. Where the supply is good and the load tolerant, a line-interactive unit is a reasonable and efficient choice; where a generator is part of the system, it rarely is.
The output waveform is the other difference worth checking. Many small offline and line-interactive units produce a stepped approximation of a sine wave on battery, sometimes sold as a modified or simulated sine wave. Modern computer power supplies with power factor correction usually accept it, but motors, small transformers, some medical equipment and anything with a timing circuit derived from the supply may not, and can run hot, hum or misbehave. Double-conversion units produce a true sine wave at all times. Where a smaller unit is chosen, confirm that its battery-mode output is a sine wave if the load includes anything other than electronic power supplies.
Runtime does not scale in proportion to load
A battery delivers more total energy when it is discharged slowly than when it is discharged fast, so halving the load more than doubles the runtime. The effect is commonly described by an exponent in the relationship between load and runtime. With an exponent of 1.2, which is in the usual range for lead-acid batteries at UPS discharge rates, a battery giving 10 minutes at full load gives about 23 minutes at half load and about 53 minutes at a quarter load.
| Load, as a share of the full-load figure | In proportion (exponent 1.0) | Exponent 1.2 | Exponent 1.3 |
|---|---|---|---|
| 100% | 10 min | 10 min | 10 min |
| 50% | 20 min | about 23 min | about 25 min |
| 25% | 40 min | about 53 min | about 61 min |
The working is the full-load runtime multiplied by the load ratio raised to the exponent: for half load, 10 × 21.2. The exponent varies with the battery type, age and temperature, so the table is a guide to the shape, not a substitute for the maker’s runtime table for the actual battery. It does explain two things often seen on site: a UPS lightly loaded runs far longer than its rated autonomy suggests, and the same UPS, after load has been added over the years, runs far shorter than a simple proportion would predict.
Choosing final-circuit breakers that the inverter can trip
An inverter cannot deliver the fault current a transformer can. It limits its own current to protect its transistors, typically to a few times its rating for a short time, and if a fault downstream needs more current than that to trip its breaker, the breaker does not trip quickly. The UPS then either transfers to bypass, where the mains clears the fault, or, with no bypass available, shuts down and drops every load it feeds.
The check is simple arithmetic. A single-phase 20 kVA output at 230 V is rated about 87 A. If the inverter can deliver about 2.5 times that for the duration of a fault, about 217 A is available. A type C miniature circuit breaker trips instantly at up to 10 times its rating, so it needs up to 10 times its rating to be sure of tripping: a 20 A type C breaker, needing up to 200 A, trips on inverter current alone; a 32 A one, needing up to 320 A, may not.
Use the inverter’s actual short-circuit figure from its datasheet, keep the final-circuit breakers small, and treat any circuit that cannot be cleared on the inverter alone as dependent on the bypass — which, on generator or with the bypass unavailable, it cannot rely on.
The documents a critical-power site should hold
Every outage is easier to recover from, and every engineer’s visit quicker, when the site holds a small set of current documents in one place: the single-line diagram as built; the settings of every UPS, transfer switch and generator controller; the battery records with the last discharge test; the load readings by circuit; the procedures for transfer to maintenance bypass and back; and the contact details and response times for every service provider. Kept current and kept beside the equipment, they turn a night-time fault into a procedure rather than an investigation.
Common mistakes
- Sizing from nameplates instead of measured load.
- Checking kVA but not the kW rating.
- Buying long battery runtime instead of a reliable generator.
- Shared single points of failure in a redundant design.
- Never testing the UPS and generator together.
What to send us
Send the load list with criticality, measured load if available, the runtime you need and details of any generator. WhatsApp 98852 01608 or use the enquiry form.
Evidence note. Figures are illustrative; the UPS and battery makers’ data govern final sizing.
Questions engineers ask
Why does a UPS run much longer at half load?
Because a battery delivers more total energy when discharged slowly. Runtime does not scale in proportion: with an exponent of about 1.2, typical of lead-acid batteries, a battery giving 10 minutes at full load gives about 23 minutes at half load and about 53 minutes at a quarter load. The same effect means a UPS that has had load added over the years runs much shorter than a simple proportion predicts. Use the maker runtime table for the actual battery.
Which breakers can a UPS inverter trip on its own?
Only small ones, because an inverter limits its fault current to a few times its rating. A 20 kVA single-phase output is rated about 87 amps; at about 2.5 times, about 217 amps is available. A type C breaker needs up to 10 times its rating to trip instantly, so a 20 amp type C trips on inverter current alone while a 32 amp one may not. Keep final-circuit breakers small and check against the inverter short-circuit figure.
How much runtime?
Enough to cover the generator start, the transfer and a margin, including a failed first start attempt. Where there is no generator, runtime is set by how long the loads must keep running or shut down safely. Size it at the end-of-life battery capacity and the expected room temperature, not new battery figures.
Online or line-interactive?
Online double-conversion for critical loads that need a clean, continuous supply with no transfer break. Line-interactive units suit less critical loads where a very short transfer is acceptable, at lower cost and with less heat. The choice follows the load tolerance to breaks and voltage variation.
Do I need a bypass?
For maintenance and fault resilience, yes. A static bypass transfers the load automatically when the UPS faults or is overloaded, and an external maintenance bypass lets the UPS be isolated for service with the load still supplied. Both are interlocked so the sources can never be connected wrongly.
Is UPS enough alone?
Only for short outages, because battery runtime is limited and expensive to extend. For longer outages a generator with an automatic mains failure panel takes over, and the UPS bridges the gap while it starts and transfers. Size the generator for the UPS input, including battery recharge and its harmonic effect.
Values are illustrative. Use manufacturer data.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.