Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

Power Requirement Configurator

Configure a complete generator power requirement: running load, largest transient, voltage, continuity, site conditions, fuel autonomy and what each decides.

In short. A power requirement that can be engineered has eleven parts: the application, the location, the existing supply, the running load, the largest transient load, the voltage, phase and frequency, the continuity requirement, the site conditions, the fuel autonomy, any redundancy and whether the need is temporary. Configuring a requirement means writing each down with its source and uncertainty, so the generator, panel and installation are selected from evidence rather than a kVA guessed over the phone.

Send your enquiry

Fields marked * are required. Give a phone number or an email address, whichever you prefer.

Your details are used only to respond to this enquiry (privacy notice). Photographs, nameplates and documents can be shared by email or WhatsApp after we reply. Prefer to talk? Call 98852 01608 or WhatsApp us.

Why the requirement comes before the generator

The commonest sizing error in Indian industry is to add up the nameplates of everything on site, apply a round margin and buy that kVA. The result is a set that runs at a quarter load for life, or one that trips every time the largest motor starts because the total was right but the transient was never considered. A configured requirement separates those questions.

It states what the set must carry continuously, what it must survive momentarily, what the loads can tolerate during a transfer, and what the site will do to the set’s rating. The generator is the output of that work, and the detailed method is under generator sizing. What follows is the checklist of inputs and why each one changes the answer.

The eleven inputs and what each one decides

InputWhat to recordWhat it decides
ApplicationFactory, hospital, data hall, pump station, construction site, eventDuty class, acceptable interruption, applicable standards
LocationAddress, altitude, indoor or outdoor, urban or ruralDerating, noise limits, emission norms, access for delivery and service
Existing power systemDISCOM connection and contract demand, transformer rating, existing generators and panelsTransfer arrangement, paralleling scope, reuse of infrastructure
Running loadMeasured demand in kW and power factor, or a load list with diversityBase generator kW
Largest transient loadBiggest motor with starting method, UPS rating, transformer inrush, welding or medical imaging loadsAlternator size, voltage dip, step acceptance
Voltage, phase and frequency415 V three-phase or 230 V single-phase at 50 Hz; any 11 kV or 60 Hz needAlternator winding, transformer need, switchgear class
Continuity requirementWhich loads must never break, which accept 10 to 30 seconds, which can waitUPS, AMF timing, load shedding, number of sets
Site conditionsAmbient maximum, dust, humidity, space, ventilation, fuel delivery accessDerating, enclosure type, cooling, filtration
Fuel autonomyHours the set must run without refuelling, delivery lead timeTank size, day-tank arrangement, storage compliance
RedundancyN, N+1 or 2N expectation, maintenance coverNumber and size of sets, synchronising
Temporary power needDuration, start date, whether the load will growRent or buy, mobile or stationary set

Getting the load figures right

Two load figures carry most of the weight. The running load should come from measurement wherever a supply exists: a month of DISCOM maximum demand data or a week of logging on the main incomer is worth more than any nameplate list. Where the site is new, build a load list with realistic demand and diversity factors rather than connected load, following the method under load inventory. The transient figure is the largest single step the set will see, which is usually the biggest direct-on-line motor but can be a UPS switching on with discharged batteries, a transformer being energised or a bank of lights after a transfer.

For that step, record the kW, the starting method and whether it can be sequenced after the rest of the site is stable. A 55 kW motor started direct-on-line draws roughly six to seven times its full-load current for a second or two, and its effect on the alternator is covered under motor starting.

Sgen ≥ Prun / PF, checked against Sstart at the permitted voltage dip

Here Sgen is the generator rating in kVA, Prun is the running load in kW, PF is the load power factor, and Sstart is the starting kVA demanded by the largest transient. Worked example (illustrative): a workshop measures 180 kW running at 0.85 power factor, giving 212 kVA, so a 250 kVA set would carry the steady load at about 85%.

Its largest motor is 45 kW started direct-on-line, demanding around 300 kVA for a moment; whether the 250 kVA set holds voltage within the 15 to 20% dip the site accepts depends on the alternator’s transient reactance and must be checked against the manufacturer’s motor-starting data, and if not, a soft starter or a larger alternator frame is the answer.

Loads that need an engineering review

Writing the brief so it survives the quotation stage

A good requirement brief fits on a page and states, for every figure, whether it was measured, calculated from a list or assumed. It names the continuity consequence in plain terms: which production line stops, which ward is affected, how much product spoils per hour.

