Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

Rental ATS

How to arrange a rental ATS or manual changeover for temporary generator backup, selected by voltage, poles, fault duty, neutral and operating sequence.

In short. A rental generator only becomes standby power when there is a safe, defined way to move the load from the normal source to the generator and back. A rental ATS or interlocked manual changeover provides that path. It must be selected by voltage, current, number of poles, fault withstand, neutral arrangement and the operating sequence, never by current rating alone. AMF logic on the generator starts the engine; it does not transfer the load.

Starting the generator is only half the sequence

A common assumption is that a rental set with an AMF controller provides automatic backup. AMF logic monitors the normal source and starts the generator when it fails. Something else must then disconnect the load from the failed supply, connect it to the generator, and reverse that when the normal supply returns, without ever connecting the two sources together. That is the job of the transfer equipment. The arrangement is simple to describe: normal source and rental generator each feed a transfer device, and the transfer device feeds the essential load. See the automatic transfer switches page for permanent ATS types.

Three separate functions

These may sit in one controller, but confusing them leads to weak temporary designs.

Selection inputs, not just amperes

InputWhy it matters
Voltage and system415 V three-phase four-wire or other; sets insulation and control supply
Continuous currentMust carry the real load including any growth during the hire
Number of polesThree-pole or four-pole, depending on whether the neutral is switched
Source configurationUtility plus generator, or generator plus generator
Fault dutyWithstand and close-on rating for the prospective fault current at that point
Neutral architectureWhere the neutrals are earthed and whether switching is needed to avoid parallel earth paths
Load typeMotor-heavy loads may need a delayed transition to let motor voltage decay
Operating sequenceTransfer and retransfer timing, test mode, manual override

“Load is 800 A, therefore use an 800 A ATS” is incomplete. A device can carry 800 A continuously and still be unsuitable if its fault withstand is below the site’s prospective fault current, if it is three-pole where the neutral arrangement needs four, or if it is rated for indoor use and sits in the rain. The ATS and changeover switchgear engineering guide covers these ratings.

Neutral switching and earthing

When a temporary generator has its own earthed neutral and the building’s transformer neutral is also earthed, an unswitched neutral creates two earth paths. Neutral current then divides between the neutral conductor and earth, which can cause earth-fault protection to trip or fail to detect real faults. A four-pole changeover that switches the neutral is the usual solution where the generator is a separately derived source. The right choice depends on the existing installation, so it must be checked on site; the earthing and neutral architecture page explains the options.

Manual or automatic transfer

Some projects suit an approved, interlocked manual changeover: a planned outage where a technician is on site, or a construction supply with no critical loads. Others need automatic operation because no one will be present when supply fails, or the load cannot wait. The engineering is the same; the difference is how transfer is initiated.

Timers that matter

Automatic transfer should not happen because a single voltage sample looks abnormal. A start delay of a few seconds distinguishes a brief DISCOM dip from a sustained failure. A retransfer delay keeps the load on the generator until the utility has been stable for several minutes, and a cool-down timer runs the set unloaded before stopping.

Total interruption on transfer (s) = start delay + engine start and stabilise time + transfer switching time

The start delay is the confirmation time set on the controller, start and stabilise time is the engine’s time to reach rated voltage and frequency, and switching time is the mechanical operation of the changeover. As an illustration (illustrative), 3 seconds of delay, 10 seconds to stabilise and under 1 second to switch gives about 14 seconds without supply. Loads that cannot tolerate that need a UPS.

Integrating with what exists

A rental changeover connects into the existing installation, so the design must account for what is being bypassed, replaced or maintained. During planned outages, do not design a temporary connection that depends on the switchgear being removed from service. Not every facility load should move to rental generation; the loads that transfer should match the generator’s rating and the operating plan. Commissioning should prove transfer, retransfer, phase sequence on both sources and interlock operation before the system is relied on.

Selecting a rental changeover (illustrative)

A clinic takes a 125 kVA rental set as standby while its own generator is replaced. The site is supplied by a DISCOM transformer with its neutral earthed at the transformer, and the clinic main board has a 200 A incomer. This is how the transfer device is chosen.

Selection inputSite valueDecision
Voltage and phases415 V, three phase and neutralDevice rated for 415 V
Set full-load current125 kVA at 415 V is about 174 AAt least the set current, and the board incomer rating of 200 A
Fault withstandFault level from the transformer side at the boardWithstand rating above that level, or protected by the upstream breaker
Neutral arrangementTransformer neutral earthed; rental set neutral earthed at the setFour-pole device so the neutral is switched with the phases
OperationClinic needs automatic transferATS with mains and generator sensing, interlocked
Interruption toleranceSome medical equipment cannot tolerate a breakUPS ahead of those loads; ATS covers the rest

The current figure comes from 125000 ÷ (1.732 × 415), about 174 A. Selecting the device by that number alone would miss the neutral, fault and interruption questions that decide whether the arrangement is safe.

