Rental Transformers

How rental transformers fit into temporary power systems, how to rate the generator for inrush, and what to check on vector group, impedance and protection.

In short. A rental transformer is needed when the temporary generator produces one voltage and the site or load needs another, typically 415 V generation feeding an 11 kV or 6.6 kV network, or a medium-voltage rental plant stepping down to 415 V. Select it on kVA, voltages, vector group, impedance and protection, and check that the generator can energise it, because transformer inrush can exceed the generator’s transient capability even when the running load is small.

When a temporary power system needs a transformer

Most rental generators in India generate 415 V three-phase at 50 Hz, which matches the majority of factory, commercial and construction loads, so no transformer is needed. The exceptions should be recognised early, because a transformer changes the layout, cable sizes, protection and mobilisation plan.

In each case the transformer is part of the temporary plant and has to be rated together with the generator, switchgear and cables.

The selection data that matters

These parameters have to be fixed before a unit can be matched to a project.

ParameterWhy it matters on a rental jobTypical check
Rated kVASets the continuous load at site ambientCover peak temporary load with margin for 45 degrees Celsius summers
Primary and secondary voltage, tap rangeWrong tap means the load sees high or low voltage all dayConfirm the actual site voltage, not the nominal, and the direction of power flow
Vector groupDecides phase shift and whether a neutral is availableDyn11 is the common Indian distribution group; paralleling with an existing transformer needs the same group
Percentage impedanceSets fault level on the secondary and voltage regulation under loadLower impedance gives better regulation but higher fault current for the switchgear to clear
ProtectionHT fuse or breaker, Buchholz, winding temperature, earth faultProtection must suit the generator’s lower fault current, not only the utility’s

Energisation: the generator must survive the inrush

A transformer draws a magnetising inrush when it is switched on. The peak depends on the point on the voltage wave at closing and on residual flux in the core, and it is commonly several times rated current for a few cycles, decaying over a second or more. A grid absorbs this easily.

A rental generator has a much higher source impedance, so the inrush produces a deep voltage dip that the AVR and governor must recover from. A generator rated comfortably above the running load can still trip on under-voltage, see the inrush as a fault, or sag long enough to drop contactors already connected. There are three ways to manage this.

Where the transformer is large relative to the generator, an energisation study is worthwhile. See transformer energisation and inrush studies for how that is done.

Protection and earthing change when the source is a generator

Utility fault current at an industrial 11 kV bus can be 10 kA or more. A rental generator feeding the same bus through a step-up transformer typically delivers around three times its rated current into a fault, decaying quickly unless the alternator has permanent-magnet excitation. Relays set for utility fault levels may not operate, or may operate too slowly, on generator supply, so settings on both sides of the rental transformer should be reviewed for the generator case before energising.

Neutral earthing also needs a decision. A Dyn11 step-down transformer creates a new neutral on its secondary, which must be earthed at the transformer with the electrode resistance measured, while the generator’s own neutral on the delta side is treated separately. The rules are covered in earthing and neutral grounding, and the switching and interlocking in ATS and changeover switchgear engineering.

Cables and layout around a rental transformer

A transformer adds two cable systems. The LV side carries the full current, around 1391 A for 1000 kVA at 415 V, which means three or four single-core cables per phase and attention to current sharing. The HT side carries roughly 52 A for the same 1000 kVA at 11 kV through one three-core XLPE cable with heat-shrink terminations made by an HT-competent jointer, because a failed termination under load is a serious arc hazard. See temporary power cables for sizing practice.

An oil-filled unit needs a level pad, a spill bund, clearances from buildings and exhaust, and a barricade where HT terminals are exposed. Crane access and ground bearing for a 3 to 5 tonne unit should be confirmed at the site survey, not on delivery day.

A worked illustration

A pharmaceutical unit near Hyderabad must take its 1000 kVA, 11/0.415 kV transformer out for a ten-day overhaul (illustrative). The shutdown load is about 450 kVA. Because the LT board can be fed directly at 415 V with the transformer isolated, no rental transformer is needed and a 625 kVA set through a temporary changeover carries the load with starting margin. Had the work been on the LT board, with other substations fed through the HT ring, a step-up transformer, HT breaker and a larger generator sized for energisation would have been in scope. The asset being isolated, not the load, decides whether a transformer is required.

