In short. Planned-outage power is temporary generation installed for a scheduled shutdown of a transformer, HT panel, main LT board or DISCOM feeder. Because the date is known, the rental system can be surveyed, connected and tested before the permanent source is isolated. Decide which loads must stay on, choose a connection point that does not depend on the equipment being worked on, prove the generator under load beforehand and write the return-to-normal sequence before the outage starts.
The advantage a planned outage gives you
An emergency forces decisions in hours. A planned outage gives weeks. That time should be spent removing uncertainty: measuring the real load, walking the cable route, confirming the connection point and agreeing switching steps with everyone who will be on site. In our experience the outages that go badly are rarely let down by the generator. They fail because the temporary supply was connected to a board that was itself part of the work, or because nobody had decided which loads could be left off.
Start with what the outage removes
The first question is which asset is being isolated, because that decides where temporary power can connect.
| Work being done | What becomes unavailable | Usual temporary connection |
|---|---|---|
| DISCOM feeder or HT breaker maintenance | Incoming supply only | Existing DG changeover or LT incomer, with HT isolated and locked |
| Distribution transformer overhaul | Transformer and its LT incomer | LT main board, downstream of the transformer breaker |
| Main LT switchboard work | The board itself and its changeover | Directly to sub-boards or critical feeders, bypassing the main board |
| Permanent generator replacement | Standby source only | Rental set into the existing DG incomer or ATS |
If the main switchboard is under maintenance, the normal DG connection point disappears with it. The temporary design must not depend on any switchgear that is intentionally out of service. Transfer arrangements are covered in rental ATS.
Decide the loads, then size
List every load on the affected boards and classify it: must stay on, may stay on if capacity allows, and will be off. Process cooling, fire systems, server rooms, cold rooms and safety lighting usually fall in the first group; non-essential air conditioning and production lines often fall in the third. Measure maximum demand from the energy meter or a logger over a representative week rather than adding nameplate ratings. Then size the generator for the retained running load plus the largest motor start or block load at reconnection. The power requirement configurator helps structure this list.
Install, test and verify before isolation
Where the site allows, the rental set should be delivered, connected and run under load a day or more before the outage, ideally on a load bank or on a part of the real load that can be switched safely. This confirms phase rotation at the connection point, cable terminations, protection settings and fuel arrangements while the permanent supply is still there as a fall-back. Agree a written switching programme covering each isolation, the lock-out points, the order of transfer and the person authorised for each step. Test equipment options are on load bank rental.
During the outage
Restore loads in a staged sequence rather than all at once, largest motors first while the generator is lightly loaded, then the remaining groups at intervals. Keep someone responsible for the generator throughout: reading load per phase, coolant temperature and fuel level at fixed intervals. If the work overruns, the fuel and hire plans should already state how an extension is handled; see rental fuel tanks.
Returning to normal supply
The return sequence deserves the same care as the start. Confirm the permanent asset has been tested and released by the team that worked on it, check phase rotation on the restored supply before any load is transferred back, and decide whether the return will be a brief break or a synchronised changeover. Most sites accept a short planned break, which keeps the switching simple. Remove temporary connections, restore any changed relay settings and record the final state.
A planned outage timeline (illustrative)
A planned outage goes smoothly when every step has a date. The timeline below is typical for a transformer overhaul at an LT-connected factory, with the outage on day zero.
| When | Step | Output |
|---|---|---|
| Three weeks before | Site survey, load measurement, connection point agreed | Retained load list and single-line sketch |
| Two weeks before | Set and cable sizes fixed, switching programme drafted | Equipment list and draft programme |
| One week before | Programme reviewed with the DISCOM, contractor and site team | Signed switching programme and contact list |
| Two days before | Set delivered, cables laid, connection made to the agreed point | Installation check sheet |
| Day before | Load test on the retained loads, fuel filled, alarms tested | Test record with voltage, frequency and load |
| Day zero | Isolation, transfer to rental supply, work begins | Running log every hour |
| Restoration | Permanent supply proved, load returned, set removed | Completed programme and handback note |
What a switching programme contains
The switching programme is the single document everyone follows on the day. It lists each step in order, the device to be operated, who operates it, who confirms it, and the check to be made before the next step. It includes the isolation and locking of the equipment under work, the point at which the rental set takes the load, the order in which loads are reconnected, and the full return-to-normal sequence. Every person on the switching list has a copy, and the programme is followed step by step even when the work runs smoothly, because skipped steps are how back-feeds and dropped loads happen.
Fuel and running hours during the outage
Fuel is planned from the measured retained load and the expected outage length, with a margin for overruns, which are common on transformer and HT work. A set carrying 200 kW for a 36-hour outage delivers 7200 kWh; at around 0.27 litres per kWh that is close to 1950 litres, so the base tank and any external tank are planned to cover it with a refill arranged in advance. On outages longer than the service interval, an oil and filter change is planned into the programme, since our standard is every 250 to 500 running hours or six months, whichever comes first.