Commissioning the rental transfer

  1. Check phase rotation on both sources at the transfer device before any load is moved.
  2. Prove the interlock: attempt to close the second source while the first is closed and confirm it is blocked.
  3. Set and record the timers: mains fail confirmation, generator warm-up, transfer, retransfer and cool-down.
  4. Simulate a mains failure by opening the incomer, and record the transfer time and voltage at the load.
  5. Restore mains, confirm retransfer after the set delay and the cool-down before the engine stops.
  6. Hand over with a one-page sheet showing the settings, the test results and who to call.

When a manual changeover is the right choice

An interlocked manual changeover is simpler, cheaper and often more appropriate for planned work, events and construction, where someone is always present and a short delay before transfer is acceptable. It still needs an interlock that makes it impossible to connect both sources together, a clear label showing which position is which, and a written switching procedure. Automatic transfer is chosen when nobody may be present when the mains fail, or when the loads need restoring within seconds.

Removing a rental transfer at the end of a hire

At the end of the hire the site is returned to its permanent arrangement in a planned sequence: the load is placed on the normal supply, the rental set is stopped after cool-down, the transfer device is isolated from both sources, and the permanent changeover or generator connection is restored and tested. The final test is the same mains-failure simulation used at commissioning, proving that the site’s own standby system works before the rental equipment leaves.

Short dips and nuisance transfers

Many DISCOM feeders in Telangana see brief dips and auto-reclose operations lasting a second or two. A rental ATS set with too short a confirmation delay starts the generator and transfers for every one of them, which wears the switchgear, interrupts loads twice and runs the engine cold for minutes at a time. A confirmation delay of a few seconds, chosen after looking at how the local supply behaves, avoids this while still transferring promptly for a real outage. The retransfer delay is set longer, so the site does not move back to a supply that fails again moments later.

Records that make the next hire easier

The commissioning sheet, the settings and the transfer test results are kept with the site’s electrical records after the hire ends. The next time a rental set is needed, whether for another generator overhaul or a planned outage, the connection point, the device rating and the timer settings are already known, and the arrangement can be prepared and proved far more quickly.

Common mistakes

What to send us

Send the incoming panel’s single-line diagram or photographs, the main breaker rating, the transformer kVA if known, the loads to be backed up, and whether someone will be on site to switch manually. Tell us how long the arrangement is needed and how quickly loads must be restored. Use the generator rental enquiry.

Questions engineers ask

How is a rental ATS commissioned?

Phase rotation is checked on both sources, the interlock is proved by trying to close the second source while the first is closed, the timers are set and recorded, a mains failure is simulated with the transfer time and load voltage recorded, and retransfer and cool-down are confirmed. A one-page sheet of settings and results is handed over.

Why does my rental ATS transfer for every short dip?

Its mains fail confirmation delay is too short for the local supply, which often sees brief dips and auto-reclose operations. A delay of a few seconds chosen after looking at the supply behaviour avoids needless starts and transfers, while the retransfer delay is set longer so the site does not return to a supply that fails again.

Can I connect a rental generator without an ATS?

Only through an interlocked manual changeover that prevents both sources being connected at once. Connecting a generator to a live panel without a transfer device risks back-feeding the DISCOM network, which endangers line workers and damages equipment. A manual changeover suits sites where someone is always present to operate it.

Should the rental ATS be three-pole or four-pole?

It depends on the earthing arrangement. If the generator neutral is earthed at the set and the transformer neutral is earthed too, a four-pole device that switches the neutral is usually needed, so earth-fault protection works correctly on both sources. Check the existing installation before deciding.

How long is the interruption during automatic transfer?

Typically 10 to 20 seconds, made up of the confirmation delay, the engine starting and stabilising, and the switching operation. Loads that cannot tolerate that interruption need a UPS ahead of them. The actual time is measured and recorded during commissioning with a simulated mains failure, and checked again whenever the settings change.

Who sets the ATS timers?

They should be set during commissioning to suit the behaviour of the local supply and the loads, then recorded on the handover sheet. Defaults rarely suit every site, especially where the DISCOM supply has frequent short dips, which a confirmation delay of a few seconds rides through.

Generators by rating

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.

CallWhatsAppEnquire