Selecting a temporary step-up transformer (illustrative)

A factory’s 11 kV incoming transformer is out for repair, and its 11 kV ring of plant transformers must be kept alive at reduced load. Two 1250 kVA generator sets at 415 V feed a step-up transformer. The selection data is set out below.

ItemValue or decision
Load to be carriedAbout 1600 kW, 2000 kVA at 0.8 power factor
GenerationTwo 1250 kVA sets in parallel at 415 V, 2500 kVA total
Transformer rating2000 kVA, 415 V to 11 kV
Vector group and earthingChosen so the 11 kV system has a defined earth for protection
LV currentAbout 2780 A at 2000 kVA
HV currentAbout 105 A at 2000 kVA
EnergisationInrush checked against the two sets; energised with the sets running before load is added

The LV current comes from 2,000,000 ÷ (1.732 × 415) and the HV current from 2,000,000 ÷ (1.732 × 11,000). The contrast explains why long runs are made at 11 kV: one HV cable carries what would need many parallel LV cables.

Checks before energising

  1. Insulation resistance of windings and cables tested and recorded.
  2. Tap position set for the expected voltage at the load.
  3. Oil level and temperature indicators checked on oil-filled units, with the bund in place.
  4. HV protection relay settings entered for generator fault levels and tested.
  5. Earthing of the transformer tank, neutral and HV system measured.
  6. Phase sequence confirmed so motors on the 11 kV side run the right way.

During the temporary period

Transformer loading, oil or winding temperature, and the voltage at the far end of the HV network are recorded each shift. The generator sets are monitored for the reactive load the transformer and the plant draw, because a lightly loaded transformer can make the load look different to the voltage regulators. When the permanent transformer returns, the temporary transformer is de-energised only after load has been moved, and its connections are removed under the same permit system used to install them.

How Reddy Generators approaches HV temporary power

Generator sets below 1250 kVA generate at 415 V, so any connection to an 11 kV network goes through a step-up transformer with its own HV switchgear and protection. Each such arrangement is engineered and confirmed for the specific project, including the availability of the transformer and HV equipment, rather than offered as a standard item.

Common mistakes

What to send us

Send the single-line diagram showing the incoming supply, the asset being isolated and the proposed temporary connection point, nameplate photographs of the existing transformer, and the load list or maximum demand records for the outage period. Add site photographs of the proposed generator and transformer positions and the crane access. With these we can confirm whether a transformer is needed at all and size the generator for energisation rather than running load. Send a generator rental enquiry or see transformer sizing for the calculation background.

Questions engineers ask

What current flows on each side of a 2000 kVA step-up transformer?

About 2780 A on the 415 V side and about 105 A on the 11 kV side at full rating. That contrast is why long runs are made at 11 kV: a single HV cable carries what would need many parallel LV cables, with far less voltage drop and copper over the same distance.

What is checked before energising a temporary transformer?

Insulation resistance of windings and cables, the tap position, oil level and temperature indicators on oil-filled units with the bund in place, HV relay settings for generator fault levels, earthing of the tank, neutral and HV system, and phase sequence so motors on the HV side run the right way.

Can a 415 V rental generator feed my 11 kV plant?

Yes, through a step-up transformer with its own HT breaker and protection. The generator must be rated for the transformer inrush, the relay settings must be reviewed for generator fault levels, and the DISCOM incomer must be isolated and locked out so there is no possibility of back-feeding the grid.

How much bigger than the transformer should the generator be?

It depends on the transformer design and whether the core is energised cold. A generator kVA of 1.5 to 2 times the transformer kVA is a reasonable planning assumption for dead energisation, but the confirmed answer comes from the generator’s transient data and the transformer’s inrush figure, or from soft-start energisation that avoids the problem.

Oil-filled or dry-type for a temporary job?

Dry-type units are lighter, need no bund and suit short urban jobs. Oil-filled units suit longer industrial deployments where a bund and safe clearances can be provided. The choice also depends on the rating, the site fire rules, the space available and how often the unit will be moved.

Do I need to change the plant’s relay settings for the rental period?

Usually yes. Generator fault current is a fraction of utility fault current, so overcurrent elements set for the grid may not pick up. Temporary settings are calculated for the generator source, entered, tested and recorded, then restored to the permanent values when the normal supply returns.

Generators by rating

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.