Risks to cover before the date
- Overrun: what happens if the work takes a day longer, including fuel and operator cover.
- Generator fault: which loads drop first and how they are protected, for example by UPS or a second set.
- Back-feed: how the rental set is kept separate from the isolated equipment and the DISCOM network.
- Protection: whether existing breakers will clear a fault on the lower fault level of a generator supply.
- Weather: cable routes and set positions protected from monsoon water.
Classifying loads for a planned outage (illustrative)
| Load | Measured demand | Class |
|---|---|---|
| Process cooling and pumps | 85 kW | Must stay on |
| Fire systems and safety lighting | 15 kW | Must stay on |
| Server room and offices | 40 kW | Must stay on |
| Cold store | 60 kW | May stay on if capacity allows |
| Production lines | 220 kW | Off during the outage |
| General air conditioning | 90 kW | Off during the outage |
The must-stay-on group totals 140 kW, and with the cold store it reaches 200 kW, or 250 kVA at 0.8 power factor. A 320 kVA set carries the full retained list at about 78% and leaves margin for the pumps restarting after transfer, while a 250 kVA set would have to drop the cold store. Writing the classes down before the day turns a stressful decision into a line in the switching programme.
Returning to permanent supply without surprises
The return to normal is where many planned outages go wrong, because everyone is tired and the work is finished. The permanent source is proved before any load is moved: the repaired transformer or board is tested, the protection is restored and the phase rotation is checked against the rental supply so motors do not run backwards.
Loads are then moved back in the same groups used during the outage, the rental set is run down on no load for its cool-down, and its isolation is confirmed before cables are removed. A short handback note records the time of each step, the final readings and anything found during the work that needs follow-up, such as a weak cable or an alarm that tripped during the outage.
Planning the return sequence at the same time as the outage itself, and printing it on the same switching programme, is the single habit that prevents most incidents on the last day.
Keeping the running log, the test record and the handback note together gives the site a ready template for the next planned outage, which is often only a year or two away when transformers and boards follow a maintenance cycle.
Common mistakes
- Connecting the rental set to the board that is being worked on. The temporary supply is lost the moment the work starts.
- Sizing from the sum of nameplates. The generator is larger and more lightly loaded than needed, or the real starting load trips a smaller set.
- Skipping the pre-outage load run. Reversed phase rotation or a loose termination appears with the whole plant waiting.
- Leaving the return sequence undefined. Loads come back at once on the restored supply and protection trips again.
What to send us
Send the outage date and duration, the single-line diagram with the equipment being isolated marked, the list of loads that must stay on with maximum demand readings, and photographs of the proposed connection point and generator position. Send a generator rental enquiry early so the survey and pre-outage test can be scheduled. For the plant-wide case see shutdown and turnaround power.
Questions engineers ask
What is a switching programme for a planned outage?
A step-by-step document listing each switching operation in order, the device, who operates it, who confirms it and the check before the next step. It covers isolation and locking of the equipment under work, transfer to the rental set, the order of reconnecting loads and the full return to normal supply.
How much fuel does a planned outage need?
Multiply the retained load in kW by the outage hours to get kWh, then by roughly 0.27 litres per kWh at good loading. A 200 kW load for 36 hours is 7200 kWh, close to 1950 litres. Add margin for overruns, which are common on transformer and HT work, and arrange refills in advance.
How early should I book a generator for a planned outage?
Two to three weeks is comfortable for a typical LT connection, and longer if a transformer, HT work or several sets are involved. The time is used for the survey, load measurement, cable planning, the switching programme and a pre-outage load test, not only for arranging the set itself.
Can the changeover to rental power be done without a break?
Only with synchronising equipment and protection that allow the rental set to parallel briefly with the existing source, which also needs DISCOM permission where the grid is involved. Most planned outages accept a short break of a few seconds to minutes, protected by UPS for the loads that cannot tolerate it.
What size generator do I need for my outage?
One sized for the retained running load plus the largest starting event, not the whole plant. Measured maximum demand on the loads that must stay on is the right starting point, with margin for motor starting and for loads reconnected in groups after the transfer to the rental set.
Who operates the generator during the outage?
That is agreed in the scope. It can be the rental supplier technician, the site electrical team after a handover, or both on shifts. What matters is that one named person is responsible at all times, knows the switching programme and keeps the hourly running log of load, fuel and alarms.
Generators by rating
- Under 15 kVA generators
- 15–50 kVA generators
- 50–125 kVA generators
- 125–250 kVA generators
- 250–500 kVA generators
- 500–1000 kVA generators
- 1000–2000 kVA generators
- 2000 kVA and above generators
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.