It states the fuel autonomy in hours and the delivery lead time, because that fixes the tank and the arrangement discussed under fuel tank sizing. It gives the site constraints that decide the physical form: the space available, whether the set must be inside a building, the distance to the nearest neighbour for noise, and how a lorry and crane will reach the position. And it says what is unknown. A brief that admits the running load is estimated and the largest motor is yet to be confirmed produces a quotation with those items flagged for verification, which is far safer than a quotation that quietly assumes them.

An example of a complete brief (illustrative)

InputExample entry
ApplicationStandby for a 60-bed hospital wing
Running loadAbout 180 kW, from a load list and meter readings
Largest motor and starter22 kW fire pump on its own supply; 15 kW chilled water pump with soft starter
Sensitive loadsUPS for theatres and ICU, about 40 kVA
Duty and hoursStandby, about 150 hours a year
SiteGround-floor plant room, maximum air temperature about 45 degrees Celsius
ConstraintsNoise limit at boundary, fuel storage for 24 hours

A brief like this lets equipment be sized and compared properly at the first attempt.

What changes by application

ApplicationExtra detail needed
HospitalsEssential load classes, transfer time limits, UPS loads
FactoriesMotor list with starting methods, process loads that cannot stop
Data roomsIT load, cooling, UPS type and redundancy
Construction sitesCrane and welding loads, duration, relocation plans
RentalDates, access, cable runs, fuel arrangement

How the brief is used

The running load and growth set the rating, the largest motor and starter check the transient response, sensitive loads check waveform quality, duty decides the rating type, and site conditions decide derating, enclosure and installation. Each input changes a specific decision, which is why leaving one blank usually means a question back before a sound proposal can be made.

What to attach with the brief

A load list or meter readings, photographs of the planned location and access route, any existing single-line diagram, and nameplate photographs of the largest motors. These attachments answer most follow-up questions before they are asked.

Common mistakes

What to send us

Send the completed requirement in whatever form you have it: a load list or metered demand data, the nameplate of the largest motor and any UPS, a note on voltage and phase, the site address with photographs of the proposed generator position, the hours of autonomy needed, and the continuity consequence of an outage. Mark anything you are unsure of. We will return a requirement summary with the generator range, panel and installation items it implies and the figures that still need confirming. Send your power requirement for engineering review.

Questions engineers ask

What does a complete generator requirement brief include?

The application, running load with its source, largest motor and starter, sensitive loads such as UPS, duty and yearly hours, site location and maximum air temperature, and constraints like noise limits and fuel storage. The illustrative hospital wing brief shows each entry filled in with a realistic value.

What extra details are needed for different applications?

Hospitals need essential load classes, transfer limits and UPS loads; factories need motor lists with starting methods; data rooms need IT load, cooling and UPS type; construction sites need crane and welding loads and duration; rentals need dates, access, cable runs and fuel arrangements for the whole hire.

How is each input in a requirement brief used?

Running load and growth set the rating, the largest motor checks transient response, sensitive loads check waveform quality, duty decides the rating type, and site conditions decide derating, enclosure and installation. A blank input usually means a question back before a sound proposal can be prepared.

What should be attached to a generator enquiry?

A load list or meter readings, photographs of the planned location and access route, any existing single-line diagram, and nameplate photographs of the largest motors. These answer most follow-up questions in advance and allow the equipment to be sized correctly first time, without repeated site visits.

How much margin should I add to the running load?

Enough to keep the set between roughly 50 and 80% loaded in normal operation, after allowing for confirmed expansion plans. A fixed 25% margin on top of connected load almost always produces an oversized set; a margin on measured demand is the right basis. Logged demand over a typical month is the best starting figure.

Do I need to specify power factor?

Yes. Generator sets are rated in kVA at 0.8 power factor, so a 250 kVA set delivers 200 kW at that figure and its engine is sized accordingly. A site at 0.95 power factor with power factor correction is engine-limited before it is alternator-limited, and the quotation needs to reflect that.

What if I do not know the largest motor?

Say so, and we will identify it on a site visit or from the motor control centre schedule. It is the figure most likely to change the generator size, so it should never be assumed. Note the motor kW, the starting method and what it drives, since a direct-on-line start needs a much larger set than a soft-started one.

Does a temporary requirement need the same detail?

It needs the same load and transient figures, because a rental set trips on an unanticipated motor start exactly as a purchased one does. It needs less on installation and more on access, cable lengths, fuel responsibility and duration. Fuel is on the customer account.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.

CallWhatsAppEnquire